What’s in the report? →

Possession date of Jai Shree Ganesh Co-Operative Housing Society Limited (MahaRERA P51700048313): 30 April 2027, moved from 31 December 2024 (24 months later). It has 28 homes, 79% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700048313, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700048313, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Jai Shree Ganesh Co-Operative Housing Society Limited?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Jai Shree Ganesh Co-Operative Housing Society Limited has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51700024963)

    Reason the builder gave MahaRERA: “As per attachment”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EA30062501866)

    Reason the builder gave MahaRERA: “As per attachment”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA26122519036)

    Reason the builder gave MahaRERA:
    “The application for Full Occupancy certificate also submitted to Competent authority that is Kalyan Dombivli Municipal Corporation through the online “Mahavastu” portal as on 1st April 2025 vide application number KDMCC/2025/1506048/71544.…” Read the full reason“The application for Full Occupancy certificate also submitted to Competent authority that is Kalyan Dombivli Municipal Corporation through the online “Mahavastu” portal as on 1st April 2025 vide application number KDMCC/2025/1506048/71544. Screenshot of the application is annexed herewith for your quick reference. It may be noted that all the required NOC’s are submitted by the promoter and there are no compliance pending to be complied on the part of the Promoter, in order to receive Occupancy Certificate from Kalyan Dombivli Municipal Corporation. The application for full Occupancy Certif…”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Jai Shree Ganesh Co-Operative Housing Society Limited’s extension records on MahaRERA (P51700048313), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Jai Shree Ganesh Co-Operative Housing Society Limited

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700048313
Status
Registered and active
Builder
Shree Vyankatesh Enterprises
Location
Dombivli west, Thane · 421202
Project type
Residential / Group Housing
Registered on
26 Dec 2022
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
79%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Jai Shree Ganesh Co-Operative Housing Society Limited, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Jai Shree Ganesh Co-Operative Housing Society Limited100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Jai Shree Ganesh Co-Operative Housing Society Limited: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jai Shree Ganesh Co-Operative Housing Society Limited every 1–2 months.

Jai Shree Ganesh Co-Operative Housing Society Limited: buildings, flats and land, as filed on MahaRERA

  • Buildings: Jai Shree Ganesh Co-Operative Housing Society Limited (8 floors, 31 units)
  • Land: 496 sq m (about 0.1 acres) · sanctioned built-up 1,779 sq m
  • Land, as filed: Old Survey No 326 (part) New Survey No 229 (part) H No. A Plot no 57
  • Map: Get directions

The builder’s record and reviews

Shree Vyankatesh Enterprises (a group of 2 linked companies) has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.

Read Google reviews of Jai Shree Ganesh Co-Operative Housing Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Jai Shree Ganesh Co-Operative Housing Society Limited: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Jai Shree Ganesh Co-Operative Housing Society Limited

What is the possession date of Jai Shree Ganesh Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jai Shree Ganesh Co-Operative Housing Society Limited in Dombivli west, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Jai Shree Ganesh Co-Operative Housing Society Limited?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Jai Shree Ganesh Co-Operative Housing Society Limited's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Jai Shree Ganesh Co-Operative Housing Society Limited extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2025, giving the reason "As per attachment"; to 31 December 2025, giving the reason "As per attachment"; to 31 December 2026, giving the reason "The application for Full Occupancy certificate also submitted to Competent authority that is Kalyan Dombivli Municipal Corporation through the online “Mahavastu” portal as on 1st April 2025 vide application number KDMCC/2025/1506048/71544. Screenshot of the application is annexed herewith for your quick reference. It may be noted that all the required NOC’s are submitted by the promoter and there are no compliance pending to be complied on the part of the Promoter, in order to receive Occupancy Certificate from Kalyan Dombivli Municipal Corporation. The application for full Occupancy Certif…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Jai Shree Ganesh Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jai Shree Ganesh Co-Operative Housing Society Limited in Dombivli west, Thane is P51700048313.

Is Jai Shree Ganesh Co-Operative Housing Society Limited registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited is registered as P51700048313 and its status is "Registered and active".

What is the current construction status of Jai Shree Ganesh Co-Operative Housing Society Limited? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Jai Shree Ganesh Co-Operative Housing Society Limited is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Jai Shree Ganesh Co-Operative Housing Society Limited have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Jai Shree Ganesh Co-Operative Housing Society Limited safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited is registered on MahaRERA as P51700048313, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Jai Shree Ganesh Co-Operative Housing Society Limited?

Jai Shree Ganesh Co-Operative Housing Society Limited is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Jai Shree Ganesh Co-Operative Housing Society Limited?

For a flat in Jai Shree Ganesh Co-Operative Housing Society Limited (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Jai Shree Ganesh Co-Operative Housing Society Limited received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Jai Shree Ganesh Co-Operative Housing Society Limited a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited is a redevelopment: 12 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Jai Shree Ganesh Co-Operative Housing Society Limited uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Jai Shree Ganesh Co-Operative Housing Society Limited was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Jai Shree Ganesh Co-Operative Housing Society Limited's possession date changes?

The latest dates are on Jai Shree Ganesh Co-Operative Housing Society Limited's MahaRERA page (P51700048313). GharKundli's Kundli Watch sends a free WhatsApp update on Jai Shree Ganesh Co-Operative Housing Society Limited every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Jai Shree Ganesh Co-Operative Housing Society Limited have?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited has one building filed: Jai Shree Ganesh Co-Operative Housing Society Limited with 8 floors and 31 units.

How big is the land of Jai Shree Ganesh Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited stands on 496 sq m of land (about 0.1 acres), with 1,779 sq m of sanctioned built-up area.

What is the track record of Jai Shree Ganesh Co-Operative Housing Society Limited's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Vyankatesh Enterprises (a group of 2 linked companies) has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Jai Shree Ganesh Co-Operative Housing Society Limited?

Google Maps has reviews of Jai Shree Ganesh Co-Operative Housing Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Jai Shree Ganesh Co-Operative Housing Society Limited?

Jai Shree Ganesh Co-Operative Housing Society Limited by Shree Vyankatesh Enterprises is in Dombivli west, Thane, pincode 421202, Maharashtra, and is registered on MahaRERA as P51700048313, per GharKundli's check of MahaRERA records. Its land is filed as Old Survey No 326 (part) New Survey No 229 (part) H No. A Plot no 57. GharKundli lists all 226 MahaRERA projects in Vishnunagar (421202).

How many flats are in Jai Shree Ganesh Co-Operative Housing Society Limited, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited has 28 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.

When was Jai Shree Ganesh Co-Operative Housing Society Limited registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jai Shree Ganesh Co-Operative Housing Society Limited was registered on MahaRERA on 26 December 2022. GharKundli did not find a title report on the land on file there.

Does Jai Shree Ganesh Co-Operative Housing Society Limited have any legal issues or court cases?

No court cases are listed for Jai Shree Ganesh Co-Operative Housing Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Jai Shree Ganesh Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Vyankatesh Enterprises, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 226 projects in Vishnunagar (421202) →

Other projects by Shree Vyankatesh Enterprises

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.