by RNA Builders (NG) · Goddev, Thane 401101Also near Mira Road East, Bhayander East, Village NavgharRegistered on MahaRERA as “N G AVENUE”

What’s in the report? →

Possession date of RNA N G Avenue (MahaRERA P51700031064): 30 April 2028, moved from 31 December 2023 (48 months later). It has 20 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700031064, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700031064, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about RNA N G Avenue?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of RNA N G Avenue has moved

  1. 31 December 2023

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA11092502558)

    Reason the builder gave MahaRERA:
    “Reasons for Delay: 1. Delay in Statutory Approvals: Permissions from urban local bodies and utility agencies were delayed, affecting the construction schedule for environmental clearances. 2. Unforeseen Technical Challenges: Site-related is…” Read the full reason“Reasons for Delay: 1. Delay in Statutory Approvals: Permissions from urban local bodies and utility agencies were delayed, affecting the construction schedule for environmental clearances. 2. Unforeseen Technical Challenges: Site-related issues including environmental clearances.”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RNA N G Avenue’s extension records on MahaRERA (P51700031064), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RNA N G Avenue

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700031064
Status
Registered and active
Builder
RNA Builders (NG)
Location
Goddev, Thane · 401101
Project type
Residential / Group Housing
Registered on
5 Oct 2021
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
20
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
22

Construction progress of RNA N G Avenue, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
N G AVENUE100%20%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • N G AVENUE: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RNA N G Avenue every 1–2 months.

RNA N G Avenue: buildings, flats and land, as filed on MahaRERA

  • Buildings: N G AVENUE (5 floors, 20 units)
  • Land: 630 sq m (about 0.2 acres) · sanctioned built-up 948 sq m · recreational space 95 sq m
  • Boundaries filed include: CNG STATION, MIRA BHAYANDAR ROAD
  • Land, as filed: OLD S NO 368/28 NEW SURVEY NO 70/28
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

RNA Builders NG has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 16 months); 11 still being built, 6 past the promised date (typically 32 months late); 4 lapsed. 19 complaints on MahaRERA across 5 projects.

Read Google reviews of RNA N G Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RNA N G Avenue: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about RNA N G Avenue

What is the possession date of RNA N G Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RNA N G Avenue in Goddev, Thane is 30 April 2028 — 48 months later than 31 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for RNA N G Avenue?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RNA N G Avenue's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of RNA N G Avenue extended?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Reasons for Delay: 1. Delay in Statutory Approvals: Permissions from urban local bodies and utility agencies were delayed, affecting the construction schedule for environmental clearances. 2. Unforeseen Technical Challenges: Site-related issues including environmental clearances.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of RNA N G Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RNA N G Avenue in Goddev, Thane is P51700031064.

Is RNA N G Avenue registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue is registered as P51700031064 and its status is "Registered and active".

What is the current construction status of RNA N G Avenue? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue's status on MahaRERA is "Registered and active". As filed by the builder, slab work on N G AVENUE is 20% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does RNA N G Avenue have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is RNA N G Avenue safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue is registered on MahaRERA as P51700031064, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in RNA N G Avenue?

RNA N G Avenue is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in RNA N G Avenue?

For a flat in RNA N G Avenue (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has RNA N G Avenue received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has RNA N G Avenue uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for RNA N G Avenue was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if RNA N G Avenue's possession date changes?

The latest dates are on RNA N G Avenue's MahaRERA page (P51700031064). GharKundli's Kundli Watch sends a free WhatsApp update on RNA N G Avenue every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RNA N G Avenue have?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue has one building filed: N G AVENUE with 5 floors and 20 units.

How big is the land of RNA N G Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue stands on 630 sq m of land (about 0.2 acres), with 948 sq m of sanctioned built-up area and 95 sq m of recreational open space.

What is the track record of RNA N G Avenue's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA Builders NG has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 16 months); 11 still being built, 6 past the promised date (typically 32 months late); 4 lapsed. 19 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of RNA N G Avenue?

Google Maps has reviews of RNA N G Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of RNA N G Avenue?

RNA N G Avenue by RNA Builders (NG) is in Goddev, Thane, pincode 401101 (near Mira Road East, Bhayander East, Village Navghar), Maharashtra, and is registered on MahaRERA as P51700031064, per GharKundli's check of MahaRERA records. Its boundaries filed there include CNG STATION, MIRA BHAYANDAR ROAD. Its land is filed as OLD S NO 368/28 NEW SURVEY NO 70/28. GharKundli lists all 99 MahaRERA projects in Bhayander West (401101).

How many flats are in RNA N G Avenue, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue has 20 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was RNA N G Avenue registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA N G Avenue was registered on MahaRERA on 5 October 2021. GharKundli did not find a title report on the land on file there.

Does RNA N G Avenue have any legal issues or court cases?

No court cases are listed for RNA N G Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of RNA N G Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RNA Builders (NG), which has 22 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Bhayander West (401101)

All 99 projects in Bhayander West (401101) →

Other projects by RNA Builders (NG)

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.