Possession date of Mangeshi Crown: 31 July 2032. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1330002600843, and currently active. Its completion date is now July 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Mangeshi Crown?
How the possession date of Mangeshi Crown has moved
31 March 2032
Completion date given when the project was registered
31 July 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Mangeshi Crown’s extension records on MahaRERA (PM1330002600843), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mangeshi Crown
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1330002600843
- Status
- Registered and active
- Builder
- MANGESHI BUILDCON
- Location
- Kalyan, Thane · 421301
- Project type
- Mixed
- Registered on
- 18 Jun 2026
- Completion date at registration
- March 2032
- Latest completion date
- July 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 59
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Mangeshi Crown, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1 | 100% | 20% | 0% | 0% |
| Building No 2 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 1: covers 9 floors
- Building No 2: covers 5 floors
Latest CC order on MahaRERA: dated 11/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mangeshi Crown every month.
Mangeshi Crown: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 165 – 920 | 52 |
| 2 BHK | 517 – 667 | 37 |
| Shops | 146 – 912 | 32 |
| 3 BHK | 763 – 865 | 12 |
| 1 BHK | 336 – 353 | 10 |
- Buildings: Building No 1 (9 floors, 120 units) · Building No 2 (5 floors, 23 units)
- Car parking: 259 covered
- Land: 3,341 sq m (about 0.8 acres) · sanctioned built-up 8,400 sq m
- Boundaries filed include: 24 Meter Broad Road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Mangeshi Crown →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mangeshi Crown: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mangeshi Crown
What is the possession date of Mangeshi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mangeshi Crown in Kalyan, Thane is 31 July 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Mangeshi Crown?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mangeshi Crown's builder has filed on MahaRERA, the official one, is 31 July 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Mangeshi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mangeshi Crown in Kalyan, Thane is PM1330002600843.
Is Mangeshi Crown registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangeshi Crown is registered as PM1330002600843 and its status is "Registered and active".
What is the construction status of Mangeshi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangeshi Crown's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 20% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Mangeshi Crown have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Mangeshi Crown safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangeshi Crown is registered on MahaRERA as PM1330002600843, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Mangeshi Crown's possession date changes?
The latest dates are on Mangeshi Crown's MahaRERA page (PM1330002600843). GharKundli's Kundli Watch sends a free WhatsApp update on Mangeshi Crown every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mangeshi Crown have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangeshi Crown has 2 buildings filed: Building No 1 with 9 floors and 120 units; Building No 2 with 5 floors and 23 units.
What are the flat sizes (carpet area) in Mangeshi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Mangeshi Crown: 2 BHK: 517 to 667 sq ft carpet (37 homes); 3 BHK: 763 to 865 sq ft carpet (12 homes); 1 BHK: 336 to 353 sq ft carpet (10 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Mangeshi Crown have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 259 covered car parking spaces for Mangeshi Crown.
How big is the land of Mangeshi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangeshi Crown stands on 3,341 sq m of land (about 0.8 acres), with 8,400 sq m of sanctioned built-up area.
Where can I read reviews of Mangeshi Crown?
Google Maps has reviews of Mangeshi Crown written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mangeshi Crown?
Mangeshi Crown by MANGESHI BUILDCON is in Kalyan, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as PM1330002600843, per GharKundli's check of MahaRERA records. Its boundaries filed there include 24 Meter Broad Road.
How many homes are in Mangeshi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangeshi Crown has 59 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Mangeshi Crown registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangeshi Crown was registered on MahaRERA on 18 June 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on Mangeshi Crown?
No court cases are listed for Mangeshi Crown on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Mangeshi Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANGESHI BUILDCON.
Check it yourself on MahaRERA
- How to check the possession date of Mangeshi Crown
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421301
All 582 projects in Kalyan (421301) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.