Possession date of N G AROMA PHASE I: 31 December 2026. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700032309, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about N G AROMA PHASE I?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on N G AROMA PHASE I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700032309
Status
Registered and active
Builder
RNA Builders (NG)
Location
Navghar, Thane · 401107
Project type
Residential / Group Housing
Registered on
29 Dec 2021
Completion date at registration
December 2026
Homes
165
Sold or booked
25%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
22

Construction progress of N G AROMA PHASE I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%85%60%5%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING NO 1: covers 23 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on N G AROMA PHASE I every month.

N G AROMA PHASE I: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (23 floors, 179 units)
  • Car parking: 82 covered
  • Land: 2,483 sq m (about 0.6 acres) · sanctioned built-up 9,862 sq m

The builder’s record and reviews

RNA Builders NG has 23 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 16 months); 7 still being built, 2 past the promised date (typically 24 months late); 4 lapsed. 4 complaints on MahaRERA across 4 projects.

Read Google reviews of N G AROMA PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

N G AROMA PHASE I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about N G AROMA PHASE I

What is the possession date of N G AROMA PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for N G AROMA PHASE I in Navghar, Thane is 31 December 2026.

Is the builder's possession date different from the MahaRERA date for N G AROMA PHASE I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date N G AROMA PHASE I's builder has filed on MahaRERA, the official one, is 31 December 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of N G AROMA PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of N G AROMA PHASE I in Navghar, Thane is P51700032309.

Is N G AROMA PHASE I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), N G AROMA PHASE I is registered as P51700032309 and its status is "Registered and active".

What is the construction status of N G AROMA PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), N G AROMA PHASE I's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 1 is 85% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does N G AROMA PHASE I have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is N G AROMA PHASE I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), N G AROMA PHASE I is registered on MahaRERA as P51700032309, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does N G AROMA PHASE I have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: N G AROMA PHASE II (P51700032464, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.

How can I get updates if N G AROMA PHASE I's possession date changes?

The latest dates are on N G AROMA PHASE I's MahaRERA page (P51700032309). GharKundli's Kundli Watch sends a free WhatsApp update on N G AROMA PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does N G AROMA PHASE I have?

According to GharKundli's check of MahaRERA records (updated October 2026), N G AROMA PHASE I has one building filed: BUILDING NO 1 with 23 floors and 179 units.

How much parking does N G AROMA PHASE I have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 82 covered car parking spaces for N G AROMA PHASE I.

How big is the land of N G AROMA PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), N G AROMA PHASE I stands on 2,483 sq m of land (about 0.6 acres), with 9,862 sq m of sanctioned built-up area.

What is the track record of N G AROMA PHASE I's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA Builders NG has 23 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 16 months); 7 still being built, 2 past the promised date (typically 24 months late); 4 lapsed. 4 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of N G AROMA PHASE I?

Google Maps has reviews of N G AROMA PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is N G AROMA PHASE I?

N G AROMA PHASE I by RNA Builders (NG) is in Navghar, Thane (pincode 401107), Maharashtra, and is registered on MahaRERA as P51700032309, per GharKundli's check of MahaRERA records.

How many homes are in N G AROMA PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), N G AROMA PHASE I has 165 homes in 1 tower registered on MahaRERA, and 25% of them are sold or booked.

When was N G AROMA PHASE I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), N G AROMA PHASE I was registered on MahaRERA on 29 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on N G AROMA PHASE I?

No court cases are listed for N G AROMA PHASE I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of N G AROMA PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RNA Builders (NG), which has 22 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Navghar

All 322 projects in Mira Road East (401107) →

Other projects by RNA Builders (NG)

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.