ART SHREE
by ART ENTERPRISES · Kalyan, Thane
Possession date of ART SHREE: 30 April 2027, moved from 31 March 2026 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700055811, and currently active. Its completion date has moved from March 2026 to April 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ART SHREE?
How the possession date of ART SHREE has moved
31 March 2026
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA14072621753)
Reason the builder gave MahaRERA:
“An additional floor has been approved by the concerned authority, resulting in an increase in the project's FSI and overall scope of work. we kindly request an extension of the project completion date until 31st December 2026 to complete th…” Read the full reason
“An additional floor has been approved by the concerned authority, resulting in an increase in the project's FSI and overall scope of work. we kindly request an extension of the project completion date until 31st December 2026 to complete the additional construction work.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ART SHREE’s extension records on MahaRERA (P51700055811), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ART SHREE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700055811
- Status
- Registered and active
- Builder
- ART ENTERPRISES
- Location
- Kalyan, Thane · 421301
- Project type
- Residential / Group Housing
- Registered on
- 22 Apr 2024
- Completion date at registration
- March 2026
- Latest completion date
- April 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Sold or booked
- 21%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ART SHREE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ART SHREE | 100% | 80% | 60% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- ART SHREE: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ART SHREE every month.
ART SHREE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 Room Kitchen | 240 – 253 | 7 |
| 1 BHK | 336 – 351 | 7 |
- Buildings: ART SHREE (8 floors, 14 units)
- Land: 145 sq m (about 0.0 acres) · sanctioned built-up 560 sq m
- Boundaries filed include: Asha Sadan Society, Siddheshwar Society
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ART SHREE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ART SHREE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ART SHREE
What is the possession date of ART SHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ART SHREE in Kalyan, Thane is 30 April 2027 — 9 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ART SHREE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ART SHREE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 9 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ART SHREE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "An additional floor has been approved by the concerned authority, resulting in an increase in the project's FSI and overall scope of work. we kindly request an extension of the project completion date until 31st December 2026 to complete the additional construction work.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ART SHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ART SHREE in Kalyan, Thane is P51700055811.
Is ART SHREE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE is registered as P51700055811 and its status is "Registered and active".
What is the construction status of ART SHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ART SHREE is 80% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does ART SHREE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ART SHREE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE is registered on MahaRERA as P51700055811, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ART SHREE's possession date changes?
The latest dates are on ART SHREE's MahaRERA page (P51700055811). GharKundli's Kundli Watch sends a free WhatsApp update on ART SHREE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ART SHREE have?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE has one building filed: ART SHREE with 8 floors and 14 units.
What are the flat sizes (carpet area) in ART SHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ART SHREE: 1 Room Kitchen: 240 to 253 sq ft carpet (7 homes); 1 BHK: 336 to 351 sq ft carpet (7 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of ART SHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE stands on 145 sq m of land (about 0.0 acres), with 560 sq m of sanctioned built-up area.
Where can I read reviews of ART SHREE?
Google Maps has reviews of ART SHREE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ART SHREE?
ART SHREE by ART ENTERPRISES is in Kalyan, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700055811, per GharKundli's check of MahaRERA records. Its boundaries filed there include Asha Sadan Society, Siddheshwar Society.
How many homes are in ART SHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE has 14 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.
When was ART SHREE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ART SHREE was registered on MahaRERA on 22 April 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on ART SHREE?
No court cases are listed for ART SHREE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ART SHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ART ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of ART SHREE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 421301
All 582 projects in Kalyan (421301) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.