Skip to content
GharKundli

Lodha Lower Parel Project

by MACROTECH DEVELOPERS LIMITED (Lodha) · Lower Parel, Mumbai

Possession: Lodha Lower Parel Project is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900022245. Status: Completed. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Lodha Lower Parel Project?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Lodha Lower Parel Project has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 29 June 2025

    Extended at the builder's request (MahaRERA application EXT51900025860)

    Reason the builder gave MahaRERA:
    “We have completed 97% of the work, with the Occupation Certificate pending for only two flats. We have also uploaded photos of the building. We request an extension to complete the remaining common area work, obtain the Occupation Certifica…” Read the full reason“We have completed 97% of the work, with the Occupation Certificate pending for only two flats. We have also uploaded photos of the building. We request an extension to complete the remaining common area work, obtain the Occupation Certificate, and complete the Form 4 procedure.”

Source: Lodha Lower Parel Project’s extension records on MahaRERA (P51900022245), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lodha Lower Parel Project

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints and 2 court cases, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900022245
Status
Completed
Builder
MACROTECH DEVELOPERS LIMITED
Location
Lower Parel, Mumbai · 400013
Project type
Residential / Group Housing
Registered on
5 Sep 2019
Completion date at registration
December 2024
Latest completion date
June 2025
Delay so far
6 months
Homes
135
Towers
1
Complaints on MahaRERA
5
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
134

Construction progress of Lodha Lower Parel Project, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Lodha Lower Parel Project100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Lower Parel Project every month.

Lodha Lower Parel Project: buildings, flats and land, as filed on MahaRERA

  • Buildings: Lodha Lower Parel Project (44 floors)
  • Land: 3,626 sq m (about 0.9 acres) · recreational space 732 sq m
  • Boundaries filed include: 50 Wide Sun Mill Road, 30 Wide Sun Mill Road

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.

Read Google reviews of Lodha Lower Parel Project →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lodha Lower Parel Project: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Lodha Lower Parel Project

What is the possession date of Lodha Lower Parel Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Lower Parel Project in Lower Parel, Mumbai is 29 June 2025 — 6 months later than 30 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Lodha Lower Parel Project?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Lower Parel Project's builder has filed on MahaRERA, the official one, is 29 June 2025, already 6 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Lodha Lower Parel Project extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project's builder applied to MahaRERA to extend the completion date once: to 29 June 2025, giving the reason "We have completed 97% of the work, with the Occupation Certificate pending for only two flats. We have also uploaded photos of the building. We request an extension to complete the remaining common area work, obtain the Occupation Certificate, and complete the Form 4 procedure.".

What is the RERA number of Lodha Lower Parel Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Lower Parel Project in Lower Parel, Mumbai is P51900022245.

Is Lodha Lower Parel Project registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project is registered as P51900022245 and its status is "Completed".

What is the construction status of Lodha Lower Parel Project?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project's status on MahaRERA is "Completed". As filed by the builder, slab work on Lodha Lower Parel Project is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Lodha Lower Parel Project have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Lodha Lower Parel Project safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project is registered on MahaRERA as P51900022245, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Lodha Lower Parel Project's possession date changes?

The latest dates are on Lodha Lower Parel Project's MahaRERA page (P51900022245). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Lower Parel Project every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lodha Lower Parel Project have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project has one building filed: Lodha Lower Parel Project with 44 floors.

How big is the land of Lodha Lower Parel Project?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project stands on 3,626 sq m of land (about 0.9 acres) and 732 sq m of recreational open space.

What is the track record of Lodha Lower Parel Project's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Lodha Lower Parel Project?

Google Maps has reviews of Lodha Lower Parel Project written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Lodha Lower Parel Project?

Lodha Lower Parel Project by MACROTECH DEVELOPERS LIMITED (Lodha) is in Lower Parel, Mumbai (pincode 400013), Maharashtra, and is registered on MahaRERA as P51900022245, per GharKundli's check of MahaRERA records. Its boundaries filed there include 50 Wide Sun Mill Road, 30 Wide Sun Mill Road.

How many homes are in Lodha Lower Parel Project?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project has 135 homes in 1 tower registered on MahaRERA.

When was Lodha Lower Parel Project registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Lower Parel Project was registered on MahaRERA on 5 September 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Lodha Lower Parel Project?

2 court cases are listed for Lodha Lower Parel Project on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Lodha Lower Parel Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MACROTECH DEVELOPERS LIMITED, the company Lodha files this project under, which has 134 other projects registered on MahaRERA.

Other projects in Lower Parel

All 61 projects in Lower Parel (400013) →

Other projects by MACROTECH DEVELOPERS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.