Nandigram

by YOGESH KISHOR MAHAJAN · Mahagiri Kharkar Ali, Thane 400601Also near Majiwade, Badlapur, Naupada

What’s in the report? →

Possession date of Nandigram (MahaRERA P51700049363): 30 November 2026, moved from 31 March 2025 (16 months later). It has 14 homes, 9% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700049363, and currently active. Its completion date has moved from March 2025 to November 2026: 16 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700049363, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Nandigram?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Nandigram has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EA14052501126)

    Reason the builder gave MahaRERA: “As per the attachment”
  3. 31 July 2026

    Extended at the builder's request (MahaRERA application EA16022619845)

    Reason the builder gave MahaRERA:
    “The current facts of the case are being explained hereunder. As the registration is already expired, we are facing many operational difficulties including no advertisement. The main reason for the delay is pace of sales being lower than exp…” Read the full reason“The current facts of the case are being explained hereunder. As the registration is already expired, we are facing many operational difficulties including no advertisement. The main reason for the delay is pace of sales being lower than expected and thereby effecting the cash flows of the project. Lower than expected cash flows has in turn effected the pace of construction of the project thereby making it impossible to meet the scheduled due date 31/03/2025. It may be noted that till date we have only sold three flats out of 11 flats available for sale. In addition to poor cash flows, cost…”
  4. 30 November 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Nandigram’s extension records on MahaRERA (P51700049363), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Nandigram

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700049363
Status
Registered and active
Builder
YOGESH KISHOR MAHAJAN
Location
Mahagiri Kharkar Ali, Thane · 400601
Project type
Residential / Group Housing
Registered on
7 Feb 2023
Completion date at registration
March 2025
Latest completion date
November 2026
Delay so far
16 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
14
Sold or booked
9%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Nandigram, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Building100%100%80%50%

Commencement certificate (CC), as filed on MahaRERA

  • A Building: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nandigram every 1–2 months.

Nandigram: buildings, flats and land, as filed on MahaRERA

  • Buildings: A Building (8 floors, 14 units)
  • Car parking: 14 covered
  • Land: 370 sq m (about 0.1 acres) · sanctioned built-up 1,114 sq m
  • Boundaries filed include: Anjuman Islam School
  • Land, as filed: Tikka No 5, 62A/1, 62D/1, 62C, 62E
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Nandigram →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nandigram: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nandigram

What is the possession date of Nandigram?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nandigram in Mahagiri Kharkar Ali, Thane is 30 November 2026 — 16 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 16 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Nandigram?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nandigram's builder has filed on MahaRERA, the official one, is 30 November 2026, already 16 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Nandigram extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "As per the attachment"; to 31 July 2026, giving the reason "The current facts of the case are being explained hereunder. As the registration is already expired, we are facing many operational difficulties including no advertisement. The main reason for the delay is pace of sales being lower than expected and thereby effecting the cash flows of the project. Lower than expected cash flows has in turn effected the pace of construction of the project thereby making it impossible to meet the scheduled due date 31/03/2025. It may be noted that till date we have only sold three flats out of 11 flats available for sale. In addition to poor cash flows, cost…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Nandigram?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nandigram in Mahagiri Kharkar Ali, Thane is P51700049363.

Is Nandigram registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram is registered as P51700049363 and its status is "Registered and active".

What is the current construction status of Nandigram? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A Building is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Nandigram have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Nandigram safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram is registered on MahaRERA as P51700049363, its completion date has moved 16 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nandigram?

Nandigram is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Nandigram?

For a flat in Nandigram (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Nandigram received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram is still under construction, with 30 November 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Nandigram uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nandigram was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nandigram's possession date changes?

The latest dates are on Nandigram's MahaRERA page (P51700049363). GharKundli's Kundli Watch sends a free WhatsApp update on Nandigram every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nandigram have?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram has one building filed: A Building with 8 floors and 14 units.

How much parking does Nandigram have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 14 covered car parking spaces for Nandigram.

How big is the land of Nandigram?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram stands on 370 sq m of land (about 0.1 acres), with 1,114 sq m of sanctioned built-up area.

What are the reviews of Nandigram?

Google Maps has reviews of Nandigram written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nandigram?

Nandigram by YOGESH KISHOR MAHAJAN is in Mahagiri Kharkar Ali, Thane, pincode 400601 (near Majiwade, Badlapur, Naupada), Maharashtra, and is registered on MahaRERA as P51700049363, per GharKundli's check of MahaRERA records. Its boundaries filed there include Anjuman Islam School. Its land is filed as Tikka No 5, 62A/1, 62D/1, 62C, 62E. GharKundli lists all 178 MahaRERA projects in Thane (400601).

How many flats are in Nandigram, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram has 14 homes in 1 tower registered on MahaRERA, and 9% of them are sold or booked.

When was Nandigram registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandigram was registered on MahaRERA on 7 February 2023. GharKundli did not find a title report on the land on file there.

Does Nandigram have any legal issues or court cases?

No court cases are listed for Nandigram on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Nandigram?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YOGESH KISHOR MAHAJAN.

All projects with possession due in 2026 in Thane →

Other projects in Thane

All 178 projects in Thane (400601) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.