INNOVATIVE INFOCOM AND IT PARKS
by INNOVATIVE INFOCOM & IT PARKS PRIVATE LIMITED · Kopar Khairane, Thane
Registered on MahaRERA under P51700077514, and currently active. Its completion date has moved from November 2027 to March 2028, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on INNOVATIVE INFOCOM AND IT PARKS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700077514
- Status
- Registered and active
- Builder
- INNOVATIVE INFOCOM & IT PARKS PRIVATE LIMITED
- Location
- Kopar Khairane, Thane · 400710
- Project type
- Commercial
- Registered on
- 20 Aug 2024
- Completion date at registration
- November 2027
- Latest completion date
- March 2028
- Delay so far
- 4 months
- Homes
- 42
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Kundli Watch
INNOVATIVE INFOCOM AND IT PARKS: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about INNOVATIVE INFOCOM AND IT PARKS
Is INNOVATIVE INFOCOM AND IT PARKS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), INNOVATIVE INFOCOM AND IT PARKS is registered as P51700077514 and its status is "Registered and active".
Where is INNOVATIVE INFOCOM AND IT PARKS?
INNOVATIVE INFOCOM AND IT PARKS by INNOVATIVE INFOCOM & IT PARKS PRIVATE LIMITED is in Kopar Khairane, Thane (pincode 400710), Maharashtra, and is registered on MahaRERA as P51700077514, per GharKundli's check of MahaRERA records.
When is possession of INNOVATIVE INFOCOM AND IT PARKS due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for INNOVATIVE INFOCOM AND IT PARKS in Kopar Khairane, Thane is 26 March 2028 — 4 months later than 26 November 2027, the date given at registration.
Does INNOVATIVE INFOCOM AND IT PARKS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of INNOVATIVE INFOCOM AND IT PARKS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is INNOVATIVE INFOCOM & IT PARKS PRIVATE LIMITED.
Other projects in pincode 400710
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.