MahaRERA projects in Shahad, Thane (421103)
According to GharKundli's check of MahaRERA records, 32 housing projects are registered in pincode 421103 (Shahad, Thane). 20 are still being built, 7 with possession due by the end of 2027. For 25, the completion date on MahaRERA is later than the one first promised. 9 have at least one complaint filed on MahaRERA.
Pincode 421103 also covers: Kalyan, Mharal, Varap, Village Shahad, Mamnoli, Vaholi.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| BALAJI VIVANTA MAYUR ENTERPRISES BUILDERS & DEVELOPERS | De-registered | 31 Dec 2023passed | same | 0 |
| GURUDEV ORCHID GURUDEV DEVELOPERS | Active | 30 Jan 2027 | 31 Mar 2025 | 0 |
| MAHADEV HEIGHTS ONBV REALITY | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| SIDDHIVINAYAK HOMES SIDDHIVINAYAK BUILDERS AND DEVELOPERS | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Vasudev Laxmi Park MAHESH MANOHAR SALPHALE | Active | 1 May 2027 | 1 Jan 2027 | 0 |
| Mangalmurti Heights Ramesh Nanalal Jain | Active | 31 Jul 2027 | 31 Mar 2024 | 0 |
| Vedaant Meadows VEDAANT BUILDERS | Active | 31 Dec 2027 | 31 Dec 2025 | 1 |
| VISHWAJEET PRECIOUS PHASE IV ABHIJEET CONSTRUCTION | Active | 30 Jul 2028 | 30 Mar 2028 | 0 |
| Mahadev Enclaves Mahadev Enclaves | Active | 31 Jul 2028 | 31 Mar 2028 | 0 |
| BUILDING G SAI ICON PHASE 2 Mutha Properties | Active | 30 Apr 2029 | 30 Dec 2023 | 0 |
| KRISHNA EMPIRE PHASE 4 CHIRAG ENTERPRISES | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Rajyog Riddhi Siddhi Buildcon | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| VISHWAJEET TOWN GULABRAO BABURAO KARANJULE PATIL | Active | 31 May 2029 | 31 Jan 2029 | 0 |
| BALAJI GARDEN Mayur Enterprises Builders and Developers | Active | 31 Jul 2029 | 31 Mar 2029 | 0 |
| PRECIOUS ORCHID Precious Keystone LLP | Active | 30 Sep 2029 | 31 May 2029 | 1 |
| PRECIOUS AVALON PHASE-1 VINAYAK ASSOCIATES | Active | 30 Apr 2030 | 30 Dec 2029 | 0 |
| Sunteck Crescent Park -1 SUNTECK PROPERTY HOLDINGS PRIVATE LIMITED | Active | 30 Apr 2030 | 31 Dec 2029 | 3 |
| VISHWAJEET TOWN PHASE II GBK GROUP LLP | Active | 23 Aug 2030 | 23 Apr 2030 | 0 |
| Sunteck Crescent Park -2 SUNTECK PROPERTY HOLDINGS PRIVATE LIMITED | Active | 30 Apr 2032 | 31 Dec 2029 | 1 |
| Mohan Parkland Phase IA MOHAN BUILT-SPACES LLP | Active | 31 Dec 2032 | same | 0 |
| VISHWAJEET PRECIOUS PHASE III ABHIJEET PRIDE | Completed | 2 Mar 2024 | same | 0 |
| ADITYA APARTMENTS BUILDING C NAVIN NARANJI JAIN | Completed | 30 Jun 2024 | 30 Jun 2020 | 0 |
| YASHVI RESIDENCY PATEL & CO. | Completed | 30 Jun 2024 | 30 Dec 2022 | 0 |
| Birla Vanya - Phase 1 Century Textiles & Industries Ltd (Birla) | Completed | 30 Jun 2025 | same | 7 |
| Birla Vanya Phase 2 Century Textiles & Industries Ltd (Birla) | Completed | 30 Jun 2025 | 31 Mar 2025 | 2 |
| VISHWAJEET PRECIOUS PHASE II ABHIJEET PRIDE | Completed | 16 May 2026 | same | 1 |
| PRECIOUS MEADOWS VINAYAK ASSOCIATES | Completed | 30 Nov 2026 | 31 May 2025 | 1 |
| Palm Prism P J Construction | Lapsed | 31 Dec 2022passed | 31 Jul 2020 | 0 |
| SHREEJI NX SHREE GANESHKRUPA CONSTRUCTION | Lapsed | 30 Jun 2026passed | same | 0 |
| GANESH DARSHAN ARUN BALU PATIL | Lapsed | 30 Aug 2026passed | 30 Apr 2026 | 0 |
| SADGURU KRUPA II PHASE CHIRAG ENTERPRISES | Lapsed | 1 Oct 2026passed | 30 May 2024 | 0 |
| MILLENIUM HEIGHTS K P DEVELOPERS | — | — | — | 6 |
Other areas in Thane
- Kulgaon · 735
- Kalyan · 510
- Ambernath · 403
- Tilaknagar · 354
- Bhiwandi · 348
- Mira Road East · 277
- Kalyan East · 250
- Manpada · 232
- Naupada · 223
- Vishnunagar · 198
- Mumbra · 188
- Sandozbaugh · 180
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.