Trimity Stellar
by Trimity Realty LLP · Thane west, Thane 400602Also near Naupada, Panchpakhadi, CharaiRegistered on MahaRERA as “Stellar”
What’s in the report? →Possession date of Trimity Stellar (MahaRERA P51700048590): 30 October 2029, moved from 31 December 2027 (18 months later). It has 605 homes, 25% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700048590, and currently active. Its completion date has moved from December 2027 to October 2029: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700048590, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Trimity Stellar?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Trimity Stellar has moved
31 December 2027
Completion date given when the project was registered
30 June 2029
Extended at the builder's request (MahaRERA application EA31122519172)
Reason the builder gave MahaRERA: “as per attacted Self Declaration”
30 October 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Trimity Stellar’s extension records on MahaRERA (P51700048590), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Trimity Stellar
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700048590
- Status
- Registered and active
- Builder
- Trimity Realty LLP
- Location
- Thane west, Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 10 Jan 2023
- Completion date at registration
- December 2027
- Latest completion date
- October 2029
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 605
- Sold or booked
- 25%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Trimity Stellar, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shree Sainath SRA Sahakari Gruha Nirman Sanstha | 100% | 25% | 0% | 0% |
| Stellar | 100% | 10% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Shree Sainath SRA Sahakari Gruha Nirman Sanstha: covers 33 floors
- Stellar: covers 62 floors
Latest CC order on MahaRERA: dated 13/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Trimity Stellar every 1–2 months.
Trimity Stellar: buildings, flats and land, as filed on MahaRERA
- Buildings: Shree Sainath SRA Sahakari Gruha Nirman Sanstha (33 floors, 368 units) · Stellar (62 floors, 300 units)
- Car parking: 406 covered
- Land: 5,132 sq m (about 1.3 acres) · sanctioned built-up 36,122 sq m · recreational space 658 sq m
- Land, as filed: Final Plot No 325 (part)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Trimity Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 23 months); 3 still being built, 2 past the promised date (typically 23 months late). 8 complaints on MahaRERA across 2 projects.
Read Google reviews of Trimity Stellar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Trimity Stellar: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Trimity Stellar
What is the possession date of Trimity Stellar?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Trimity Stellar in Thane west, Thane is 30 October 2029 — 18 months later than 31 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Trimity Stellar?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Trimity Stellar's builder has filed on MahaRERA, the official one, is 30 October 2029, already 18 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Trimity Stellar extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar's builder applied to MahaRERA to extend the completion date once: to 30 June 2029, giving the reason "as per attacted Self Declaration". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Trimity Stellar?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Trimity Stellar in Thane west, Thane is P51700048590.
Is Trimity Stellar registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar is registered as P51700048590 and its status is "Registered and active".
What is the current construction status of Trimity Stellar? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 10% to 25% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Trimity Stellar have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Trimity Stellar safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar is registered on MahaRERA as P51700048590, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Trimity Stellar?
Trimity Stellar is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Trimity Stellar?
For a flat in Trimity Stellar (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Trimity Stellar received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar is still under construction, with 30 October 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Trimity Stellar a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar is a redevelopment: 289 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Trimity Stellar uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Trimity Stellar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Trimity Stellar's possession date changes?
The latest dates are on Trimity Stellar's MahaRERA page (P51700048590). GharKundli's Kundli Watch sends a free WhatsApp update on Trimity Stellar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Trimity Stellar have?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar has 2 buildings filed: Shree Sainath SRA Sahakari Gruha Nirman Sanstha with 33 floors and 368 units; Stellar with 62 floors and 300 units.
How much parking does Trimity Stellar have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 406 covered car parking spaces for Trimity Stellar.
How big is the land of Trimity Stellar?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar stands on 5,132 sq m of land (about 1.3 acres), with 36,122 sq m of sanctioned built-up area and 658 sq m of recreational open space.
What is the track record of Trimity Stellar's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 23 months); 3 still being built, 2 past the promised date (typically 23 months late). 8 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Trimity Stellar?
Google Maps has reviews of Trimity Stellar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Trimity Stellar?
Trimity Stellar by Trimity Realty LLP is in Thane west, Thane, pincode 400602 (near Naupada, Panchpakhadi, Charai), Maharashtra, and is registered on MahaRERA as P51700048590, per GharKundli's check of MahaRERA records. Its land is filed as Final Plot No 325 (part). GharKundli lists all 258 MahaRERA projects in Naupada (400602).
How many flats are in Trimity Stellar, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar has 605 homes in 2 towers registered on MahaRERA, and 25% of them are sold or booked.
When was Trimity Stellar registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Stellar was registered on MahaRERA on 10 January 2023. GharKundli did not find a title report on the land on file there.
Does Trimity Stellar have any legal issues or court cases?
No court cases are listed for Trimity Stellar on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Trimity Stellar?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Trimity Realty LLP.
Check it yourself on MahaRERA
- How to check the possession date of Trimity Stellar
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in Naupada (400602)
- Platinum Square
- Raunak Residency
- Mount casa
- Kashish Park Tower B
- Rustomjee Azziano Wing L
- Rustomjee Azziano Wing F
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.