Vaishnavi Heights

by VAISHNAVI CONSTRUCTION · Thangewadi, Thane 421301

What’s in the report? →

Possession date of Vaishnavi Heights (MahaRERA P51700051267): 30 April 2027, moved from 30 July 2024 (29 months later). It has 49 homes, 63% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700051267, and currently active. Its completion date has moved from July 2024 to April 2027: 29 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700051267, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Vaishnavi Heights?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vaishnavi Heights has moved

  1. 30 July 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51700024407)

    Reason the builder gave MahaRERA:
    “1) Initially we have taken three plots for development later stage one more adjacent plot’s development was merged with this ongoing development. After execution of the redevelopment agreement sanction of the revised plans and permission to…” Read the full reason“1) Initially we have taken three plots for development later stage one more adjacent plot’s development was merged with this ongoing development. After execution of the redevelopment agreement sanction of the revised plans and permission to construct took the time to start the construction work. 2) After all the permissions are in place there was shortage of Labors in the said area as various redevelopment are going on and most of the labor’s migration to native place in summer.”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA23092502665)

    Reason the builder gave MahaRERA:
    “1) Due to an unforeseen personal emergency, the appointed contractor had to return to his native place, resulting in the unavailability of both the contractor and his labour team. During this interim period, we initiated the process of iden…” Read the full reason“1) Due to an unforeseen personal emergency, the appointed contractor had to return to his native place, resulting in the unavailability of both the contractor and his labour team. During this interim period, we initiated the process of identifying and onboarding a suitable replacement contractor. Given the due diligence required for selection, negotiations, and mobilization of a new workforce, there was an unavoidable delay in resuming site activities 2) The finishing work experienced a slight delay due to the unavailability of quality-approved materials. As we are committed to maintaining…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Vaishnavi Heights’s extension records on MahaRERA (P51700051267), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vaishnavi Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700051267
Status
Registered and active
Builder
VAISHNAVI CONSTRUCTION
Location
Thangewadi, Thane · 421301
Project type
Residential / Group Housing
Registered on
8 Jun 2023
Completion date at registration
July 2024
Latest completion date
April 2027
Delay so far
29 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
49
Sold or booked
63%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Vaishnavi Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VAISHNAVI HEGHITS A WING100%100%100%60%
VAISHNAVI HEIGHTS B WING100%100%60%0%

Commencement certificate (CC), as filed on MahaRERA

  • VAISHNAVI HEGHITS A WING: covers 7 floors
  • VAISHNAVI HEIGHTS B WING: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vaishnavi Heights every 1–2 months.

Vaishnavi Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: VAISHNAVI HEGHITS A WING (7 floors, 38 units) · VAISHNAVI HEIGHTS B WING (7 floors, 21 units)
  • Land: 940 sq m (about 0.2 acres) · sanctioned built-up 2,231 sq m · recreational space 940 sq m
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Vaishnavi Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vaishnavi Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vaishnavi Heights

What is the possession date of Vaishnavi Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vaishnavi Heights in Thangewadi, Thane is 30 April 2027 — 29 months later than 30 July 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 29 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vaishnavi Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vaishnavi Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, already 29 months later than the 30 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vaishnavi Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "1) Initially we have taken three plots for development later stage one more adjacent plot’s development was merged with this ongoing development. After execution of the redevelopment agreement sanction of the revised plans and permission to construct took the time to start the construction work. 2) After all the permissions are in place there was shortage of Labors in the said area as various redevelopment are going on and most of the labor’s migration to native place in summer."; to 31 December 2026, giving the reason "1) Due to an unforeseen personal emergency, the appointed contractor had to return to his native place, resulting in the unavailability of both the contractor and his labour team. During this interim period, we initiated the process of identifying and onboarding a suitable replacement contractor. Given the due diligence required for selection, negotiations, and mobilization of a new workforce, there was an unavoidable delay in resuming site activities 2) The finishing work experienced a slight delay due to the unavailability of quality-approved materials. As we are committed to maintaining…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Vaishnavi Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vaishnavi Heights in Thangewadi, Thane is P51700051267.

Is Vaishnavi Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights is registered as P51700051267 and its status is "Registered and active".

What is the current construction status of Vaishnavi Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Vaishnavi Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vaishnavi Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights is registered on MahaRERA as P51700051267, its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vaishnavi Heights?

Vaishnavi Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vaishnavi Heights?

For a flat in Vaishnavi Heights (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Vaishnavi Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Vaishnavi Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vaishnavi Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Vaishnavi Heights have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: VAISHNAVI HEIGHTS (P51700023882, possession 1 Jan 2024). Check that your agreement names the registration of your own wing.

How can I get updates if Vaishnavi Heights's possession date changes?

The latest dates are on Vaishnavi Heights's MahaRERA page (P51700051267). GharKundli's Kundli Watch sends a free WhatsApp update on Vaishnavi Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vaishnavi Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights has 2 buildings filed: VAISHNAVI HEGHITS A WING with 7 floors and 38 units; VAISHNAVI HEIGHTS B WING with 7 floors and 21 units.

How big is the land of Vaishnavi Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights stands on 940 sq m of land (about 0.2 acres), with 2,231 sq m of sanctioned built-up area and 940 sq m of recreational open space.

What are the reviews of Vaishnavi Heights?

Google Maps has reviews of Vaishnavi Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vaishnavi Heights?

Vaishnavi Heights by VAISHNAVI CONSTRUCTION is in Thangewadi, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700051267, per GharKundli's check of MahaRERA records. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

How many flats are in Vaishnavi Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights has 49 homes in 2 towers registered on MahaRERA, and 63% of them are sold or booked.

When was Vaishnavi Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaishnavi Heights was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Does Vaishnavi Heights have any legal issues or court cases?

No court cases are listed for Vaishnavi Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vaishnavi Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VAISHNAVI CONSTRUCTION, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 582 projects in Kalyan (421301) →

Other projects by VAISHNAVI CONSTRUCTION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.