New Suyash CHS
by Ganesh Chandrakant Malvankar · Naupada, Thane 400602
What’s in the report? →Possession date of New Suyash CHS (MahaRERA P51700052617): 30 October 2027, moved from 31 December 2025 (18 months later). It has 43 homes, 52% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700052617, and currently active. Its completion date has moved from December 2025 to October 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700052617, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about New Suyash CHS?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of New Suyash CHS has moved
31 December 2025
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA12032620188)
Reason the builder gave MahaRERA:
“Dear Sir/Ma’am, I, Ganesh Chandrakant Malvankar, hereby declare the following with respect to the project “New Suyash CHS” bearing registration number P51700052617 registered under MahaRERA 1. Status of Work Completed: We are pleased to inf…” Read the full reason
“Dear Sir/Ma’am, I, Ganesh Chandrakant Malvankar, hereby declare the following with respect to the project “New Suyash CHS” bearing registration number P51700052617 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying fo…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: New Suyash CHS’s extension records on MahaRERA (P51700052617), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on New Suyash CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700052617
- Status
- Registered and active
- Builder
- Ganesh Chandrakant Malvankar
- Location
- Naupada, Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 11 Sep 2023
- Completion date at registration
- December 2025
- Latest completion date
- October 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 43
- Sold or booked
- 52%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of New Suyash CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| New Suyash CHS | 100% | 100% | 85% | 85% |
Commencement certificate (CC), as filed on MahaRERA
- New Suyash CHS: covers 9 floors
Latest CC order on MahaRERA: dated 26/11/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on New Suyash CHS every 1–2 months.
New Suyash CHS: buildings, flats and land, as filed on MahaRERA
- Buildings: New Suyash CHS (9 floors, 43 units)
- Car parking: 33 covered
- Land: 710 sq m (about 0.2 acres) · sanctioned built-up 2,703 sq m
- Land, as filed: 811,812,813,814 T No 11
- Map: Get directions
The builder’s record and reviews
Ganesh Chandrakant Malvankar has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 17 months late). No complaints on MahaRERA.
Read Google reviews of New Suyash CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
New Suyash CHS: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about New Suyash CHS
What is the possession date of New Suyash CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for New Suyash CHS in Naupada, Thane is 30 October 2027 — 18 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for New Suyash CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date New Suyash CHS's builder has filed on MahaRERA, the official one, is 30 October 2027, already 18 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of New Suyash CHS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "Dear Sir/Ma’am, I, Ganesh Chandrakant Malvankar, hereby declare the following with respect to the project “New Suyash CHS” bearing registration number P51700052617 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying fo…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of New Suyash CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of New Suyash CHS in Naupada, Thane is P51700052617.
Is New Suyash CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS is registered as P51700052617 and its status is "Registered and active".
What is the current construction status of New Suyash CHS? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on New Suyash CHS is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does New Suyash CHS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is New Suyash CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS is registered on MahaRERA as P51700052617, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in New Suyash CHS?
New Suyash CHS is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in New Suyash CHS?
For a flat in New Suyash CHS (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has New Suyash CHS received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is New Suyash CHS a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS is a redevelopment: 18 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has New Suyash CHS uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for New Suyash CHS was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if New Suyash CHS's possession date changes?
The latest dates are on New Suyash CHS's MahaRERA page (P51700052617). GharKundli's Kundli Watch sends a free WhatsApp update on New Suyash CHS every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does New Suyash CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS has one building filed: New Suyash CHS with 9 floors and 43 units.
How much parking does New Suyash CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered car parking spaces for New Suyash CHS.
How big is the land of New Suyash CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS stands on 710 sq m of land (about 0.2 acres), with 2,703 sq m of sanctioned built-up area.
What is the track record of New Suyash CHS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganesh Chandrakant Malvankar has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 17 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of New Suyash CHS?
Google Maps has reviews of New Suyash CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of New Suyash CHS?
New Suyash CHS by Ganesh Chandrakant Malvankar is in Naupada, Thane, pincode 400602, Maharashtra, and is registered on MahaRERA as P51700052617, per GharKundli's check of MahaRERA records. Its land is filed as 811,812,813,814 T No 11. GharKundli lists all 258 MahaRERA projects in Naupada (400602).
How many flats are in New Suyash CHS, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS has 43 homes in 1 tower registered on MahaRERA, and 52% of them are sold or booked.
When was New Suyash CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), New Suyash CHS was registered on MahaRERA on 11 September 2023. GharKundli did not find a title report on the land on file there.
Does New Suyash CHS have any legal issues or court cases?
No court cases are listed for New Suyash CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of New Suyash CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ganesh Chandrakant Malvankar, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of New Suyash CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Naupada (400602)
- Asavari Co Op HSG Soc LTD
- The Lake Corner
- Platinum Square
- Parvati Niwas
- Rivanta
- Ekatva Crescent
- Pitruchhaya
- Navyug Co.Op.Hsg.Limited
Other projects by Ganesh Chandrakant Malvankar
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.