Radheshyam Royal

by RADHEYSHYAM ROSHANLAL GUPTA · diaghar, Thane 421301

What’s in the report? →

Possession date of Radheshyam Royal (MahaRERA P51700006917): 7 August 2024, moved from 31 December 2019 (56 months later), and it has already passed. It has 56 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700006917. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700006917, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2024) has passed.

What do you want to know about Radheshyam Royal?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Radheshyam Royal has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51700002499)

    Reason the builder gave MahaRERA:
    “1) Due to amendment Permission /Commencement Certificate , the original plan which was Lower Stilt + Ground + 1 to 3rd + 4th (Pt) Floor in RERA was ammended/ upgraded to Lower Stilt + Ground + 1 to 5th + 6th (Pt) Floor by the addition of Pr…” Read the full reason“1) Due to amendment Permission /Commencement Certificate , the original plan which was Lower Stilt + Ground + 1 to 3rd + 4th (Pt) Floor in RERA was ammended/ upgraded to Lower Stilt + Ground + 1 to 5th + 6th (Pt) Floor by the addition of Premium FSI, for which the time required for the execution of this additional floor will be more. (attached amendment certificate and plan) 2) Due to heavy recession in the real estate region, there are no bookings in the project, which had become very difficult for the completion of the project in time.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51700009405)

    Reason the builder gave MahaRERA:
    “DUE TO HUGE PANDEMIC EFFECT AND COMPLETE LOCKDOWN IN MAHARASHTRA AND SHORTAGE OF MIGRANT LABOURERS AND SHORTAGE IN SUPPLY OF BUILDING MATERIALS AND ESSENTIAL DUE TO CORONA VIRUS, THE PROJECT COULD NOT BE COMPLETED IN TIME. ALSO THE PLAN HAS…” Read the full reason“DUE TO HUGE PANDEMIC EFFECT AND COMPLETE LOCKDOWN IN MAHARASHTRA AND SHORTAGE OF MIGRANT LABOURERS AND SHORTAGE IN SUPPLY OF BUILDING MATERIALS AND ESSENTIAL DUE TO CORONA VIRUS, THE PROJECT COULD NOT BE COMPLETED IN TIME. ALSO THE PLAN HAS BEEN REVISED FROM LOWER STILT + GROUND + 4 PART TO LOWER STILT + GROUND + 6 PART. HENCE EXTENSION REQUIRED FOR THE COMPLETION OF PROJECT.”
  4. 7 August 2024

    Extended at the builder's request (MahaRERA application EXT51700027143)

    Reason the builder gave MahaRERA:
    “Dear Sir, Earlier this week we had uploaded Occupancy certificate (OC) and Form 4 to update the completion of the above-mentioned project, however on December 28, 2024 we received a communication from MahaRERA that the application for exten…” Read the full reason“Dear Sir, Earlier this week we had uploaded Occupancy certificate (OC) and Form 4 to update the completion of the above-mentioned project, however on December 28, 2024 we received a communication from MahaRERA that the application for extension is required to be uploaded as the date of OC has exceeded the proposed completion date as mentioned on RERA portal. As directed by the authority and to comply with the requirements of the Act we hereby apply for post-facto extension of the project. We state that 1. We had submitted application for OC to the Thane Municipal Corporation on 4th March 20…”

Source: Radheshyam Royal’s extension records on MahaRERA (P51700006917), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Radheshyam Royal

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700006917
Status
Lapsed (registration period ended)
Builder
RADHEYSHYAM ROSHANLAL GUPTA
Location
diaghar, Thane · 421301
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
December 2019
Latest completion date
August 2024
Delay so far
56 months
Homes
56
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Radheshyam Royal, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RADHEYSHYAM ROYAL100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Radheshyam Royal every 1–2 months.

Radheshyam Royal: buildings, flats and land, as filed on MahaRERA

  • Buildings: RADHEYSHYAM ROYAL (8 floors)
  • Land: 1,600 sq m (about 0.4 acres) · sanctioned built-up 1,560 sq m · recreational space 242 sq m
  • Boundaries filed include: HIGHWAY
  • Land, as filed: 80-2C AND 80-3
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Radheshyam Royal →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Radheshyam Royal: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Radheshyam Royal

What is the possession date of Radheshyam Royal?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Radheshyam Royal in diaghar, Thane is 7 August 2024 — 56 months later than 31 December 2019, the date given at registration. That date has already passed.

