Sanghvi Parsssva Elysium
by Sanghvi Parsssva Buildcon LLP · GS Ward, Mumbai
Registered on MahaRERA under PM1170002500896, and currently active. Its completion date has moved from December 2029 to April 2030, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PM1170002500896
- Status
- Registered and active
- Builder
- Sanghvi Parsssva Buildcon LLP
- Location
- GS Ward, Mumbai · 400013
- Project type
- Mixed
- Registered on
- 22 Sep 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- Delay so far
- 4 months
- Homes
- 88
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
GharKundli’s full report on Sanghvi Parsssva Elysium
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
Sanghvi Parsssva Elysium: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Sanghvi Parsssva Elysium
Is Sanghvi Parsssva Elysium registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Parsssva Elysium is registered as PM1170002500896 and its status is "Registered and active".
Where is Sanghvi Parsssva Elysium?
Sanghvi Parsssva Elysium by Sanghvi Parsssva Buildcon LLP is in GS Ward, Mumbai (pincode 400013), Maharashtra, and is registered on MahaRERA as PM1170002500896, per GharKundli's check of MahaRERA records.
When is possession of Sanghvi Parsssva Elysium due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sanghvi Parsssva Elysium in GS Ward, Mumbai is 30 April 2030 — 4 months later than 31 December 2029, the date given at registration.
Does Sanghvi Parsssva Elysium have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Sanghvi Parsssva Elysium?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sanghvi Parsssva Buildcon LLP.
Other projects in pincode 400013
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.