V TEN RESIDENCY
by V TEN REALTY PRIVATE LIMITED · Chikanghar, Thane
Possession: V TEN RESIDENCY is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700005357. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about V TEN RESIDENCY?
How the possession date of V TEN RESIDENCY has moved
30 December 2020
Completion date given when the project was registered
31 August 2023
Extended at the builder's request (MahaRERA application EXT51700010832)
Reason the builder gave MahaRERA: “1. Due to corona, various lockdown and non availability of labour 2. Due to Change in plan layout and as per permission granted by KDMC”
29 February 2024
Revised completion date on MahaRERA
Source: V TEN RESIDENCY’s extension records on MahaRERA (P51700005357), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on V TEN RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the February 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700005357
- Status
- Completed
- Builder
- V TEN REALTY PRIVATE LIMITED
- Location
- Chikanghar, Thane · 421301
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- February 2024
- Delay so far
- 38 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of V TEN RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MAHANANDA | 100% | 100% | 50% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on V TEN RESIDENCY every month.
V TEN RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: MAHANANDA (9 floors)
- Land: 2,930 sq m (about 0.7 acres) · sanctioned built-up 1,525 sq m · recreational space 413 sq m
The builder’s record and reviews
Shri Kalki Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.
Read Google reviews of V TEN RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
V TEN RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about V TEN RESIDENCY
What is the possession date of V TEN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for V TEN RESIDENCY in Chikanghar, Thane is 29 February 2024 — 38 months later than 30 December 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for V TEN RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date V TEN RESIDENCY's builder has filed on MahaRERA, the official one, is 29 February 2024, already 38 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of V TEN RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 August 2023, giving the reason "1. Due to corona, various lockdown and non availability of labour 2. Due to Change in plan layout and as per permission granted by KDMC".
What is the RERA number of V TEN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of V TEN RESIDENCY in Chikanghar, Thane is P51700005357.
Is V TEN RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY is registered as P51700005357 and its status is "Completed".
What is the construction status of V TEN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on MAHANANDA is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does V TEN RESIDENCY have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is V TEN RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY is registered on MahaRERA as P51700005357, its MahaRERA status is "Completed", its completion date has moved 38 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if V TEN RESIDENCY's possession date changes?
The latest dates are on V TEN RESIDENCY's MahaRERA page (P51700005357). GharKundli's Kundli Watch sends a free WhatsApp update on V TEN RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does V TEN RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY has one building filed: MAHANANDA with 9 floors.
How big is the land of V TEN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY stands on 2,930 sq m of land (about 0.7 acres), with 1,525 sq m of sanctioned built-up area and 413 sq m of recreational open space.
What is the track record of V TEN RESIDENCY's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri Kalki Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of V TEN RESIDENCY?
Google Maps has reviews of V TEN RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is V TEN RESIDENCY?
V TEN RESIDENCY by V TEN REALTY PRIVATE LIMITED is in Chikanghar, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700005357, per GharKundli's check of MahaRERA records.
How many homes are in V TEN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY has 24 homes in 1 tower registered on MahaRERA.
When was V TEN RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), V TEN RESIDENCY was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on V TEN RESIDENCY?
No court cases are listed for V TEN RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of V TEN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is V TEN REALTY PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of V TEN RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Chikanghar
- KESHAR AAGAN COOPERATIVE HOUSING SOCIETY
- GEETANT ASHRAY
- PINNACLE WEST
- SKF HARMONIE
- BALAJI EXOTICA BUILDING TYPE D PHASE III
- Nakshatra
- GAYATRI NIWAS
- MADHAV HEIGHT
Other projects by V TEN REALTY PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.