Kamdhenu 23 West Grande

by Accura Developers LLP · Khairane, ThaneAlso near Ghansoli, Kopar Khairne, Millenium Business Park

Possession date of Kamdhenu 23 West Grande: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700055502, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Kamdhenu 23 West Grande?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Kamdhenu 23 West Grande has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kamdhenu 23 West Grande’s extension records on MahaRERA (P51700055502), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kamdhenu 23 West Grande

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700055502
Status
Registered and active
Builder
Accura Developers LLP
Location
Khairane, Thane · 400709
Project type
Commercial
Registered on
2 Apr 2024
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
79%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Kamdhenu 23 West Grande, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building A100%100%53.33%16%

Commencement certificate (CC), as filed on MahaRERA

  • Building A: covers 28 (Ground + 27 Upper Floors)

Latest CC order on MahaRERA: dated 20/04/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kamdhenu 23 West Grande every month.

Kamdhenu 23 West Grande: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Accura Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2020, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Kamdhenu 23 West Grande →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kamdhenu 23 West Grande: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Kamdhenu 23 West Grande

What is the possession date of Kamdhenu 23 West Grande?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kamdhenu 23 West Grande in Khairane, Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kamdhenu 23 West Grande?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kamdhenu 23 West Grande's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kamdhenu 23 West Grande?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kamdhenu 23 West Grande in Khairane, Thane is P51700055502.

Is Kamdhenu 23 West Grande registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kamdhenu 23 West Grande is registered as P51700055502 and its status is "Registered and active".

What is the construction status of Kamdhenu 23 West Grande?

According to GharKundli's check of MahaRERA records (updated October 2026), Kamdhenu 23 West Grande's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building A is 100% done and internal work 53.33%. GharKundli's full report compares construction progress with the deadline.

Does Kamdhenu 23 West Grande have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kamdhenu 23 West Grande safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kamdhenu 23 West Grande is registered on MahaRERA as P51700055502, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Kamdhenu 23 West Grande's possession date changes?

The latest dates are on Kamdhenu 23 West Grande's MahaRERA page (P51700055502). GharKundli's Kundli Watch sends a free WhatsApp update on Kamdhenu 23 West Grande every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kamdhenu 23 West Grande have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kamdhenu 23 West Grande has one building filed: Building A with 28 floors and 544 units.

How much parking does Kamdhenu 23 West Grande have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 555 covered car parking spaces for Kamdhenu 23 West Grande.

How big is the land of Kamdhenu 23 West Grande?

According to GharKundli's check of MahaRERA records (updated October 2026), Kamdhenu 23 West Grande stands on 4,975 sq m of land (about 1.2 acres), with 33,631 sq m of sanctioned built-up area.

What is the track record of Kamdhenu 23 West Grande's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Accura Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2020, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Kamdhenu 23 West Grande?

Google Maps has reviews of Kamdhenu 23 West Grande written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Kamdhenu 23 West Grande?

Kamdhenu 23 West Grande by Accura Developers LLP is in Khairane, Thane (pincode 400709), near Ghansoli, Kopar Khairne, Millenium Business Park, Maharashtra, and is registered on MahaRERA as P51700055502, per GharKundli's check of MahaRERA records.

How many homes are in Kamdhenu 23 West Grande?

According to GharKundli's check of MahaRERA records (updated October 2026), Kamdhenu 23 West Grande has 0 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.

When was Kamdhenu 23 West Grande registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kamdhenu 23 West Grande was registered on MahaRERA on 2 April 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on Kamdhenu 23 West Grande?

No court cases are listed for Kamdhenu 23 West Grande on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Kamdhenu 23 West Grande?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Accura Developers LLP, which has 1 other project registered on MahaRERA.

All projects with possession due in 2029 in Thane →

Other projects in Thane

All 25 projects in Koparkhairane (400709) →

Other projects by Accura Developers LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.