Kerala Village Phase-2
by JOHN MATHEW · Near Shenwa Naka, Thane 421601
What’s in the report? →Possession date of Kerala Village Phase-2 (MahaRERA P51700051512): 31 July 2027, moved from 31 December 2025 (15 months later). It has 127 homes, 61% sold or booked. 1 complaint on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700051512, and currently active. Its completion date has moved from December 2025 to July 2027: 15 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700051512, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Kerala Village Phase-2?
1 complaint MahaRERA par. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kerala Village Phase-2 has moved
31 December 2025
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA16122518703)
Reason the builder gave MahaRERA:
“Respected Sir We hereby submit this application seeking extension of the project completion date for Kerala Village – Phase 2, registered with MahaRERA under Registration No. P51700051512, up to 31st March 2027, in accordance with Section 6…” Read the full reason
“Respected Sir We hereby submit this application seeking extension of the project completion date for Kerala Village – Phase 2, registered with MahaRERA under Registration No. P51700051512, up to 31st March 2027, in accordance with Section 6 of the Real Estate (Regulation and Development) Act, 2016. Project Background Kerala Village is being developed in two phases. • Phase 1, comprising Studio Apartments No. 1, 2 & 3 and 25 Villas, has been completed. The Planning Authority has granted the Occupancy Certificate dated 02.12.2024, bearing No. Mahasul/K-1/T-11/NAP/Sathgaon/Tal: Shahapur/Partly…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kerala Village Phase-2’s extension records on MahaRERA (P51700051512), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kerala Village Phase-2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- KERALA VILLAGEP51700006990 · possession 31 Mar 2025
- MahaRERA registration
- P51700051512
- Status
- Registered and active
- Builder
- JOHN MATHEW
- Location
- Near Shenwa Naka, Thane · 421601
- Project type
- Others
- Registered on
- 23 Jun 2023
- Completion date at registration
- December 2025
- Latest completion date
- July 2027
- Delay so far
- 15 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 127
- Sold or booked
- 61%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Kerala Village Phase-2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Type D | 100% | 100% | 100% | 0% |
| Type E Tourists Home | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Type D: covers 6 floors
- Type E Tourists Home: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kerala Village Phase-2 every 1–2 months.
Kerala Village Phase-2: buildings, flats and land, as filed on MahaRERA
- Buildings: Type D (6 floors, 29 units) · Type E Tourists Home (8 floors, 98 units)
- Car parking: 12 covered
- Land: 8,045 sq m (about 2.0 acres) · sanctioned built-up 4,990 sq m · recreational space 797 sq m
- Land, as filed: Survey No.396(Pt ), 397 ( Pt ) & 399
- Map: Get directions
The builder’s record and reviews
John Mathew has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Kerala Village Phase-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kerala Village Phase-2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kerala Village Phase-2
What is the possession date of Kerala Village Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kerala Village Phase-2 in Near Shenwa Naka, Thane is 31 July 2027 — 15 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 15 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kerala Village Phase-2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kerala Village Phase-2's builder has filed on MahaRERA, the official one, is 31 July 2027, already 15 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kerala Village Phase-2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Respected Sir We hereby submit this application seeking extension of the project completion date for Kerala Village – Phase 2, registered with MahaRERA under Registration No. P51700051512, up to 31st March 2027, in accordance with Section 6 of the Real Estate (Regulation and Development) Act, 2016. Project Background Kerala Village is being developed in two phases. • Phase 1, comprising Studio Apartments No. 1, 2 & 3 and 25 Villas, has been completed. The Planning Authority has granted the Occupancy Certificate dated 02.12.2024, bearing No. Mahasul/K-1/T-11/NAP/Sathgaon/Tal: Shahapur/Partly…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Kerala Village Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kerala Village Phase-2 in Near Shenwa Naka, Thane is P51700051512.
Is Kerala Village Phase-2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2 is registered as P51700051512 and its status is "Registered and active".
What is the current construction status of Kerala Village Phase-2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Kerala Village Phase-2 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
1 complaint is filed on this project. Know what went wrong before you pay a token. See how it ended →
Is Kerala Village Phase-2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2 is registered on MahaRERA as P51700051512, its completion date has moved 15 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kerala Village Phase-2?
Kerala Village Phase-2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kerala Village Phase-2?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kerala Village Phase-2: gharkundli.com/tools/property-cost-calculator
Has Kerala Village Phase-2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2 is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Kerala Village Phase-2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kerala Village Phase-2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Kerala Village Phase-2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: KERALA VILLAGE (P51700006990, possession 31 Mar 2025). Check that your agreement names the registration of your own wing.
How can I get updates if Kerala Village Phase-2's possession date changes?
The latest dates are on Kerala Village Phase-2's MahaRERA page (P51700051512). GharKundli's Kundli Watch sends a free WhatsApp update on Kerala Village Phase-2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kerala Village Phase-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2 has 2 buildings filed: Type D with 6 floors and 29 units; Type E Tourists Home with 8 floors and 98 units.
How much parking does Kerala Village Phase-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for Kerala Village Phase-2.
How big is the land of Kerala Village Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2 stands on 8,045 sq m of land (about 2.0 acres), with 4,990 sq m of sanctioned built-up area and 797 sq m of recreational open space.
What is the track record of Kerala Village Phase-2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), John Mathew has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Kerala Village Phase-2?
Google Maps has reviews of Kerala Village Phase-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kerala Village Phase-2?
Kerala Village Phase-2 by JOHN MATHEW is in Near Shenwa Naka, Thane, pincode 421601, Maharashtra, and is registered on MahaRERA as P51700051512, per GharKundli's check of MahaRERA records. Its land is filed as Survey No.396(Pt ), 397 ( Pt ) & 399. GharKundli lists all 184 MahaRERA projects in Shahapur (421601).
How many flats are in Kerala Village Phase-2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2 has 127 homes in 2 towers registered on MahaRERA, and 61% of them are sold or booked.
When was Kerala Village Phase-2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kerala Village Phase-2 was registered on MahaRERA on 23 June 2023. GharKundli did not find a title report on the land on file there.
Does Kerala Village Phase-2 have any legal issues or court cases?
No court cases are listed for Kerala Village Phase-2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Kerala Village Phase-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JOHN MATHEW, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kerala Village Phase-2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Shahapur
- Aghav Resideny
- The White Villas
- The White Villas Kasara Phase 2
- Prem Narayan Residency
- Visava
- Sai Anand Apartment
- Chintamani Habitat (Fortuna Bungalow)
- Mirador Utsav Phase 1
Other projects by JOHN MATHEW
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.