Royal Fantasy Phase III
by Royal Fantasy Constructions Private Limited · Andheri, MumbaiAlso near Jogeshwari East, Mogra, Goregaon East
Possession date of Royal Fantasy Phase III: 30 June 2027, moved from 31 December 2019 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800009920, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Royal Fantasy Phase III?
How the possession date of Royal Fantasy Phase III has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800005128)
Reason the builder gave MahaRERA:
“Our under construction real estate project is getting delayed due to several reasons as follows: 1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend…” Read the full reason
“Our under construction real estate project is getting delayed due to several reasons as follows: 1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition for sale 2. Other reasons: • Contractor’s inability to complete scheduled phase due to shortage of labour faced by him. • Last year disruptions due to GST & demonetization implementations. • Non-availability of sand on time. 3. Default from contactors: • Contra…”30 June 2023
Extended at the builder's request (MahaRERA application EXT51800010335)
Reason the builder gave MahaRERA:
“1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability…” Read the full reason
“1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending. 6. Due to COVID Pandemic Factor, the construction was not completed within the project completion date.”30 June 2024
Extended at the builder's request (MahaRERA application EXT51800016975)
Reason the builder gave MahaRERA:
“1. Temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time 3. Default fr…” Read the full reason
“1. Temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time 3. Default from contractors 4. Outstanding receivable from buyers 5. Registration of some flats were still pending”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800024314)
Reason the builder gave MahaRERA:
“1. Work in progress in phase 3 is slow as compared to our schedule because we have to take utmost care of possession given to flat buyers in phase 1 close to the phase 3 building during construction activity. 2. The Flat buyers are not payi…” Read the full reason
“1. Work in progress in phase 3 is slow as compared to our schedule because we have to take utmost care of possession given to flat buyers in phase 1 close to the phase 3 building during construction activity. 2. The Flat buyers are not paying payments as per the schedule and we have to arrange funds from other sources every time which takes time.”30 June 2026
Extended at the builder's request (MahaRERA application EA03072501942)
Reason the builder gave MahaRERA:
“i) The project comprises three phases—Phase 1, Phase 2, and Phase 3—being developed on the same plot of land and includes two buildings: Dreamax Vega and Dreamax Height. Phase 1 has been successfully completed, Occupation Certificate (OC) h…” Read the full reason
“i) The project comprises three phases—Phase 1, Phase 2, and Phase 3—being developed on the same plot of land and includes two buildings: Dreamax Vega and Dreamax Height. Phase 1 has been successfully completed, Occupation Certificate (OC) has been obtained, and possession has been handed over to the respective allottees. Phase 2 is nearing completion. However, the progress of Phase 3 has been comparatively slower due to the necessity of exercising extreme caution during construction activities, as Phase 3 is in close proximity to the already occupied Phase 1. This precaution is being taken…”30 June 2027
Extended at the builder's request (MahaRERA application EA26062621549)
Reason the builder gave MahaRERA:
“The project completion was delayed due to the need for additional safety precautions during construction, as Phase 3 is located adjacent to the occupied Phase 1, to ensure the safety and comfort of residents. Further, irregular payments by…” Read the full reason
“The project completion was delayed due to the need for additional safety precautions during construction, as Phase 3 is located adjacent to the occupied Phase 1, to ensure the safety and comfort of residents. Further, irregular payments by certain allottees affected the project's cash flow, resulting in delays in arranging alternative funding and consequently slowing the construction progress.”
Source: Royal Fantasy Phase III’s extension records on MahaRERA (P51800009920), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Royal Fantasy Phase III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Royal Fantasy Phase IP51800009606 · possession 30 Jun 2022
- Royal Fantasy Phase IIP51800004649 · possession 31 Dec 2026
- MahaRERA registration
- P51800009920
- Status
- Registered and active
- Builder
- Royal Fantasy Constructions Private Limited
- Location
- Andheri, Mumbai · 400093
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- June 2027
- Delay so far
- 90 months
- Homes
- 59
- Sold or booked
- 83%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Royal Fantasy Phase III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable | 100% | 100% | 90% | 0% |
| Dreamax Height Wing A PH Full - no Saleable | 100% | 100% | 95% | 75% |
| Dreamax Vega Wing D | 100% | 100% | 100% | 85% |
| Dreamax Height Wing B 12th - 15th floor | 100% | 100% | 85% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable: covers 3 floors
- Dreamax Height Wing A PH Full - no Saleable: covers 15 floors
- Dreamax Vega Wing D: covers 12 floors
- Dreamax Height Wing B 12th - 15th floor: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Royal Fantasy Phase III every month.
Royal Fantasy Phase III: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 678 – 714 | 41 |
| Other | 289 – 1,176 | 12 |
| 1 BHK | 465 – 473 | 6 |
| Shops | 4,252 | 1 |
- Buildings: Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable (4 floors, 1 units) · Dreamax Height Wing A PH Full - no Saleable (16 floors, 11 units) · Dreamax Vega Wing D (16 floors, 40 units) · Dreamax Height Wing B 12th - 15th floor (5 floors, 8 units)
- Car parking: 44 covered
- Land: 6,117 sq m (about 1.5 acres) · sanctioned built-up 2,044 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Royal Fantasy Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 39 months); 2 still being built, 2 past the promised date (typically 85 months late). 8 complaints on MahaRERA across 2 projects.
