SHISHODIA ARCADE C WING
by JAGATVIRSINGH SHISHODIA · Kalyan, Thane
Registered on MahaRERA under P51700076598, and currently active. Its completion date has moved from December 2026 to April 2027, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on SHISHODIA ARCADE C WING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700076598
- Status
- Registered and active
- Builder
- JAGATVIRSINGH SHISHODIA
- Location
- Kalyan, Thane · 421301
- Project type
- Residential / Group Housing
- Registered on
- 18 Jun 2024
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- Delay so far
- 4 months
- Homes
- 60
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
SHISHODIA ARCADE C WING: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHISHODIA ARCADE C WING
Is SHISHODIA ARCADE C WING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHISHODIA ARCADE C WING is registered as P51700076598 and its status is "Registered and active".
Where is SHISHODIA ARCADE C WING?
SHISHODIA ARCADE C WING by JAGATVIRSINGH SHISHODIA is in Kalyan, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700076598, per GharKundli's check of MahaRERA records.
When is possession of SHISHODIA ARCADE C WING due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHISHODIA ARCADE C WING in Kalyan, Thane is 30 April 2027 — 4 months later than 31 December 2026, the date given at registration.
Does SHISHODIA ARCADE C WING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of SHISHODIA ARCADE C WING?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAGATVIRSINGH SHISHODIA.
Other projects in pincode 421301
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.