Lodha Kandivali Project - Tower 3
by Macrotech Developers Limited (Lodha) · Akurli Village, Mumbai
Possession: Lodha Kandivali Project - Tower 3 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800031346. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Lodha Kandivali Project - Tower 3?
How the possession date of Lodha Kandivali Project - Tower 3 has moved
31 October 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA03042620549)
Reason the builder gave MahaRERA:
“We have already uploaded the Full Occupancy Certificate dated 28th April 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request y…” Read the full reason
“We have already uploaded the Full Occupancy Certificate dated 28th April 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request you to kindly grant an extension upto 30th June 2026 for the above-mentioned project. The purpose of seeking this extension is to complete necessary corrections and updates, including alignment of BUA, Units, FSI, and other project details with the approved Full Occupancy Certificate plans.”
Source: Lodha Kandivali Project - Tower 3’s extension records on MahaRERA (P51800031346), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lodha Kandivali Project - Tower 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Lodha Kandivali Project-Tower 1P51800045908 · possession 28 Feb 2028
- Lodha Kandivali Project - Tower 2P51800031351 · possession 31 Jul 2026
- Lodha Kandivali Project - Tower 4P51800031532 · possession 31 May 2025
- Lodha Kandivali Project - Tower 5P51800032605 · possession 31 Jul 2026
- MahaRERA registration
- P51800031346
- Status
- Completed
- Builder
- Macrotech Developers Limited
- Location
- Akurli Village, Mumbai · 400101
- Project type
- Residential / Group Housing
- Registered on
- 23 Oct 2021
- Completion date at registration
- October 2025
- Latest completion date
- June 2026
- Delay so far
- 8 months
- Homes
- 63
- Sold or booked
- 97%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 134
Construction progress of Lodha Kandivali Project - Tower 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower 3 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Tower 3: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Kandivali Project - Tower 3 every month.
Lodha Kandivali Project - Tower 3: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 693 | 41 |
| 4 BHK | 1,449 | 22 |
- Buildings: Tower 3 (23 floors, 63 units)
- Car parking: 85 covered
- Land: 1,015 sq m (about 0.3 acres) · sanctioned built-up 6,750 sq m · recreational space 222 sq m
- Boundaries filed include: Akurli Road
The builder’s record and reviews
Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.
Read Google reviews of Lodha Kandivali Project - Tower 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lodha Kandivali Project - Tower 3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Lodha Kandivali Project - Tower 3
What is the possession date of Lodha Kandivali Project - Tower 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Kandivali Project - Tower 3 in Akurli Village, Mumbai is 30 June 2026 — 8 months later than 31 October 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Lodha Kandivali Project - Tower 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Kandivali Project - Tower 3's builder has filed on MahaRERA, the official one, is 30 June 2026, already 8 months later than the 31 October 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lodha Kandivali Project - Tower 3 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "We have already uploaded the Full Occupancy Certificate dated 28th April 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the category of “Lapsed Projects.” In this regard, we request you to kindly grant an extension upto 30th June 2026 for the above-mentioned project. The purpose of seeking this extension is to complete necessary corrections and updates, including alignment of BUA, Units, FSI, and other project details with the approved Full Occupancy Certificate plans.".
What is the RERA number of Lodha Kandivali Project - Tower 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Kandivali Project - Tower 3 in Akurli Village, Mumbai is P51800031346.
Is Lodha Kandivali Project - Tower 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3 is registered as P51800031346 and its status is "Completed".
What is the construction status of Lodha Kandivali Project - Tower 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3's status on MahaRERA is "Completed". As filed by the builder, slab work on Tower 3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Lodha Kandivali Project - Tower 3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Lodha Kandivali Project - Tower 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3 is registered on MahaRERA as P51800031346, its MahaRERA status is "Completed", its completion date has moved 8 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Lodha Kandivali Project - Tower 3 have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Lodha Kandivali Project-Tower 1 (P51800045908, possession 28 Feb 2028); Lodha Kandivali Project - Tower 2 (P51800031351, possession 31 Jul 2026); Lodha Kandivali Project - Tower 4 (P51800031532, possession 31 May 2025); Lodha Kandivali Project - Tower 5 (P51800032605, possession 31 Jul 2026). Check that your agreement names the registration of your own wing.
How can I get updates if Lodha Kandivali Project - Tower 3's possession date changes?
The latest dates are on Lodha Kandivali Project - Tower 3's MahaRERA page (P51800031346). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Kandivali Project - Tower 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lodha Kandivali Project - Tower 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3 has one building filed: Tower 3 with 23 floors and 63 units.
What are the flat sizes (carpet area) in Lodha Kandivali Project - Tower 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Lodha Kandivali Project - Tower 3: 2 BHK: 693 sq ft carpet (41 homes); 4 BHK: 1449 sq ft carpet (22 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Lodha Kandivali Project - Tower 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 85 covered car parking spaces for Lodha Kandivali Project - Tower 3.
How big is the land of Lodha Kandivali Project - Tower 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3 stands on 1,015 sq m of land (about 0.3 acres), with 6,750 sq m of sanctioned built-up area and 222 sq m of recreational open space.
What is the track record of Lodha Kandivali Project - Tower 3's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Lodha Kandivali Project - Tower 3?
Google Maps has reviews of Lodha Kandivali Project - Tower 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Lodha Kandivali Project - Tower 3?
Lodha Kandivali Project - Tower 3 by Macrotech Developers Limited (Lodha) is in Akurli Village, Mumbai (pincode 400101), Maharashtra, and is registered on MahaRERA as P51800031346, per GharKundli's check of MahaRERA records. Its boundaries filed there include Akurli Road.
How many homes are in Lodha Kandivali Project - Tower 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3 has 63 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.
When was Lodha Kandivali Project - Tower 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Kandivali Project - Tower 3 was registered on MahaRERA on 23 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Lodha Kandivali Project - Tower 3?
No court cases are listed for Lodha Kandivali Project - Tower 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Lodha Kandivali Project - Tower 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Macrotech Developers Limited, the company Lodha files this project under, which has 134 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Lodha Kandivali Project - Tower 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Akurli Village
- Lodha Kandivali Project - Tower 2
- Lodha Kandivali Project - Tower 5
- Shikara Orchid
- Belmac Riverside - III B BLDG
- Belmac Riverside - III A BLDG
- BELMAC RIVERSIDE-I
Other projects by Macrotech Developers Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.