Possession date of Farida Heights: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1170002500991, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Farida Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Farida Heights has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Farida Heights’s extension records on MahaRERA (PM1170002500991), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Farida Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1170002500991
Status
Registered and active
Builder
Ideal Life Spaces LLP
Location
C Ward, Mumbai · 400003
Project type
Mixed
Registered on
29 Sep 2025
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
75
Sold or booked
10%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Farida Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Farida Heights100%100%90%0%

Commencement certificate (CC), as filed on MahaRERA

  • Farida Heights: covers 23 floors

Latest CC order on MahaRERA: dated 23/03/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Farida Heights every month.

Farida Heights: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK348 – 39173
Shops141 – 2216
Office Space185 – 3953
Other215 – 2882

The builder’s record and reviews

Green Environment Constructions (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Farida Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Farida Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Farida Heights

What is the possession date of Farida Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Farida Heights in C Ward, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Farida Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Farida Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Farida Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Farida Heights in C Ward, Mumbai is PM1170002500991.

Is Farida Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Farida Heights is registered as PM1170002500991 and its status is "Registered and active".

What is the construction status of Farida Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Farida Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Farida Heights is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Farida Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Farida Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Farida Heights is registered on MahaRERA as PM1170002500991, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Farida Heights's possession date changes?

The latest dates are on Farida Heights's MahaRERA page (PM1170002500991). GharKundli's Kundli Watch sends a free WhatsApp update on Farida Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Farida Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Farida Heights has one building filed: Farida Heights with 23 floors and 84 units.

What are the flat sizes (carpet area) in Farida Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Farida Heights: 1 BHK: 348 to 391 sq ft carpet (73 homes); Other: 215 to 288 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Farida Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 19 covered car parking spaces for Farida Heights.

How big is the land of Farida Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Farida Heights stands on 410 sq m of land (about 0.1 acres), with 3,204 sq m of sanctioned built-up area.

What is the track record of Farida Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Green Environment Constructions (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Farida Heights?

Google Maps has reviews of Farida Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Farida Heights?

Farida Heights by Ideal Life Spaces LLP is in C Ward, Mumbai (pincode 400003), near Girgaon, Bhuleshwar, Masjid Bunder, Maharashtra, and is registered on MahaRERA as PM1170002500991, per GharKundli's check of MahaRERA records.

How many homes are in Farida Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Farida Heights has 75 homes in 1 tower registered on MahaRERA, and 10% of them are sold or booked.

When was Farida Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Farida Heights was registered on MahaRERA on 29 September 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on Farida Heights?

No court cases are listed for Farida Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Farida Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ideal Life Spaces LLP.

All projects with possession due in 2027 in Mumbai City →

Other projects in Mumbai City

All 20 projects in Mandvi (400003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.