Vasudha Geetant Ashray
by VASUDHA CONSTRUCTION COMPANY · Chikanghar, Thane 421301Registered on MahaRERA as “GEETANT ASHRAY”
What’s in the report? →Possession date of Vasudha Geetant Ashray (MahaRERA P51700050597): 31 December 2025, moved from 31 December 2024 (12 months later), and it has already passed. It has 28 homes, 57% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700050597. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700050597, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Vasudha Geetant Ashray?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vasudha Geetant Ashray has moved
31 December 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT51700025919)
Reason the builder gave MahaRERA:
“the project has faced unforeseen delays due to ongoing road construction work in the vicinity, which has significantly impacted the supply of construction materials and availability of labour. The restricted "movement of transportation vehi…” Read the full reason
“the project has faced unforeseen delays due to ongoing road construction work in the vicinity, which has significantly impacted the supply of construction materials and availability of labour. The restricted "movement of transportation vehicles and workers has adversely affected the progress of our project, causing unavoidable delays beyond our control”31 December 2025
Extended at the builder's request (MahaRERA application EA23072502169)
Reason the builder gave MahaRERA:
“The Project got delayed due to an unforeseen shortage of labour caused by health crises, migration of workers, etc. Despite our best efforts to secure adequate labour resources, the unavailability of skilled labour has led to unavoidable se…” Read the full reason
“The Project got delayed due to an unforeseen shortage of labour caused by health crises, migration of workers, etc. Despite our best efforts to secure adequate labour resources, the unavailability of skilled labour has led to unavoidable setbacks in the progress of the work. Once the above work is completed, we will make application for Completion Certificate (CC)/Occupancy Certificate (OC) with the respective Municipal Authority. Obtaining CC/OC will take a few months; hence we make a humble request to you to provide an extension.”
Source: Vasudha Geetant Ashray’s extension records on MahaRERA (P51700050597), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vasudha Geetant Ashray
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700050597
- Status
- Lapsed (registration period ended)
- Builder
- VASUDHA CONSTRUCTION COMPANY
- Location
- Chikanghar, Thane · 421301
- Project type
- Others
- Registered on
- 21 Apr 2023
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 28
- Sold or booked
- 57%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Vasudha Geetant Ashray, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GEETANT ASHRAY | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- GEETANT ASHRAY: covers GROUND TO FIRST, FIRST TO SIXTH, SIXTH TO SEVENTH FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vasudha Geetant Ashray every 1–2 months.
Vasudha Geetant Ashray: buildings, flats and land, as filed on MahaRERA
- Buildings: GEETANT ASHRAY (9 floors, 37 units)
- Land: 780 sq m (about 0.2 acres) · sanctioned built-up 1,880 sq m
- Boundaries filed include: AADARSH COOP HSG SOCIETY, VASUNDHARA COOP HSG SOCIETY, VIDYA MANDIR SCHOOL
- Land, as filed: SURVEY NO 42/A HISSA NO 19B/16
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vasudha Geetant Ashray →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vasudha Geetant Ashray: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vasudha Geetant Ashray
What is the possession date of Vasudha Geetant Ashray?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vasudha Geetant Ashray in Chikanghar, Thane is 31 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vasudha Geetant Ashray?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vasudha Geetant Ashray's builder has filed on MahaRERA, the official one, is 31 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vasudha Geetant Ashray extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "the project has faced unforeseen delays due to ongoing road construction work in the vicinity, which has significantly impacted the supply of construction materials and availability of labour. The restricted "movement of transportation vehicles and workers has adversely affected the progress of our project, causing unavoidable delays beyond our control"; to 31 December 2025, giving the reason "The Project got delayed due to an unforeseen shortage of labour caused by health crises, migration of workers, etc. Despite our best efforts to secure adequate labour resources, the unavailability of skilled labour has led to unavoidable setbacks in the progress of the work. Once the above work is completed, we will make application for Completion Certificate (CC)/Occupancy Certificate (OC) with the respective Municipal Authority. Obtaining CC/OC will take a few months; hence we make a humble request to you to provide an extension.".
What is the RERA number of Vasudha Geetant Ashray?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vasudha Geetant Ashray in Chikanghar, Thane is P51700050597.
Is Vasudha Geetant Ashray registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray is registered as P51700050597 and its status is "Lapsed (registration period ended)".
What is the current construction status of Vasudha Geetant Ashray? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GEETANT ASHRAY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vasudha Geetant Ashray have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vasudha Geetant Ashray safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray is registered on MahaRERA as P51700050597, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vasudha Geetant Ashray?
Vasudha Geetant Ashray isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vasudha Geetant Ashray?
For a flat in Vasudha Geetant Ashray (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Vasudha Geetant Ashray received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Vasudha Geetant Ashray?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Vasudha Geetant Ashray uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vasudha Geetant Ashray was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vasudha Geetant Ashray's possession date changes?
The latest dates are on Vasudha Geetant Ashray's MahaRERA page (P51700050597). GharKundli's Kundli Watch sends a free WhatsApp update on Vasudha Geetant Ashray every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vasudha Geetant Ashray have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray has one building filed: GEETANT ASHRAY with 9 floors and 37 units.
How big is the land of Vasudha Geetant Ashray?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray stands on 780 sq m of land (about 0.2 acres), with 1,880 sq m of sanctioned built-up area.
What are the reviews of Vasudha Geetant Ashray?
Google Maps has reviews of Vasudha Geetant Ashray written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vasudha Geetant Ashray?
Vasudha Geetant Ashray by VASUDHA CONSTRUCTION COMPANY is in Chikanghar, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700050597, per GharKundli's check of MahaRERA records. Its boundaries filed there include AADARSH COOP HSG SOCIETY, VASUNDHARA COOP HSG SOCIETY, VIDYA MANDIR SCHOOL. Its land is filed as SURVEY NO 42/A HISSA NO 19B/16. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Vasudha Geetant Ashray, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray has 28 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.
When was Vasudha Geetant Ashray registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vasudha Geetant Ashray was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.
Does Vasudha Geetant Ashray have any legal issues or court cases?
1 court case is listed for Vasudha Geetant Ashray on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Vasudha Geetant Ashray?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VASUDHA CONSTRUCTION COMPANY.
Check it yourself on MahaRERA
- How to check the possession date of Vasudha Geetant Ashray
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kalyan (421301)
- Keshar Aagan Cooperative Housing Society
- Pinnacle West
- SKF Harmonie
- Balaji Exotica Building Type D Phase III
- Nakshatra
- V Ten Residency
- Gayatri Niwas
- Madhav Height
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.