Samarth Shivani Co-Operative Housing Society Limited

by GURURAJ ENTERPRISES BUILDERS AND DEVELOPERS · Shirgaon, Thane 421503

What’s in the report? →

Possession date of Samarth Shivani Co-Operative Housing Society Limited (MahaRERA P51700052991): 31 August 2026, moved from 31 August 2025 (12 months later), and it has already passed. It has 28 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700052991. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700052991, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2026) has passed.

What do you want to know about Samarth Shivani Co-Operative Housing Society Limited?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Samarth Shivani Co-Operative Housing Society Limited has moved

  1. 31 August 2025

    Completion date given when the project was registered

  2. 31 August 2026

    Extended at the builder's request (MahaRERA application EA30082502479)

    Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”

Source: Samarth Shivani Co-Operative Housing Society Limited’s extension records on MahaRERA (P51700052991), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Samarth Shivani Co-Operative Housing Society Limited

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700052991
Status
Lapsed (registration period ended)
Builder
GURURAJ ENTERPRISES BUILDERS AND DEVELOPERS
Location
Shirgaon, Thane · 421503
Project type
Others
Registered on
10 Oct 2023
Completion date at registration
August 2025
Latest completion date
August 2026
Delay so far
12 months
Homes
28
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Samarth Shivani Co-Operative Housing Society Limited, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Samarth Shivani Co-Operative Society Limited90%100%80%80%

Commencement certificate (CC), as filed on MahaRERA

  • Samarth Shivani Co-Operative Society Limited: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samarth Shivani Co-Operative Housing Society Limited every 1–2 months.

Samarth Shivani Co-Operative Housing Society Limited: buildings, flats and land, as filed on MahaRERA

  • Buildings: Samarth Shivani Co-Operative Society Limited (8 floors, 41 units)
  • Car parking: 18 open
  • Land: 906 sq m (about 0.2 acres) · sanctioned built-up 3,063 sq m
  • Land, as filed: S.No. 31, H. No. 2/A, Plot No. 8 & 9
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Samarth Shivani Co-Operative Housing Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Samarth Shivani Co-Operative Housing Society Limited: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Samarth Shivani Co-Operative Housing Society Limited

What is the possession date of Samarth Shivani Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Samarth Shivani Co-Operative Housing Society Limited in Shirgaon, Thane is 31 August 2026 — 12 months later than 31 August 2025, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Samarth Shivani Co-Operative Housing Society Limited?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Samarth Shivani Co-Operative Housing Society Limited's builder has filed on MahaRERA, the official one, is 31 August 2026, already 12 months later than the 31 August 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Samarth Shivani Co-Operative Housing Society Limited extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited's builder applied to MahaRERA to extend the completion date once: to 31 August 2026, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.".

What is the RERA number of Samarth Shivani Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Samarth Shivani Co-Operative Housing Society Limited in Shirgaon, Thane is P51700052991.

Is Samarth Shivani Co-Operative Housing Society Limited registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited is registered as P51700052991 and its status is "Lapsed (registration period ended)".

What is the current construction status of Samarth Shivani Co-Operative Housing Society Limited? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Samarth Shivani Co-Operative Society Limited is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Samarth Shivani Co-Operative Housing Society Limited have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Samarth Shivani Co-Operative Housing Society Limited safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited is registered on MahaRERA as P51700052991, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Samarth Shivani Co-Operative Housing Society Limited?

Samarth Shivani Co-Operative Housing Society Limited isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Samarth Shivani Co-Operative Housing Society Limited?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Samarth Shivani Co-Operative Housing Society Limited: gharkundli.com/tools/property-cost-calculator

Has Samarth Shivani Co-Operative Housing Society Limited received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 August 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Samarth Shivani Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 August 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Samarth Shivani Co-Operative Housing Society Limited a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited is a redevelopment: 24 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Samarth Shivani Co-Operative Housing Society Limited uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Samarth Shivani Co-Operative Housing Society Limited was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Samarth Shivani Co-Operative Housing Society Limited's possession date changes?

The latest dates are on Samarth Shivani Co-Operative Housing Society Limited's MahaRERA page (P51700052991). GharKundli's Kundli Watch sends a free WhatsApp update on Samarth Shivani Co-Operative Housing Society Limited every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Samarth Shivani Co-Operative Housing Society Limited have?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited has one building filed: Samarth Shivani Co-Operative Society Limited with 8 floors and 41 units.

How much parking does Samarth Shivani Co-Operative Housing Society Limited have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 open car parking spaces for Samarth Shivani Co-Operative Housing Society Limited.

How big is the land of Samarth Shivani Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited stands on 906 sq m of land (about 0.2 acres), with 3,063 sq m of sanctioned built-up area.

What are the reviews of Samarth Shivani Co-Operative Housing Society Limited?

Google Maps has reviews of Samarth Shivani Co-Operative Housing Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Samarth Shivani Co-Operative Housing Society Limited?

Samarth Shivani Co-Operative Housing Society Limited by GURURAJ ENTERPRISES BUILDERS AND DEVELOPERS is in Shirgaon, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700052991, per GharKundli's check of MahaRERA records. Its land is filed as S.No. 31, H. No. 2/A, Plot No. 8 & 9. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).

How many flats are in Samarth Shivani Co-Operative Housing Society Limited, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited has 28 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Samarth Shivani Co-Operative Housing Society Limited registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Shivani Co-Operative Housing Society Limited was registered on MahaRERA on 10 October 2023. GharKundli did not find a title report on the land on file there.

Does Samarth Shivani Co-Operative Housing Society Limited have any legal issues or court cases?

No court cases are listed for Samarth Shivani Co-Operative Housing Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Samarth Shivani Co-Operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GURURAJ ENTERPRISES BUILDERS AND DEVELOPERS.

All projects with possession due in 2026 in Thane →

Other projects in Kulgaon (421503)

All 938 projects in Kulgaon (421503) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.