Moon Midtown Eve

by MOON STAR DEVELOPERS LLP · Wadeghar, Thane 421301Registered on MahaRERA as “MIDTOWN EVE”

What’s in the report? →

Possession date of Moon Midtown Eve (MahaRERA P51700049094): 30 October 2027, moved from 30 June 2026 (12 months later). It has 84 homes, 69% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700049094, and currently active. Its completion date has moved from June 2026 to October 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700049094, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Moon Midtown Eve?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Moon Midtown Eve has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA09052620890)

    Reason the builder gave MahaRERA:
    “The project has suffered delays due to unforeseen and unavoidable circumstances, specifically: • The appointed contractor was having a labour shortage for 5 to 7 months. Due to unforeseen labour issues/shortage of , materials at the site du…” Read the full reason“The project has suffered delays due to unforeseen and unavoidable circumstances, specifically: • The appointed contractor was having a labour shortage for 5 to 7 months. Due to unforeseen labour issues/shortage of , materials at the site due to war, the progress of work has been temporarily affected.”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Moon Midtown Eve’s extension records on MahaRERA (P51700049094), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Moon Midtown Eve

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700049094
Status
Registered and active
Builder
MOON STAR DEVELOPERS LLP
Location
Wadeghar, Thane · 421301
Project type
Others
Registered on
30 Jan 2023
Completion date at registration
June 2026
Latest completion date
October 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
84
Sold or booked
69%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Moon Midtown Eve, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MIDTOWN EVE100%100%90%80%

Commencement certificate (CC), as filed on MahaRERA

  • MIDTOWN EVE: covers 23 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Moon Midtown Eve every 1–2 months.

Moon Midtown Eve: buildings, flats and land, as filed on MahaRERA

  • Buildings: MIDTOWN EVE (23 floors, 98 units)
  • Car parking: 59 covered
  • Land: 1,545 sq m (about 0.4 acres) · sanctioned built-up 7,498 sq m
  • Land, as filed: 40/1
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Moon Midtown Eve →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Moon Midtown Eve: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Moon Midtown Eve

What is the possession date of Moon Midtown Eve?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Moon Midtown Eve in Wadeghar, Thane is 30 October 2027 — 12 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Moon Midtown Eve?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Moon Midtown Eve's builder has filed on MahaRERA, the official one, is 30 October 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Moon Midtown Eve extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "The project has suffered delays due to unforeseen and unavoidable circumstances, specifically: • The appointed contractor was having a labour shortage for 5 to 7 months. Due to unforeseen labour issues/shortage of , materials at the site due to war, the progress of work has been temporarily affected.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Moon Midtown Eve?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Moon Midtown Eve in Wadeghar, Thane is P51700049094.

Is Moon Midtown Eve registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve is registered as P51700049094 and its status is "Registered and active".

What is the current construction status of Moon Midtown Eve? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MIDTOWN EVE is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Moon Midtown Eve have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Moon Midtown Eve safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve is registered on MahaRERA as P51700049094, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Moon Midtown Eve?

Moon Midtown Eve is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Moon Midtown Eve?

For a flat in Moon Midtown Eve (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Moon Midtown Eve received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Moon Midtown Eve uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Moon Midtown Eve was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Moon Midtown Eve's possession date changes?

The latest dates are on Moon Midtown Eve's MahaRERA page (P51700049094). GharKundli's Kundli Watch sends a free WhatsApp update on Moon Midtown Eve every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Moon Midtown Eve have?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve has one building filed: MIDTOWN EVE with 23 floors and 98 units.

How much parking does Moon Midtown Eve have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 59 covered car parking spaces for Moon Midtown Eve.

How big is the land of Moon Midtown Eve?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve stands on 1,545 sq m of land (about 0.4 acres), with 7,498 sq m of sanctioned built-up area.

What are the reviews of Moon Midtown Eve?

Google Maps has reviews of Moon Midtown Eve written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Moon Midtown Eve?

Moon Midtown Eve by MOON STAR DEVELOPERS LLP is in Wadeghar, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700049094, per GharKundli's check of MahaRERA records. Its land is filed as 40/1. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

How many flats are in Moon Midtown Eve, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve has 84 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.

When was Moon Midtown Eve registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Moon Midtown Eve was registered on MahaRERA on 30 January 2023. GharKundli did not find a title report on the land on file there.

Does Moon Midtown Eve have any legal issues or court cases?

1 court case is listed for Moon Midtown Eve on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Moon Midtown Eve?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MOON STAR DEVELOPERS LLP, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan (421301)

All 582 projects in Kalyan (421301) →

Other projects by MOON STAR DEVELOPERS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.