Read Google reviews of Royal Fantasy Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Royal Fantasy Phase III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Royal Fantasy Phase III
What is the possession date of Royal Fantasy Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Royal Fantasy Phase III in Andheri, Mumbai is 30 June 2027 — 90 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Royal Fantasy Phase III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Royal Fantasy Phase III's builder has filed on MahaRERA, the official one, is 30 June 2027, already 90 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Royal Fantasy Phase III extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III's builder applied to MahaRERA to extend the completion date 6 times: to 30 December 2020, giving the reason "Our under construction real estate project is getting delayed due to several reasons as follows: 1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition for sale 2. Other reasons: • Contractor’s inability to complete scheduled phase due to shortage of labour faced by him. • Last year disruptions due to GST & demonetization implementations. • Non-availability of sand on time. 3. Default from contactors: • Contra…"; to 30 June 2023, giving the reason "1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending. 6. Due to COVID Pandemic Factor, the construction was not completed within the project completion date."; to 30 June 2024, giving the reason "1. Temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time 3. Default from contractors 4. Outstanding receivable from buyers 5. Registration of some flats were still pending"; to 30 June 2025, giving the reason "1. Work in progress in phase 3 is slow as compared to our schedule because we have to take utmost care of possession given to flat buyers in phase 1 close to the phase 3 building during construction activity. 2. The Flat buyers are not paying payments as per the schedule and we have to arrange funds from other sources every time which takes time."; to 30 June 2026, giving the reason "i) The project comprises three phases—Phase 1, Phase 2, and Phase 3—being developed on the same plot of land and includes two buildings: Dreamax Vega and Dreamax Height. Phase 1 has been successfully completed, Occupation Certificate (OC) has been obtained, and possession has been handed over to the respective allottees. Phase 2 is nearing completion. However, the progress of Phase 3 has been comparatively slower due to the necessity of exercising extreme caution during construction activities, as Phase 3 is in close proximity to the already occupied Phase 1. This precaution is being taken…"; to 30 June 2027, giving the reason "The project completion was delayed due to the need for additional safety precautions during construction, as Phase 3 is located adjacent to the occupied Phase 1, to ensure the safety and comfort of residents. Further, irregular payments by certain allottees affected the project's cash flow, resulting in delays in arranging alternative funding and consequently slowing the construction progress.".
What is the RERA number of Royal Fantasy Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Royal Fantasy Phase III in Andheri, Mumbai is P51800009920.
Is Royal Fantasy Phase III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III is registered as P51800009920 and its status is "Registered and active".
What is the construction status of Royal Fantasy Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Royal Fantasy Phase III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Royal Fantasy Phase III safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III is registered on MahaRERA as P51800009920, its completion date has moved 90 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Royal Fantasy Phase III have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Royal Fantasy Phase I (P51800009606, possession 30 Jun 2022); Royal Fantasy Phase II (P51800004649, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.
How can I get updates if Royal Fantasy Phase III's possession date changes?
The latest dates are on Royal Fantasy Phase III's MahaRERA page (P51800009920). GharKundli's Kundli Watch sends a free WhatsApp update on Royal Fantasy Phase III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Royal Fantasy Phase III have?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III has 4 buildings filed: Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable with 4 floors and 1 units; Dreamax Height Wing A PH Full - no Saleable with 16 floors and 11 units; Dreamax Vega Wing D with 16 floors and 40 units; Dreamax Height Wing B 12th - 15th floor with 5 floors and 8 units.
What are the flat sizes (carpet area) in Royal Fantasy Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Royal Fantasy Phase III: 2 BHK: 678 to 714 sq ft carpet (41 homes); Other: 289 to 1176 sq ft carpet (12 homes); 1 BHK: 465 to 473 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Royal Fantasy Phase III have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 44 covered car parking spaces for Royal Fantasy Phase III.
How big is the land of Royal Fantasy Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III stands on 6,117 sq m of land (about 1.5 acres), with 2,044 sq m of sanctioned built-up area.
What is the track record of Royal Fantasy Phase III's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 39 months); 2 still being built, 2 past the promised date (typically 85 months late). 8 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Royal Fantasy Phase III?
Google Maps has reviews of Royal Fantasy Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Royal Fantasy Phase III?
Royal Fantasy Phase III by Royal Fantasy Constructions Private Limited is in Andheri, Mumbai (pincode 400093), near Jogeshwari East, Mogra, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800009920, per GharKundli's check of MahaRERA records.
How many homes are in Royal Fantasy Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III has 59 homes in 4 towers registered on MahaRERA, and 83% of them are sold or booked.
When was Royal Fantasy Phase III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Royal Fantasy Phase III was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Royal Fantasy Phase III?
No court cases are listed for Royal Fantasy Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Royal Fantasy Phase III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Royal Fantasy Constructions Private Limited, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Royal Fantasy Phase III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Andheri
- MESACON HARMONY
- M.K Heritage
- LUMA TOWERS A & B
- Pearl 2
- Royal Fantasy Phase II
- State Bank Of India Employees Sakar Swapna CHSL
- Luma Tower C
- MESACON MAGIC CARPET
Other projects by Royal Fantasy Constructions Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.