ELANZA WING B
by STONEWALL BUILDCON LLP · Navghar, ThaneAlso near Mira Road East, Bhayander, Mira Bhayandar
Possession date of ELANZA WING B: 31 July 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700076791, and currently active. Its completion date is now July 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ELANZA WING B?
How the possession date of ELANZA WING B has moved
31 March 2027
Completion date given when the project was registered
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ELANZA WING B’s extension records on MahaRERA (P51700076791), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ELANZA WING B
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- ELANZA WING AP51700076871 · possession 31 Mar 2028
- MahaRERA registration
- P51700076791
- Status
- Registered and active
- Builder
- STONEWALL BUILDCON LLP
- Location
- Navghar, Thane · 401105
- Project type
- Others
- Registered on
- 28 Jun 2024
- Completion date at registration
- March 2027
- Latest completion date
- July 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 21
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of ELANZA WING B, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ELANZA WING B | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- ELANZA WING B: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ELANZA WING B every month.
ELANZA WING B: buildings, flats and land, as filed on MahaRERA
- Buildings: ELANZA WING B (8 floors, 27 units)
- Car parking: 87 covered
- Land: 2,433 sq m (about 0.6 acres) · sanctioned built-up 1,389 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Stonewall Buildcon has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of ELANZA WING B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ELANZA WING B: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ELANZA WING B
What is the possession date of ELANZA WING B?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ELANZA WING B in Navghar, Thane is 31 July 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ELANZA WING B?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ELANZA WING B's builder has filed on MahaRERA, the official one, is 31 July 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ELANZA WING B?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ELANZA WING B in Navghar, Thane is P51700076791.
Is ELANZA WING B registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ELANZA WING B is registered as P51700076791 and its status is "Registered and active".
What is the construction status of ELANZA WING B?
According to GharKundli's check of MahaRERA records (updated October 2026), ELANZA WING B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ELANZA WING B is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does ELANZA WING B have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ELANZA WING B safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ELANZA WING B is registered on MahaRERA as P51700076791, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does ELANZA WING B have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ELANZA WING A (P51700076871, possession 31 Mar 2028). Check that your agreement names the registration of your own wing.
How can I get updates if ELANZA WING B's possession date changes?
The latest dates are on ELANZA WING B's MahaRERA page (P51700076791). GharKundli's Kundli Watch sends a free WhatsApp update on ELANZA WING B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ELANZA WING B have?
According to GharKundli's check of MahaRERA records (updated October 2026), ELANZA WING B has one building filed: ELANZA WING B with 8 floors and 27 units.
How much parking does ELANZA WING B have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 87 covered car parking spaces for ELANZA WING B.
How big is the land of ELANZA WING B?
According to GharKundli's check of MahaRERA records (updated October 2026), ELANZA WING B stands on 2,433 sq m of land (about 0.6 acres), with 1,389 sq m of sanctioned built-up area.
What is the track record of ELANZA WING B's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Stonewall Buildcon has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ELANZA WING B?
Google Maps has reviews of ELANZA WING B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ELANZA WING B?
ELANZA WING B by STONEWALL BUILDCON LLP is in Navghar, Thane (pincode 401105), near Mira Road East, Bhayander, Mira Bhayandar, Maharashtra, and is registered on MahaRERA as P51700076791, per GharKundli's check of MahaRERA records.
How many homes are in ELANZA WING B?
According to GharKundli's check of MahaRERA records (updated October 2026), ELANZA WING B has 21 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was ELANZA WING B registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ELANZA WING B was registered on MahaRERA on 28 June 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on ELANZA WING B?
2 court cases are listed for ELANZA WING B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ELANZA WING B?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is STONEWALL BUILDCON LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ELANZA WING B
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Navghar
- ELANZA WING A
- N G GRAND EMPIRE PHASE II
- CLASSIC NANDA DEEP
- SAROJ HEIGHTS
- N G AROMA PHASE I
- N G GRAND EMPIRE PHASE I
- IMPERIAL LUXURIA
- N G AROMA PHASE II
Other projects by STONEWALL BUILDCON LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.