The date has already moved 56 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Radheshyam Royal?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Radheshyam Royal's builder has filed on MahaRERA, the official one, is 7 August 2024, already 56 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Radheshyam Royal extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "1) Due to amendment Permission /Commencement Certificate , the original plan which was Lower Stilt + Ground + 1 to 3rd + 4th (Pt) Floor in RERA was ammended/ upgraded to Lower Stilt + Ground + 1 to 5th + 6th (Pt) Floor by the addition of Premium FSI, for which the time required for the execution of this additional floor will be more. (attached amendment certificate and plan) 2) Due to heavy recession in the real estate region, there are no bookings in the project, which had become very difficult for the completion of the project in time."; to 31 December 2023, giving the reason "DUE TO HUGE PANDEMIC EFFECT AND COMPLETE LOCKDOWN IN MAHARASHTRA AND SHORTAGE OF MIGRANT LABOURERS AND SHORTAGE IN SUPPLY OF BUILDING MATERIALS AND ESSENTIAL DUE TO CORONA VIRUS, THE PROJECT COULD NOT BE COMPLETED IN TIME. ALSO THE PLAN HAS BEEN REVISED FROM LOWER STILT + GROUND + 4 PART TO LOWER STILT + GROUND + 6 PART. HENCE EXTENSION REQUIRED FOR THE COMPLETION OF PROJECT."; to 7 August 2024, giving the reason "Dear Sir, Earlier this week we had uploaded Occupancy certificate (OC) and Form 4 to update the completion of the above-mentioned project, however on December 28, 2024 we received a communication from MahaRERA that the application for extension is required to be uploaded as the date of OC has exceeded the proposed completion date as mentioned on RERA portal. As directed by the authority and to comply with the requirements of the Act we hereby apply for post-facto extension of the project. We state that 1. We had submitted application for OC to the Thane Municipal Corporation on 4th March 20…".

What is the RERA number of Radheshyam Royal?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Radheshyam Royal in diaghar, Thane is P51700006917.

Is Radheshyam Royal registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal is registered as P51700006917 and its status is "Lapsed (registration period ended)".

What is the current construction status of Radheshyam Royal? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on RADHEYSHYAM ROYAL is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Radheshyam Royal have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Radheshyam Royal safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal is registered on MahaRERA as P51700006917, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 56 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Radheshyam Royal?

Radheshyam Royal isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Radheshyam Royal?

For a flat in Radheshyam Royal (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Radheshyam Royal received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 7 August 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Radheshyam Royal?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (7 August 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Radheshyam Royal uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Radheshyam Royal was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Radheshyam Royal's possession date changes?

The latest dates are on Radheshyam Royal's MahaRERA page (P51700006917). GharKundli's Kundli Watch sends a free WhatsApp update on Radheshyam Royal every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Radheshyam Royal have?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal has one building filed: RADHEYSHYAM ROYAL with 8 floors.

How big is the land of Radheshyam Royal?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal stands on 1,600 sq m of land (about 0.4 acres), with 1,560 sq m of sanctioned built-up area and 242 sq m of recreational open space.

What are the reviews of Radheshyam Royal?

Google Maps has reviews of Radheshyam Royal written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Radheshyam Royal?

Radheshyam Royal by RADHEYSHYAM ROSHANLAL GUPTA is in diaghar, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700006917, per GharKundli's check of MahaRERA records. Its boundaries filed there include HIGHWAY. Its land is filed as 80-2C AND 80-3. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

How many flats are in Radheshyam Royal?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal has 56 homes in 1 tower registered on MahaRERA.

When was Radheshyam Royal registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Radheshyam Royal was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Does Radheshyam Royal have any legal issues or court cases?

No court cases are listed for Radheshyam Royal on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Radheshyam Royal?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RADHEYSHYAM ROSHANLAL GUPTA.

Other projects in Thane

All 582 projects in Kalyan (421301) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.