Saptashree Galicia
by SAPTASHREE REALITY PRIVATE LIMITED · Kolshet, Thane 400607Also near Chakala, Andheri East, Panchpakhadi, Bhaynderpada
What’s in the report? →Possession date of Saptashree Galicia (MahaRERA P51700054273): 30 September 2028. It has 186 homes, 26% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700054273, and currently active. Its completion date is now September 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700054273, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Saptashree Galicia?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Saptashree Galicia has moved
31 May 2028
Completion date given when the project was registered
30 September 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Saptashree Galicia’s extension records on MahaRERA (P51700054273), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Saptashree Galicia
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700054273
- Status
- Registered and active
- Builder
- SAPTASHREE REALITY PRIVATE LIMITED
- Location
- Kolshet, Thane · 400607
- Project type
- Others
- Registered on
- 15 Jan 2024
- Completion date at registration
- May 2028
- Latest completion date
- September 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 186
- Sold or booked
- 26%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Saptashree Galicia, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAPTASHREE GALICIA | 100% | 88% | 25% | 5% |
Commencement certificate (CC), as filed on MahaRERA
- SAPTASHREE GALICIA: covers GROUND AND STILT FLOOR, 1ST FLOOR, 2ND TO 7TH, 9TH TO 12TH, 14TH TO 17TH AND 19TH TYPICAL FLOOR, 8TH AND 13TH AND 18TH TYPICAL REFUGE FLOOR, 20TH TO 22ND FLOOR,
Latest CC order on MahaRERA: dated 11/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saptashree Galicia every 1–2 months.
Saptashree Galicia: buildings, flats and land, as filed on MahaRERA
- Buildings: SAPTASHREE GALICIA (25 floors, 203 units)
- Car parking: 150 covered, 2 open
- Land: 2,889 sq m (about 0.7 acres) · sanctioned built-up 12,703 sq m
- Boundaries filed include: HANUMAN TEMPLE, TMC ROAD
- Land, as filed: 405 , 515, 517, 518, 519, 520, 521, 522, 523. 632, 633, 639B AT KOLSHET, TAL. & DIST. THANE
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Saptashree Reality (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project.
Read Google reviews of Saptashree Galicia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Saptashree Galicia: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Saptashree Galicia
What is the possession date of Saptashree Galicia?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Saptashree Galicia in Kolshet, Thane is 30 September 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Saptashree Galicia?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Saptashree Galicia's builder has filed on MahaRERA, the official one, is 30 September 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Saptashree Galicia?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Saptashree Galicia in Kolshet, Thane is P51700054273.
Is Saptashree Galicia registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia is registered as P51700054273 and its status is "Registered and active".
What is the current construction status of Saptashree Galicia? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAPTASHREE GALICIA is 88% done and internal work 25%. GharKundli's full report compares construction progress with the deadline.
Does Saptashree Galicia have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Saptashree Galicia safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia is registered on MahaRERA as P51700054273, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Saptashree Galicia?
Saptashree Galicia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Saptashree Galicia?
For a flat in Saptashree Galicia (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Saptashree Galicia received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia is still under construction, with 30 September 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Saptashree Galicia a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia's planning authority on MahaRERA is TMCB-24-ENTRY-37650, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Saptashree Galicia uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Saptashree Galicia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Saptashree Galicia's possession date changes?
The latest dates are on Saptashree Galicia's MahaRERA page (P51700054273). GharKundli's Kundli Watch sends a free WhatsApp update on Saptashree Galicia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Saptashree Galicia have?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia has one building filed: SAPTASHREE GALICIA with 25 floors and 203 units.
How much parking does Saptashree Galicia have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 150 covered and 2 open car parking spaces for Saptashree Galicia.
How big is the land of Saptashree Galicia?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia stands on 2,889 sq m of land (about 0.7 acres), with 12,703 sq m of sanctioned built-up area.
What is the track record of Saptashree Galicia's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Reality (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Saptashree Galicia?
Google Maps has reviews of Saptashree Galicia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Saptashree Galicia?
Saptashree Galicia by SAPTASHREE REALITY PRIVATE LIMITED is in Kolshet, Thane, pincode 400607 (near Chakala, Andheri East, Panchpakhadi, Bhaynderpada), Maharashtra, and is registered on MahaRERA as P51700054273, per GharKundli's check of MahaRERA records. Its boundaries filed there include HANUMAN TEMPLE, TMC ROAD. Its land is filed as 405 , 515, 517, 518, 519, 520, 521, 522, 523. 632, 633, 639B AT KOLSHET, TAL. & DIST. THANE. GharKundli lists all 218 MahaRERA projects in Sandozbaugh (400607).
How many flats are in Saptashree Galicia, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia has 186 homes in 1 tower registered on MahaRERA, and 26% of them are sold or booked.
When was Saptashree Galicia registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Saptashree Galicia was registered on MahaRERA on 15 January 2024. GharKundli did not find a title report on the land on file there.
Does Saptashree Galicia have any legal issues or court cases?
No court cases are listed for Saptashree Galicia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Saptashree Galicia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAPTASHREE REALITY PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Saptashree Galicia
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Sandozbaugh (400607)
All 218 projects in Sandozbaugh (400607) →Other projects by SAPTASHREE REALITY PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.