by TUSHIRAJ REALTECH PRIVATE LIMITED · Kalyan Gaothan, ThaneAlso near Kalyan D.C
Possession date of SHUBH: 18 December 2026, moved from 31 January 2022 (59 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700021050, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHUBH?
How the possession date of SHUBH has moved
31 January 2022
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT51700010576)
Reason the builder gave MahaRERA: “The Change in Plan was applied to the Kalyan Dombivali Municipal Corporation and the the approval was received late on 24/05/2021 due to covid lockdown and restrictions implemented by government of Maharashtra”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51700013623)
Reason the builder gave MahaRERA:
“Extension for 1 year being sought under this application is justified due to the following : Disruption in the industry caused by post-COVID-19 and related lockdowns impacted the construction work for over a year. Further, the increase in t…” Read the full reason
“Extension for 1 year being sought under this application is justified due to the following : Disruption in the industry caused by post-COVID-19 and related lockdowns impacted the construction work for over a year. Further, the increase in the cost of construction materials due to inflation and the War in Ukraine further hampered the development work to avoid the high-cost burden on the home buyers. Also, there was a delay in obtaining complete CC as per the plan.”18 December 2026
Extended at the builder's request (MahaRERA application EA21072621810)
Reason the builder gave MahaRERA:
“The captioned project (SHUBH, Reg. No. P51700021050) has already obtained Occupancy Certificate from the Assistant Director of Town Planning, Kalyan Dombivali Municipal Corporation, and construction activity stands substantially complete. T…” Read the full reason
“The captioned project (SHUBH, Reg. No. P51700021050) has already obtained Occupancy Certificate from the Assistant Director of Town Planning, Kalyan Dombivali Municipal Corporation, and construction activity stands substantially complete. The registration has lapsed on the MahaRERA portal solely on account of a pending technical query relating to verification of the Occupancy Certificate, which was already submitted by the Promoter in response to the Technical Officer's earlier query dated on record, but verification remains pending completion at the Authority's end as on date. Additionally…”
Source: SHUBH’s extension records on MahaRERA (P51700021050), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHUBH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700021050
- Status
- Registered and active
- Builder
- TUSHIRAJ REALTECH PRIVATE LIMITED
- Location
- Kalyan Gaothan, Thane · 421301
- Project type
- Residential / Group Housing
- Registered on
- 31 May 2019
- Completion date at registration
- January 2022
- Latest completion date
- December 2026
- Delay so far
- 59 months
- Homes
- 26
- Sold or booked
- 92%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHUBH, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHUBH | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SHUBH: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHUBH every month.
SHUBH: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 Room Kitchen | 237 – 325 | 17 |
| 1 BHK | 389 – 391 | 7 |
| 2 BHK | 581 | 1 |
| Other | 386 | 1 |
- Buildings: SHUBH (8 floors, 26 units)
- Car parking: 4 covered
- Land: 386 sq m (about 0.1 acres) · sanctioned built-up 513 sq m
- Boundaries filed include: GHODEKHOT LANE ROAD, SHUBHCHINTAN SOCIETY, KDMC SCHOOL
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHUBH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHUBH: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHUBH
What is the possession date of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHUBH in Kalyan Gaothan, Thane is 18 December 2026 — 59 months later than 31 January 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHUBH?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHUBH's builder has filed on MahaRERA, the official one, is 18 December 2026, already 59 months later than the 31 January 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHUBH extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2022, giving the reason "The Change in Plan was applied to the Kalyan Dombivali Municipal Corporation and the the approval was received late on 24/05/2021 due to covid lockdown and restrictions implemented by government of Maharashtra"; to 31 December 2023, giving the reason "Extension for 1 year being sought under this application is justified due to the following : Disruption in the industry caused by post-COVID-19 and related lockdowns impacted the construction work for over a year. Further, the increase in the cost of construction materials due to inflation and the War in Ukraine further hampered the development work to avoid the high-cost burden on the home buyers. Also, there was a delay in obtaining complete CC as per the plan."; to 18 December 2026, giving the reason "The captioned project (SHUBH, Reg. No. P51700021050) has already obtained Occupancy Certificate from the Assistant Director of Town Planning, Kalyan Dombivali Municipal Corporation, and construction activity stands substantially complete. The registration has lapsed on the MahaRERA portal solely on account of a pending technical query relating to verification of the Occupancy Certificate, which was already submitted by the Promoter in response to the Technical Officer's earlier query dated on record, but verification remains pending completion at the Authority's end as on date. Additionally…".
What is the RERA number of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHUBH in Kalyan Gaothan, Thane is P51700021050.
Is SHUBH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH is registered as P51700021050 and its status is "Registered and active".
What is the construction status of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHUBH is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHUBH have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHUBH safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH is registered on MahaRERA as P51700021050, its completion date has moved 59 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHUBH's possession date changes?
The latest dates are on SHUBH's MahaRERA page (P51700021050). GharKundli's Kundli Watch sends a free WhatsApp update on SHUBH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHUBH have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH has one building filed: SHUBH with 8 floors and 26 units.
What are the flat sizes (carpet area) in SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHUBH: 1 Room Kitchen: 237 to 325 sq ft carpet (17 homes); 1 BHK: 389 to 391 sq ft carpet (7 homes); 2 BHK: 581 sq ft carpet (1 homes); Other: 386 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SHUBH have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 4 covered car parking spaces for SHUBH.
How big is the land of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH stands on 386 sq m of land (about 0.1 acres), with 513 sq m of sanctioned built-up area.
Where can I read reviews of SHUBH?
Google Maps has reviews of SHUBH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHUBH?
SHUBH by TUSHIRAJ REALTECH PRIVATE LIMITED is in Kalyan Gaothan, Thane (pincode 421301), near Kalyan D.C, Maharashtra, and is registered on MahaRERA as P51700021050, per GharKundli's check of MahaRERA records. Its boundaries filed there include GHODEKHOT LANE ROAD, SHUBHCHINTAN SOCIETY, KDMC SCHOOL.
How many homes are in SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH has 26 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.
When was SHUBH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH was registered on MahaRERA on 31 May 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SHUBH?
No court cases are listed for SHUBH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TUSHIRAJ REALTECH PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of SHUBH
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in pincode 421301
All 582 projects in Kalyan (421301) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.