Possession date of Pancharatna Panchratna Sapphire (MahaRERA P51700050689): 31 March 2027, moved from 31 March 2026 (12 months later). It has 129 homes, 70% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700050689, and currently active.

Source: MahaRERA website — records for P51700050689, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Pancharatna Panchratna Sapphire?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Pancharatna Panchratna Sapphire has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA24022619996)

    Reason the builder gave MahaRERA:
    “The Promoter respectfully submits that the project could not be completed within the originally declared timeline due to genuine administrative, financial and execution-related challenges encountered during the course of development. The de…” Read the full reason“The Promoter respectfully submits that the project could not be completed within the originally declared timeline due to genuine administrative, financial and execution-related challenges encountered during the course of development. The delay is neither wilful nor intentional. During implementation, the project experienced delays in obtaining certain revised approvals, technical permissions and compliance clearances from competent authorities. The time involved in scrutiny, documentation updates and inter-departmental coordination extended beyond the anticipated schedule, which impacted th…”

Source: Pancharatna Panchratna Sapphire’s extension records on MahaRERA (P51700050689), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Pancharatna Panchratna Sapphire

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700050689
Status
Registered and active
Builder
PANCHARATNA DEVELOPERS
Location
Kalyan, Thane · 421306
Project type
Others
Registered on
28 Apr 2023
Completion date at registration
March 2026
Latest completion date
March 2027
Delay so far
12 months
Homes
129
Sold or booked
70%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Pancharatna Panchratna Sapphire, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pancharatna Panchratna Sapphire every 1–2 months.

Pancharatna Panchratna Sapphire: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (18 floors, 138 units)
  • Land: 4,400 sq m (about 1.1 acres) · sanctioned built-up 9,544 sq m
  • Land, as filed: SURVEY NO33 HISSA NO 4(2)
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Pancharatna Panchratna Sapphire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Pancharatna Panchratna Sapphire: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Pancharatna Panchratna Sapphire

What is the possession date of Pancharatna Panchratna Sapphire?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pancharatna Panchratna Sapphire in Kalyan, Thane is 31 March 2027 — 12 months later than 31 March 2026, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Pancharatna Panchratna Sapphire?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Pancharatna Panchratna Sapphire's builder has filed on MahaRERA, the official one, is 31 March 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Pancharatna Panchratna Sapphire extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The Promoter respectfully submits that the project could not be completed within the originally declared timeline due to genuine administrative, financial and execution-related challenges encountered during the course of development. The delay is neither wilful nor intentional. During implementation, the project experienced delays in obtaining certain revised approvals, technical permissions and compliance clearances from competent authorities. The time involved in scrutiny, documentation updates and inter-departmental coordination extended beyond the anticipated schedule, which impacted th…".

What is the RERA number of Pancharatna Panchratna Sapphire?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pancharatna Panchratna Sapphire in Kalyan, Thane is P51700050689.

Is Pancharatna Panchratna Sapphire registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire is registered as P51700050689 and its status is "Registered and active".

What is the current construction status of Pancharatna Panchratna Sapphire? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING A is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Pancharatna Panchratna Sapphire have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Pancharatna Panchratna Sapphire safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire is registered on MahaRERA as P51700050689, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Pancharatna Panchratna Sapphire?

Pancharatna Panchratna Sapphire is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Pancharatna Panchratna Sapphire?

For a flat in Pancharatna Panchratna Sapphire (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Pancharatna Panchratna Sapphire received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire is still under construction, with 31 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Pancharatna Panchratna Sapphire uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Pancharatna Panchratna Sapphire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Pancharatna Panchratna Sapphire have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: PANCHRATNA SAPPHIRE (P51700080824, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.

How can I get updates if Pancharatna Panchratna Sapphire's possession date changes?

The latest dates are on Pancharatna Panchratna Sapphire's MahaRERA page (P51700050689). GharKundli's Kundli Watch sends a free WhatsApp update on Pancharatna Panchratna Sapphire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Pancharatna Panchratna Sapphire have?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire has one building filed: WING A with 18 floors and 138 units.

How big is the land of Pancharatna Panchratna Sapphire?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire stands on 4,400 sq m of land (about 1.1 acres), with 9,544 sq m of sanctioned built-up area.

What are the reviews of Pancharatna Panchratna Sapphire?

Google Maps has reviews of Pancharatna Panchratna Sapphire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Pancharatna Panchratna Sapphire?

Pancharatna Panchratna Sapphire by PANCHARATNA DEVELOPERS is in Kalyan, Thane, pincode 421306, Maharashtra, and is registered on MahaRERA as P51700050689, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO33 HISSA NO 4(2). GharKundli lists all 270 MahaRERA projects in Kalyan East (421306).

How many flats are in Pancharatna Panchratna Sapphire, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire has 129 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.

When was Pancharatna Panchratna Sapphire registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Pancharatna Panchratna Sapphire was registered on MahaRERA on 28 April 2023. GharKundli did not find a title report on the land on file there.

Does Pancharatna Panchratna Sapphire have any legal issues or court cases?

No court cases are listed for Pancharatna Panchratna Sapphire on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Pancharatna Panchratna Sapphire?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PANCHARATNA DEVELOPERS, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan East (421306)

All 270 projects in Kalyan East (421306) →

Other projects by PANCHARATNA DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.