Skip to content
GharKundli

Lodha Amara - Tower 45

by MACROTECH DEVELOPERS LIMITED (Lodha) · Kolshet, Thane

Possession: Lodha Amara - Tower 45 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700018593. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Lodha Amara - Tower 45?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Lodha Amara - Tower 45

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the July 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700018593
Status
Completed
Builder
MACROTECH DEVELOPERS LIMITED
Location
Kolshet, Thane · 400607
Project type
Residential / Group Housing
Registered on
21 Nov 2018
Completion date at registration
July 2024
Latest completion date
July 2024
Homes
170
Towers
1
Complaints on MahaRERA
1
Court cases listed
2
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
134

Construction progress of Lodha Amara - Tower 45, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing 45100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Amara - Tower 45 every month.

Lodha Amara - Tower 45: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing 45 (30 floors)
  • Land: 2,135 sq m (about 0.5 acres) · sanctioned built-up 292 sq m · recreational space 1,740 sq m

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 373 GharKundli has checked: 207 finished, 189 within the promised date and 18 needed more time (typically 11 months); 166 still being built, 12 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.

Read Google reviews of Lodha Amara - Tower 45 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lodha Amara - Tower 45: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Lodha Amara - Tower 45

What is the possession date of Lodha Amara - Tower 45?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Lodha Amara - Tower 45 in Kolshet, Thane is 31 July 2024.

Is the builder's possession date different from the MahaRERA date for Lodha Amara - Tower 45?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Amara - Tower 45's builder has filed on MahaRERA, the official one, is 31 July 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Lodha Amara - Tower 45?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Lodha Amara - Tower 45 in Kolshet, Thane is P51700018593.

Is Lodha Amara - Tower 45 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha Amara - Tower 45 is registered as P51700018593 and its status is "Completed".

What is the construction status of Lodha Amara - Tower 45?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha Amara - Tower 45's status on MahaRERA is "Completed". As filed by the builder, slab work on Wing 45 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Lodha Amara - Tower 45 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Lodha Amara - Tower 45 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha Amara - Tower 45 is registered on MahaRERA as P51700018593, its MahaRERA status is "Completed", its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Lodha Amara - Tower 45 have other wings or phases?

Yes. MahaRERA lists 15 other registrations of the same project, each with its own possession date: LODHA AMARA - TOWER 1 - 5, 7 - 19 (P51700001065, possession 30 Nov 2019); Lodha Amara - Tower 6, 22 (P51700014760, possession 30 Jan 2024); Lodha Amara - Tower 20, 21 (P51700016961, possession 30 Sep 2023); LODHA AMARA - TOWER 23 (P51700020093, possession 29 Dec 2023); Lodha Amara Tower 24 and 25 (P51700020128, possession 31 Mar 2028); LODHA AMARA - TOWER 29,31 (P51700000981, possession 30 Jul 2022); and 9 more. Check that your agreement names the registration of your own wing.

How can I get updates if Lodha Amara - Tower 45's possession date changes?

The latest dates are on Lodha Amara - Tower 45's MahaRERA page (P51700018593). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Amara - Tower 45 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lodha Amara - Tower 45 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha Amara - Tower 45 has one building filed: Wing 45 with 30 floors.

How big is the land of Lodha Amara - Tower 45?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha Amara - Tower 45 stands on 2,135 sq m of land (about 0.5 acres), with 292 sq m of sanctioned built-up area and 1,740 sq m of recreational open space.

What is the track record of Lodha Amara - Tower 45's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 373 GharKundli has checked: 207 finished, 189 within the promised date and 18 needed more time (typically 11 months); 166 still being built, 12 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Lodha Amara - Tower 45?

Google Maps has reviews of Lodha Amara - Tower 45 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Lodha Amara - Tower 45?

Lodha Amara - Tower 45 by MACROTECH DEVELOPERS LIMITED (Lodha) is in Kolshet, Thane (pincode 400607), Maharashtra, and is registered on MahaRERA as P51700018593, per GharKundli's check of MahaRERA records.

How many homes are in Lodha Amara - Tower 45?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha Amara - Tower 45 has 170 homes in 1 tower registered on MahaRERA.

When was Lodha Amara - Tower 45 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Lodha Amara - Tower 45 was registered on MahaRERA on 21 November 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Lodha Amara - Tower 45?

2 court cases are listed for Lodha Amara - Tower 45 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Lodha Amara - Tower 45?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MACROTECH DEVELOPERS LIMITED, the company Lodha files this project under, which has 134 other projects registered on MahaRERA.

Other projects in Kolshet

All 218 projects in Sandozbaugh (400607) →

Other projects by MACROTECH DEVELOPERS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.