Mahalaxmi Heights
by Mahalaxmi Infra · Koparkhairane, ThaneAlso near Vashi, Kopar Khairane, Kopar Khairne
Possession date of Mahalaxmi Heights: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1330002500089, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Mahalaxmi Heights?
How the possession date of Mahalaxmi Heights has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Mahalaxmi Heights’s extension records on MahaRERA (PR1330002500089), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahalaxmi Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1330002500089
- Status
- Registered and active
- Builder
- Mahalaxmi Infra
- Location
- Koparkhairane, Thane · 400709
- Project type
- Residential / Group Housing
- Registered on
- 23 Jun 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 41
- Sold or booked
- 65%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 12
Construction progress of Mahalaxmi Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A (1) | 100% | 90.9% | 59.5% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- A (1): covers 22 floors
Latest CC order on MahaRERA: dated 16/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahalaxmi Heights every month.
Mahalaxmi Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: A (1) (22 floors, 41 units)
- Car parking: 48 covered
- Land: 774 sq m (about 0.2 acres) · sanctioned built-up 3,724 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Mahalaxmi Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahalaxmi Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mahalaxmi Heights
What is the possession date of Mahalaxmi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mahalaxmi Heights in Koparkhairane, Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Mahalaxmi Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahalaxmi Heights's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Mahalaxmi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mahalaxmi Heights in Koparkhairane, Thane is PR1330002500089.
Is Mahalaxmi Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights is registered as PR1330002500089 and its status is "Registered and active".
What is the construction status of Mahalaxmi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A (1) is 90.9% done and internal work 59.5%. GharKundli's full report compares construction progress with the deadline.
Does Mahalaxmi Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Mahalaxmi Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights is registered on MahaRERA as PR1330002500089, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Mahalaxmi Heights's possession date changes?
The latest dates are on Mahalaxmi Heights's MahaRERA page (PR1330002500089). GharKundli's Kundli Watch sends a free WhatsApp update on Mahalaxmi Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahalaxmi Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights has one building filed: A (1) with 22 floors and 41 units.
How much parking does Mahalaxmi Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 48 covered car parking spaces for Mahalaxmi Heights.
How big is the land of Mahalaxmi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights stands on 774 sq m of land (about 0.2 acres), with 3,724 sq m of sanctioned built-up area.
Where can I read reviews of Mahalaxmi Heights?
Google Maps has reviews of Mahalaxmi Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mahalaxmi Heights?
Mahalaxmi Heights by Mahalaxmi Infra is in Koparkhairane, Thane (pincode 400709), near Vashi, Kopar Khairane, Kopar Khairne, Maharashtra, and is registered on MahaRERA as PR1330002500089, per GharKundli's check of MahaRERA records.
How many homes are in Mahalaxmi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights has 41 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.
When was Mahalaxmi Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahalaxmi Heights was registered on MahaRERA on 23 June 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on Mahalaxmi Heights?
No court cases are listed for Mahalaxmi Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Mahalaxmi Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mahalaxmi Infra, which has 12 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mahalaxmi Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in pincode 400709
- BHOOMI ICON WING A
- THE TRELLIS
- Kamdhenu 23 West Grande
- Satyam Stella
- OPAL BAY
- BHOOMI ICON WING B
- Krishna Park view
- Satyam Dwarka
Other projects by Mahalaxmi Infra
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.