SHREEPATI CORONET

by SHREEPATI BUILD INFRA INVESTMENT LIMITED · Nana Chowk, Mumbai

Registered on MahaRERA under P51900000623, and currently active. Its completion date has moved from December 2019 to April 2027, 88 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on SHREEPATI CORONET

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900000623
Status
Registered and active
Builder
SHREEPATI BUILD INFRA INVESTMENT LIMITED
Location
Nana Chowk, Mumbai · 400010
Project type
Residential / Group Housing
Registered on
18 Jul 2017
Completion date at registration
December 2019
Latest completion date
April 2027
Delay so far
88 months
Homes
29
Towers
2
Complaints on MahaRERA
0
Court cases listed
3
Title report on file
Not found
Builder's other MahaRERA projects
2

Kundli Watch

SHREEPATI CORONET: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SHREEPATI CORONET

Is SHREEPATI CORONET registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI CORONET is registered as P51900000623 and its status is "Registered and active".

Where is SHREEPATI CORONET?

SHREEPATI CORONET by SHREEPATI BUILD INFRA INVESTMENT LIMITED is in Nana Chowk, Mumbai (pincode 400010), Maharashtra, and is registered on MahaRERA as P51900000623, per GharKundli's check of MahaRERA records.

When is possession of SHREEPATI CORONET due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREEPATI CORONET in Nana Chowk, Mumbai is 30 April 2027 — 88 months later than 30 December 2019, the date given at registration.

Does SHREEPATI CORONET have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SHREEPATI CORONET?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREEPATI BUILD INFRA INVESTMENT LIMITED, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400010

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.