Shubh Shivshakti Manokamana
by SHUBH VASTU CONSTRUCTION · Wadeghar, Thane 421301Registered on MahaRERA as “Shivshakti Manokamana”
What’s in the report? →Possession date of Shubh Shivshakti Manokamana (MahaRERA P51700050309): 30 April 2030, moved from 31 December 2026 (36 months later). It has 133 homes, 11% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700050309, and currently active. Its completion date has moved from December 2026 to April 2030: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700050309, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shubh Shivshakti Manokamana?
Possession date khiski: ab Apr 2030. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shubh Shivshakti Manokamana has moved
31 December 2026
Completion date given when the project was registered
31 December 2029
Extended at the builder's request (MahaRERA application EA04032620092)
Reason the builder gave MahaRERA:
“That due to unavoidable circumstances, including but not limited to delays in construction activities, approvals, market conditions, and other factors beyond our reasonable control, the project could not be completed within the originally a…” Read the full reason
“That due to unavoidable circumstances, including but not limited to delays in construction activities, approvals, market conditions, and other factors beyond our reasonable control, the project could not be completed within the originally approved timeline.”30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shubh Shivshakti Manokamana’s extension records on MahaRERA (P51700050309), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shubh Shivshakti Manokamana
Ready · November 2026 · 61 filings read
- Risk & trust score, every point explained
- What the title report on MahaRERA says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700050309
- Status
- Registered and active
- Builder
- SHUBH VASTU CONSTRUCTION
- Location
- Wadeghar, Thane · 421301
- Project type
- Others
- Registered on
- 1 Apr 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2030
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 133
- Sold or booked
- 11%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Yes
- Latest construction certificate
- 30 Jun 2026
Construction progress of Shubh Shivshakti Manokamana, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MANOKAMANA | 100% | 94% | 30% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- MANOKAMANA: covers 16 floors
Latest CC order on MahaRERA: dated 26/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shubh Shivshakti Manokamana every 1–2 months.
Shubh Shivshakti Manokamana: buildings, flats and land, as filed on MahaRERA
- Buildings: MANOKAMANA (16 floors, 142 units)
- Car parking: 40 covered, 20 open
- Land: 2,100 sq m (about 0.5 acres) · sanctioned built-up 8,856 sq m
- Land, as filed: 50/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shubh Shivshakti Manokamana →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shubh Shivshakti Manokamana: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shubh Shivshakti Manokamana
What is the possession date of Shubh Shivshakti Manokamana?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shubh Shivshakti Manokamana in Wadeghar, Thane is 30 April 2030 — 36 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shubh Shivshakti Manokamana?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shubh Shivshakti Manokamana's builder has filed on MahaRERA, the official one, is 30 April 2030, already 36 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shubh Shivshakti Manokamana extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "That due to unavoidable circumstances, including but not limited to delays in construction activities, approvals, market conditions, and other factors beyond our reasonable control, the project could not be completed within the originally approved timeline.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shubh Shivshakti Manokamana?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shubh Shivshakti Manokamana in Wadeghar, Thane is P51700050309.
Is Shubh Shivshakti Manokamana registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana is registered as P51700050309 and its status is "Registered and active".
What is the current construction status of Shubh Shivshakti Manokamana? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MANOKAMANA is 94% done and internal work 30%. The latest construction certificate the builder filed there is dated 30 June 2026. GharKundli's full report compares construction progress with the deadline.
Does Shubh Shivshakti Manokamana have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shubh Shivshakti Manokamana safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana is registered on MahaRERA as P51700050309, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shubh Shivshakti Manokamana?
Shubh Shivshakti Manokamana is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shubh Shivshakti Manokamana?
For a flat in Shubh Shivshakti Manokamana (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shubh Shivshakti Manokamana received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shubh Shivshakti Manokamana uploaded its title report on MahaRERA?
Yes. According to GharKundli's check of MahaRERA records (updated November 2026), an advocate's title report for Shubh Shivshakti Manokamana is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.
A loan or claim on the land can hold up your flat or your home loan. See what the title report says →
How can I get updates if Shubh Shivshakti Manokamana's possession date changes?
The latest dates are on Shubh Shivshakti Manokamana's MahaRERA page (P51700050309). GharKundli's Kundli Watch sends a free WhatsApp update on Shubh Shivshakti Manokamana every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shubh Shivshakti Manokamana have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana has one building filed: MANOKAMANA with 16 floors and 142 units.
How much parking does Shubh Shivshakti Manokamana have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 40 covered and 20 open car parking spaces for Shubh Shivshakti Manokamana.
How big is the land of Shubh Shivshakti Manokamana?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana stands on 2,100 sq m of land (about 0.5 acres), with 8,856 sq m of sanctioned built-up area.
What are the reviews of Shubh Shivshakti Manokamana?
Google Maps has reviews of Shubh Shivshakti Manokamana written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shubh Shivshakti Manokamana?
Shubh Shivshakti Manokamana by SHUBH VASTU CONSTRUCTION is in Wadeghar, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700050309, per GharKundli's check of MahaRERA records. Its land is filed as 50/2. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Shubh Shivshakti Manokamana, and how many are sold?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana has 133 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.
When was Shubh Shivshakti Manokamana registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shivshakti Manokamana was registered on MahaRERA on 1 April 2023. A title report on the land is on file there.
Does Shubh Shivshakti Manokamana have any legal issues or court cases?
No court cases are listed for Shubh Shivshakti Manokamana on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Shubh Shivshakti Manokamana?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHUBH VASTU CONSTRUCTION.
Check it yourself on MahaRERA
- How to check the possession date of Shubh Shivshakti Manokamana
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in Kalyan (421301)
- Midtown Eve
- Earth Park Building No 2
- Earth Park Building No 3
- Earth Park Building No 4
- Earth Park Building No 5
- Sai Satyam Residency B Building
- Nayan Apartment
- Sai Sharnam- Tybe B
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.