Morya Heights
by MORYA DEVELOPERS · Vashind, Thane 421601
What’s in the report? →Possession date of Morya Heights (MahaRERA P51700053294): 30 October 2026, and it has already passed. It has 72 homes, 43% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700053294, and currently active. Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700053294, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Morya Heights?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Morya Heights has moved
30 June 2026
Completion date given when the project was registered
30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Morya Heights’s extension records on MahaRERA (P51700053294), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Morya Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700053294
- Status
- Registered and active
- Builder
- MORYA DEVELOPERS
- Location
- Vashind, Thane · 421601
- Project type
- Residential / Group Housing
- Registered on
- 23 Oct 2023
- Completion date at registration
- June 2026
- Latest completion date
- October 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 72
- Sold or booked
- 43%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Morya Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 01 | 100% | 100% | 100% | 100% |
| Building No 02 | 100% | 100% | 0% | 100% |
Showing 2 of 3 towers.
Commencement certificate (CC), as filed on MahaRERA
- Building No 01: covers 8 floors
- MORYA HEIGHT: covers 3 floors
- Building No 02: covers 4 floors
Latest CC order on MahaRERA: dated 23/07/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Morya Heights every 1–2 months.
Morya Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 01 (8 floors, 67 units) · MORYA HEIGHT (7 floors) · Building No 02 (4 floors, 9 units)
- Car parking: 15 open
- Land: 1,717 sq m (about 0.4 acres) · sanctioned built-up 3,856 sq m
- Land, as filed: 108/1/4/1,108/1/11/3, 108/1/2/B, 108/1/2/A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Morya Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Morya Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Morya Heights
What is the possession date of Morya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Morya Heights in Vashind, Thane is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Morya Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Morya Heights's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Morya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Morya Heights in Vashind, Thane is P51700053294.
Is Morya Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights is registered as P51700053294 and its status is "Registered and active".
What is the current construction status of Morya Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Morya Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Morya Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights is registered on MahaRERA as P51700053294, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Morya Heights?
Morya Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Morya Heights?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Morya Heights: gharkundli.com/tools/property-cost-calculator
Has Morya Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Morya Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Morya Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Morya Heights's possession date changes?
The latest dates are on Morya Heights's MahaRERA page (P51700053294). GharKundli's Kundli Watch sends a free WhatsApp update on Morya Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Morya Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights has 3 buildings filed: Building No 01 with 8 floors and 67 units; MORYA HEIGHT with 7 floors; Building No 02 with 4 floors and 9 units.
How much parking does Morya Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 open car parking spaces for Morya Heights.
How big is the land of Morya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights stands on 1,717 sq m of land (about 0.4 acres), with 3,856 sq m of sanctioned built-up area.
What are the reviews of Morya Heights?
Google Maps has reviews of Morya Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Morya Heights?
Morya Heights by MORYA DEVELOPERS is in Vashind, Thane, pincode 421601, Maharashtra, and is registered on MahaRERA as P51700053294, per GharKundli's check of MahaRERA records. Its land is filed as 108/1/4/1,108/1/11/3, 108/1/2/B, 108/1/2/A. GharKundli lists all 184 MahaRERA projects in Shahapur (421601).
How many flats are in Morya Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights has 72 homes in 3 towers registered on MahaRERA, and 43% of them are sold or booked.
When was Morya Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Morya Heights was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.
Does Morya Heights have any legal issues or court cases?
No court cases are listed for Morya Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Morya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MORYA DEVELOPERS, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Morya Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Shahapur (421601)
- Sai Anand Apartment
- Mirador Utsav Phase 1
- Visava
- Chintamani Habitat (Fortuna Bungalow)
- Chintamani Meadows
- Icon Apartment
- Pitruchhaya Apartment
- Aghav Resideny
Other projects by MORYA DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.