Skip to content
GharKundli

AARYA PREM CO-OP HSG SOC

by K S BUILDERS & DEVELOPERS · Badlapur, Thane

Registered on MahaRERA under P51700054798, and currently active. Its completion date has moved from October 2026 to February 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on AARYA PREM CO-OP HSG SOC

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700054798
Status
Registered and active
Builder
K S BUILDERS & DEVELOPERS
Location
Badlapur, Thane · 421503
Project type
Others
Registered on
12 Feb 2024
Completion date at registration
October 2026
Latest completion date
February 2027
Delay so far
4 months
Homes
42
Sold or booked
48%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

AARYA PREM CO-OP HSG SOC: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about AARYA PREM CO-OP HSG SOC

Is AARYA PREM CO-OP HSG SOC registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AARYA PREM CO-OP HSG SOC is registered as P51700054798 and its status is "Registered and active".

Where is AARYA PREM CO-OP HSG SOC?

AARYA PREM CO-OP HSG SOC by K S BUILDERS & DEVELOPERS is in Badlapur, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as P51700054798, per GharKundli's check of MahaRERA records.

When is possession of AARYA PREM CO-OP HSG SOC due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AARYA PREM CO-OP HSG SOC in Badlapur, Thane is 28 February 2027 — 4 months later than 30 October 2026, the date given at registration.

Does AARYA PREM CO-OP HSG SOC have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of AARYA PREM CO-OP HSG SOC?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K S BUILDERS & DEVELOPERS.

Other projects in pincode 421503

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.