BHOOMI ICON WING A

by FORNAX REALTY · Kopar Khairane, ThaneAlso near Koparkhairane, Navi Mumbai, Kopar Khairne

Possession date of BHOOMI ICON WING A: 30 October 2026, moved from 30 June 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700026412, and currently active. Its completion date has moved from June 2024 to October 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about BHOOMI ICON WING A?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BHOOMI ICON WING A has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51700018786)

    Reason the builder gave MahaRERA:
    “Respected Sir, We hereby apply for extension of project called “BHOOMI ICON” registered with the regulatory authority bide project registration certificate bearing No. P51700026412 which expires on 30.06.2024. We are writing to inform you t…” Read the full reason“Respected Sir, We hereby apply for extension of project called “BHOOMI ICON” registered with the regulatory authority bide project registration certificate bearing No. P51700026412 which expires on 30.06.2024. We are writing to inform you that we have received the revised Commencement Certificates for the construction of our Residential cum Commercial building project. The first Commencement Certificate is dated 30.03.2022, indicating the construction of a 14-floor building with 52 Residential Units, 10 Commercial Shops, and 9 Offices. The revised Commencement Certificate, dated 27.04.2023,…”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA16062501612)

    Reason the builder gave MahaRERA: “Building is almost Complete. We need some more time for completion and obtaining occupancy certificate from competent authorities.”
  4. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: BHOOMI ICON WING A’s extension records on MahaRERA (P51700026412), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BHOOMI ICON WING A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700026412
Status
Registered and active
Builder
FORNAX REALTY
Location
Kopar Khairane, Thane · 400709
Project type
Mixed
Registered on
17 Sep 2020
Completion date at registration
June 2024
Latest completion date
October 2026
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
68
Sold or booked
78%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of BHOOMI ICON WING A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • A WING: covers Gr+18 upper floors

Latest CC order on MahaRERA: dated 09/02/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BHOOMI ICON WING A every month.

BHOOMI ICON WING A: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Fornax Realty has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.

Read Google reviews of BHOOMI ICON WING A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BHOOMI ICON WING A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BHOOMI ICON WING A

What is the possession date of BHOOMI ICON WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BHOOMI ICON WING A in Kopar Khairane, Thane is 30 October 2026 — 24 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for BHOOMI ICON WING A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BHOOMI ICON WING A's builder has filed on MahaRERA, the official one, is 30 October 2026, already 24 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BHOOMI ICON WING A extended?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "Respected Sir, We hereby apply for extension of project called “BHOOMI ICON” registered with the regulatory authority bide project registration certificate bearing No. P51700026412 which expires on 30.06.2024. We are writing to inform you that we have received the revised Commencement Certificates for the construction of our Residential cum Commercial building project. The first Commencement Certificate is dated 30.03.2022, indicating the construction of a 14-floor building with 52 Residential Units, 10 Commercial Shops, and 9 Offices. The revised Commencement Certificate, dated 27.04.2023,…"; to 30 June 2026, giving the reason "Building is almost Complete. We need some more time for completion and obtaining occupancy certificate from competent authorities.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of BHOOMI ICON WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BHOOMI ICON WING A in Kopar Khairane, Thane is P51700026412.

Is BHOOMI ICON WING A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A is registered as P51700026412 and its status is "Registered and active".

What is the construction status of BHOOMI ICON WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does BHOOMI ICON WING A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is BHOOMI ICON WING A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A is registered on MahaRERA as P51700026412, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does BHOOMI ICON WING A have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: BHOOMI ICON WING B (PM1331012600795, possession 31 Jul 2030). Check that your agreement names the registration of your own wing.

How can I get updates if BHOOMI ICON WING A's possession date changes?

The latest dates are on BHOOMI ICON WING A's MahaRERA page (P51700026412). GharKundli's Kundli Watch sends a free WhatsApp update on BHOOMI ICON WING A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BHOOMI ICON WING A have?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A has one building filed: A WING with 19 floors and 91 units.

How much parking does BHOOMI ICON WING A have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 93 covered car parking spaces for BHOOMI ICON WING A.

How big is the land of BHOOMI ICON WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A stands on 3,002 sq m of land (about 0.7 acres), with 7,255 sq m of sanctioned built-up area.

What is the track record of BHOOMI ICON WING A's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Fornax Realty has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of BHOOMI ICON WING A?

Google Maps has reviews of BHOOMI ICON WING A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BHOOMI ICON WING A?

BHOOMI ICON WING A by FORNAX REALTY is in Kopar Khairane, Thane (pincode 400709), near Koparkhairane, Navi Mumbai, Kopar Khairne, Maharashtra, and is registered on MahaRERA as P51700026412, per GharKundli's check of MahaRERA records.

How many homes are in BHOOMI ICON WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A has 68 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.

When was BHOOMI ICON WING A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), BHOOMI ICON WING A was registered on MahaRERA on 17 September 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on BHOOMI ICON WING A?

No court cases are listed for BHOOMI ICON WING A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of BHOOMI ICON WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is FORNAX REALTY, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in pincode 400709

All 25 projects in Koparkhairane (400709) →

Other projects by FORNAX REALTY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.