Shree Gajanan Fortune City
by ARUN BALU PATIL · Kalyan, Thane 421301
What’s in the report? →Possession date of Shree Gajanan Fortune City (MahaRERA P51700013810): 30 December 2026, moved from 30 December 2024 (24 months later). It has 417 homes (1 BHK and 2 BHK, 333–575 sq ft carpet), 73% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700013810, and currently active.
Source: MahaRERA website — records for P51700013810, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shree Gajanan Fortune City?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shree Gajanan Fortune City has moved
30 December 2024
Completion date given when the project was registered
30 December 2026
Extended at the builder's request (MahaRERA application EXT51700024800)
Source: Shree Gajanan Fortune City’s extension records on MahaRERA (P51700013810), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Gajanan Fortune City
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700013810
- Status
- Registered and active
- Builder
- ARUN BALU PATIL
- Location
- Kalyan, Thane · 421301
- Project type
- Others
- Registered on
- 25 Oct 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 417
- Sold or booked
- 73%
- Towers
- 8
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Shree Gajanan Fortune City, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 100% | 100% |
| BUILDING B | 100% | 100% | 100% | 100% |
| BUILDING C | 100% | 100% | 100% | 100% |
| BUILDING D | 0% | 0% | 0% | 0% |
| BUILDING E | 100% | 100% | 100% | 75% |
| BUILDING F | 100% | 100% | 100% | 100% |
| BUILDING G | 100% | 100% | 100% | 100% |
| BUILDING E1 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING A: covers 5 floors
- BUILDING B: covers 5 floors
- BUILDING C: covers 5 floors
- BUILDING D: covers 5 floors
- BUILDING E: covers 5 floors
- BUILDING F: covers 5 floors
- BUILDING G: covers 5 floors
- BUILDING E1: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Gajanan Fortune City every 1–2 months.
Shree Gajanan Fortune City: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 333 – 570 | 319 |
| 2 BHK | 510 – 575 | 98 |
| Shops | 97 – 213 | 30 |
- Buildings: BUILDING A (5 floors, 40 units) · BUILDING B (5 floors, 59 units) · BUILDING C (5 floors, 59 units) · BUILDING D (5 floors, 40 units) · BUILDING E (5 floors, 66 units) · BUILDING F (5 floors, 64 units) · BUILDING G (5 floors, 53 units) · BUILDING E1 (8 floors, 66 units)
- Land: 17,000 sq m (about 4.2 acres) · sanctioned built-up 23,422 sq m · recreational space 1,722 sq m
- Land, as filed: SURVEY NO 65 P
- Map: Get directions
The builder’s record and reviews
Arun Balu Patil has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, 3 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Shree Gajanan Fortune City →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Gajanan Fortune City: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shree Gajanan Fortune City
What is the possession date of Shree Gajanan Fortune City?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Gajanan Fortune City in Kalyan, Thane is 30 December 2026 — 24 months later than 30 December 2024, the date given at registration.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shree Gajanan Fortune City?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Gajanan Fortune City's builder has filed on MahaRERA, the official one, is 30 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shree Gajanan Fortune City extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City's builder applied to MahaRERA to extend the completion date once: to 30 December 2026.
What is the RERA number of Shree Gajanan Fortune City?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Gajanan Fortune City in Kalyan, Thane is P51700013810.
Is Shree Gajanan Fortune City registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City is registered as P51700013810 and its status is "Registered and active".
What is the current construction status of Shree Gajanan Fortune City? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does Shree Gajanan Fortune City have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shree Gajanan Fortune City safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City is registered on MahaRERA as P51700013810, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shree Gajanan Fortune City?
Shree Gajanan Fortune City is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shree Gajanan Fortune City?
For a flat in Shree Gajanan Fortune City (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shree Gajanan Fortune City received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City is still under construction, with 30 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shree Gajanan Fortune City uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Gajanan Fortune City was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shree Gajanan Fortune City's possession date changes?
The latest dates are on Shree Gajanan Fortune City's MahaRERA page (P51700013810). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Gajanan Fortune City every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Gajanan Fortune City have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City has 8 buildings filed: BUILDING A with 5 floors and 40 units; BUILDING B with 5 floors and 59 units; BUILDING C with 5 floors and 59 units; BUILDING D with 5 floors and 40 units; BUILDING E with 5 floors and 66 units; BUILDING F with 5 floors and 64 units; and 2 more.
What are the flat sizes (carpet area) in Shree Gajanan Fortune City?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shree Gajanan Fortune City: 1 BHK: 333 to 570 sq ft carpet (319 homes); 2 BHK: 510 to 575 sq ft carpet (98 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Shree Gajanan Fortune City?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City stands on 17,000 sq m of land (about 4.2 acres), with 23,422 sq m of sanctioned built-up area and 1,722 sq m of recreational open space.
What is the track record of Shree Gajanan Fortune City's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Arun Balu Patil has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, 3 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Shree Gajanan Fortune City?
Google Maps has reviews of Shree Gajanan Fortune City written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shree Gajanan Fortune City?
Shree Gajanan Fortune City by ARUN BALU PATIL is in Kalyan, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700013810, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 65 P. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Shree Gajanan Fortune City, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City has 417 homes in 8 towers registered on MahaRERA, and 73% of them are sold or booked.
When was Shree Gajanan Fortune City registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Gajanan Fortune City was registered on MahaRERA on 25 October 2017. GharKundli did not find a title report on the land on file there.
Does Shree Gajanan Fortune City have any legal issues or court cases?
No court cases are listed for Shree Gajanan Fortune City on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shree Gajanan Fortune City?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARUN BALU PATIL, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shree Gajanan Fortune City
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan (421301)
All 582 projects in Kalyan (421301) →Other projects by ARUN BALU PATIL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.