Ganga Residency
by MR RAVI YALLAPPA VHATKAR · Ulhasnagar 4, Thane 421004Also near Sambhaji Chowk, Kurla Camp, Ambernath West
What’s in the report? →Possession date of Ganga Residency (MahaRERA P51700051627): 30 January 2027, moved from 31 December 2025 (9 months later). It has 14 homes, 53% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700051627, and currently active. Its completion date has moved from December 2025 to January 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700051627, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Ganga Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ganga Residency has moved
31 December 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA09052620893)
Reason the builder gave MahaRERA:
“The project completion has been delayed due to pending balance construction and finishing work. Further, the DP Road work being carried out by Ulhasnagar Municipal Corporation has also affected the progress of the project. Therefore, extens…” Read the full reason
“The project completion has been delayed due to pending balance construction and finishing work. Further, the DP Road work being carried out by Ulhasnagar Municipal Corporation has also affected the progress of the project. Therefore, extension is required to complete the remaining work and obtain Completion Certificate.”30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ganga Residency’s extension records on MahaRERA (P51700051627), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ganga Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700051627
- Status
- Registered and active
- Builder
- MR RAVI YALLAPPA VHATKAR
- Location
- Ulhasnagar 4, Thane · 421004
- Project type
- Others
- Registered on
- 27 Jun 2023
- Completion date at registration
- December 2025
- Latest completion date
- January 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Sold or booked
- 53%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Ganga Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GANGA RESIDENCY | 100% | 100% | 93% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- GANGA RESIDENCY: covers Ground+7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ganga Residency every 1–2 months.
Ganga Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: GANGA RESIDENCY (8 floors, 15 units)
- Car parking: 2 covered, 4 open
- Land: 231 sq m (about 0.1 acres) · sanctioned built-up 642 sq m
- Land, as filed: U NO 81 CHALTA NO 152 152 A CTS NO 31116 SHEET NO 22 ULHASNAGAR 421004
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Ganga Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ganga Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ganga Residency
What is the possession date of Ganga Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ganga Residency in Ulhasnagar 4, Thane is 30 January 2027 — 9 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 9 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Ganga Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ganga Residency's builder has filed on MahaRERA, the official one, is 30 January 2027, already 9 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ganga Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "The project completion has been delayed due to pending balance construction and finishing work. Further, the DP Road work being carried out by Ulhasnagar Municipal Corporation has also affected the progress of the project. Therefore, extension is required to complete the remaining work and obtain Completion Certificate.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Ganga Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ganga Residency in Ulhasnagar 4, Thane is P51700051627.
Is Ganga Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency is registered as P51700051627 and its status is "Registered and active".
What is the current construction status of Ganga Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GANGA RESIDENCY is 100% done and internal work 93%. GharKundli's full report compares construction progress with the deadline.
Does Ganga Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ganga Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency is registered on MahaRERA as P51700051627, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ganga Residency?
Ganga Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ganga Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Ganga Residency: gharkundli.com/tools/property-cost-calculator
Has Ganga Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency is still under construction, with 30 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Ganga Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ganga Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ganga Residency's possession date changes?
The latest dates are on Ganga Residency's MahaRERA page (P51700051627). GharKundli's Kundli Watch sends a free WhatsApp update on Ganga Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ganga Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency has one building filed: GANGA RESIDENCY with 8 floors and 15 units.
How much parking does Ganga Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 2 covered and 4 open car parking spaces for Ganga Residency.
How big is the land of Ganga Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency stands on 231 sq m of land (about 0.1 acres), with 642 sq m of sanctioned built-up area.
What are the reviews of Ganga Residency?
Google Maps has reviews of Ganga Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ganga Residency?
Ganga Residency by MR RAVI YALLAPPA VHATKAR is in Ulhasnagar 4, Thane, pincode 421004 (near Sambhaji Chowk, Kurla Camp, Ambernath West), Maharashtra, and is registered on MahaRERA as P51700051627, per GharKundli's check of MahaRERA records. Its land is filed as U NO 81 CHALTA NO 152 152 A CTS NO 31116 SHEET NO 22 ULHASNAGAR 421004. GharKundli lists all 68 MahaRERA projects in Ulhasnagar (421004).
How many flats are in Ganga Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency has 14 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.
When was Ganga Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Residency was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.
Does Ganga Residency have any legal issues or court cases?
No court cases are listed for Ganga Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ganga Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MR RAVI YALLAPPA VHATKAR.
Check it yourself on MahaRERA
- How to check the possession date of Ganga Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ulhasnagar (421004)
- Emerald Tower
- Jankrishna Heights
- A N Empire
- Sunshine Avenue
- Vimal Raj Residency
- Sea Green Aurus
- Jannak Residency
- Yash Apartment
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.