Sunteck Crescent Park -2
by SUNTECK PROPERTY HOLDINGS PRIVATE LIMITED · Village Shahad, ThaneAlso near Gauripada, Kalyan
Possession date of Sunteck Crescent Park -2: 30 April 2032, moved from 31 December 2029 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700053312, and currently active. Its completion date has moved from December 2029 to April 2032: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sunteck Crescent Park -2?
How the possession date of Sunteck Crescent Park -2 has moved
31 December 2029
Completion date given when the project was registered
31 December 2031
Extended at the builder's request (MahaRERA application EA17062621417)
Reason the builder gave MahaRERA:
“1. The project stands at 5% completion. 2. Form B uploaded. 3. PERT for the remaining completion work is uploaded in the Application. 4. The Project got delayed due to following reasons:- a. The Promoter has not yet started sales and market…” Read the full reason
“1. The project stands at 5% completion. 2. Form B uploaded. 3. PERT for the remaining completion work is uploaded in the Application. 4. The Project got delayed due to following reasons:- a. The Promoter has not yet started sales and marketing of the said project and as on date there are no sale or any allottee in respect of any unit of the said project. The Promoter, after considering the current market conditions, intends to revise the sanctioned plans of the said project and has applied to concerned planning authorities for issuance of amendments to current sanctions, however, revised sa…”30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sunteck Crescent Park -2’s extension records on MahaRERA (P51700053312), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sunteck Crescent Park -2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 13 court cases, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Sunteck Crescent Park -1P51700053439 · possession 30 Apr 2030
- MahaRERA registration
- P51700053312
- Status
- Registered and active
- Builder
- SUNTECK PROPERTY HOLDINGS PRIVATE LIMITED
- Location
- Village Shahad, Thane · 421103
- Project type
- Residential / Group Housing
- Registered on
- 27 Oct 2023
- Completion date at registration
- December 2029
- Latest completion date
- April 2032
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 273
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 13
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Sunteck Crescent Park -2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower 2 | 0% | 0% | 0% | 0% |
| Tower 3 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Tower 2: covers Gr + 37 Floors
- Tower 3: covers Plinth Level - Zero FSI
Latest CC order on MahaRERA: dated 14/07/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunteck Crescent Park -2 every month.
Sunteck Crescent Park -2: buildings, flats and land, as filed on MahaRERA
- Buildings: Tower 2 (38 floors, 273 units)
- Car parking: 136 covered
- Land: 1,150 sq m (about 0.3 acres) · sanctioned built-up 17,927 sq m · recreational space 2,569 sq m
- Boundaries filed include: Railway Boundary, Kalyan Mohane Internal Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sunteck Realty (a group of 7 linked companies) has 42 projects on MahaRERA since 2017, this one included. Of the 34 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 20 months); 24 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 130 complaints on MahaRERA across 16 projects.
Read Google reviews of Sunteck Crescent Park -2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sunteck Crescent Park -2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sunteck Crescent Park -2
What is the possession date of Sunteck Crescent Park -2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sunteck Crescent Park -2 in Village Shahad, Thane is 30 April 2032 — 24 months later than 31 December 2029, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sunteck Crescent Park -2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunteck Crescent Park -2's builder has filed on MahaRERA, the official one, is 30 April 2032, already 24 months later than the 31 December 2029 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sunteck Crescent Park -2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "1. The project stands at 5% completion. 2. Form B uploaded. 3. PERT for the remaining completion work is uploaded in the Application. 4. The Project got delayed due to following reasons:- a. The Promoter has not yet started sales and marketing of the said project and as on date there are no sale or any allottee in respect of any unit of the said project. The Promoter, after considering the current market conditions, intends to revise the sanctioned plans of the said project and has applied to concerned planning authorities for issuance of amendments to current sanctions, however, revised sa…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sunteck Crescent Park -2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sunteck Crescent Park -2 in Village Shahad, Thane is P51700053312.
Is Sunteck Crescent Park -2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2 is registered as P51700053312 and its status is "Registered and active".
What is the construction status of Sunteck Crescent Park -2?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Sunteck Crescent Park -2 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sunteck Crescent Park -2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2 is registered on MahaRERA as P51700053312, its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Sunteck Crescent Park -2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Sunteck Crescent Park -1 (P51700053439, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.
How can I get updates if Sunteck Crescent Park -2's possession date changes?
The latest dates are on Sunteck Crescent Park -2's MahaRERA page (P51700053312). GharKundli's Kundli Watch sends a free WhatsApp update on Sunteck Crescent Park -2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sunteck Crescent Park -2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2 has one building filed: Tower 2 with 38 floors and 273 units.
How much parking does Sunteck Crescent Park -2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 136 covered car parking spaces for Sunteck Crescent Park -2.
How big is the land of Sunteck Crescent Park -2?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2 stands on 1,150 sq m of land (about 0.3 acres), with 17,927 sq m of sanctioned built-up area and 2,569 sq m of recreational open space.
What is the track record of Sunteck Crescent Park -2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Realty (a group of 7 linked companies) has 42 projects on MahaRERA since 2017, this one included. Of the 34 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 20 months); 24 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 130 complaints on MahaRERA across 16 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sunteck Crescent Park -2?
Google Maps has reviews of Sunteck Crescent Park -2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sunteck Crescent Park -2?
Sunteck Crescent Park -2 by SUNTECK PROPERTY HOLDINGS PRIVATE LIMITED is in Village Shahad, Thane (pincode 421103), near Gauripada, Kalyan, Maharashtra, and is registered on MahaRERA as P51700053312, per GharKundli's check of MahaRERA records. Its boundaries filed there include Railway Boundary, Kalyan Mohane Internal Road.
How many homes are in Sunteck Crescent Park -2?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2 has 273 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Sunteck Crescent Park -2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Crescent Park -2 was registered on MahaRERA on 27 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Sunteck Crescent Park -2?
13 court cases are listed for Sunteck Crescent Park -2 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Sunteck Crescent Park -2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUNTECK PROPERTY HOLDINGS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sunteck Crescent Park -2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421103
- SADGURU KRUPA II PHASE
- Mangalmurti Heights
- Vedaant Meadows
- GURUDEV ORCHID
- VISHWAJEET TOWN
- PRECIOUS AVALON PHASE-1
- BALAJI GARDEN
- Mohan Parkland Phase IA
Other projects by SUNTECK PROPERTY HOLDINGS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.