by RNA Builders (NG) · Goddev, Thane 401101Also near Mira Road East, Bhayander East, Village Navghar

What’s in the report? →

Possession date of N G Silver Spring Phase III (MahaRERA P51700031911): 30 April 2027, moved from 31 December 2024 (24 months later). It has 47 homes, 89% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700031911, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700031911, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about N G Silver Spring Phase III?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of N G Silver Spring Phase III has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700028149)

    Reason the builder gave MahaRERA:
    “Date:19.08.2025 To, The Secretary, Maharashtra Real Estate Regulatory Authority (MahaRERA), Mumbai. Subject: Application for Extension of Project Completion Date under Section 7(3) of the RERA Act, 2016. Reference:1. Application EXT51700028…” Read the full reason“Date:19.08.2025 To, The Secretary, Maharashtra Real Estate Regulatory Authority (MahaRERA), Mumbai. Subject: Application for Extension of Project Completion Date under Section 7(3) of the RERA Act, 2016. Reference:1. Application EXT51700028149 for registration under MahaRERA. 2. Email received on 14.08.2025. Project Name: N G SILVER SPRING PHASE III Project Registration No.: P51700031911 Promoter Name: RNA BUILDERS (NG) Project Address: N G SILVE SPRING PHASE III, plot bearing CTS OLD S NO 310 NEW S NO 56 H NO 2P OLD S NO 311 NEW S NO 43 H NO 1 at Mira Bhayandar (M Corp.), Thane, 401101. De…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA11092502565)

    Reason the builder gave MahaRERA:
    “Reasons for Delay: Delay in Statutory Approvals: Permissions from urban local bodies and utility agencies were delayed, affecting the construction schedule for environmental clearances. Revised Timeline: We seek extension from the original…” Read the full reason“Reasons for Delay: Delay in Statutory Approvals: Permissions from urban local bodies and utility agencies were delayed, affecting the construction schedule for environmental clearances. Revised Timeline: We seek extension from the original completion date 31st December, 2024 to the revised proposed date 31st December,2026.”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: N G Silver Spring Phase III’s extension records on MahaRERA (P51700031911), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on N G Silver Spring Phase III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700031911
Status
Registered and active
Builder
RNA Builders (NG)
Location
Goddev, Thane · 401101
Project type
Residential / Group Housing
Registered on
22 Nov 2021
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
47
Sold or booked
89%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
22

Construction progress of N G Silver Spring Phase III, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 3 WING B100%84%15%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING NO 3 WING B: covers 12 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on N G Silver Spring Phase III every 1–2 months.

N G Silver Spring Phase III: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 3 WING B (14 floors, 47 units)
  • Car parking: 1 covered, 12 open
  • Land: 2,500 sq m (about 0.6 acres) · sanctioned built-up 2,440 sq m · recreational space 375 sq m
  • Boundaries filed include: SHREEJI COMPLEX, IDEAL PARK, RAMDEV PARK
  • Land, as filed: OLD S NO 310 NEW S NO 56 H NO 2P OLD S NO 311 NEW S NO 43 H NO 1
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

RNA Builders NG has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 16 months); 11 still being built, 6 past the promised date (typically 32 months late); 4 lapsed. 19 complaints on MahaRERA across 5 projects.

Read Google reviews of N G Silver Spring Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

N G Silver Spring Phase III: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about N G Silver Spring Phase III

What is the possession date of N G Silver Spring Phase III?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for N G Silver Spring Phase III in Goddev, Thane is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for N G Silver Spring Phase III?

Builders and listing sites often quote an earlier "target" date for handover. The completion date N G Silver Spring Phase III's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of N G Silver Spring Phase III extended?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Date:19.08.2025 To, The Secretary, Maharashtra Real Estate Regulatory Authority (MahaRERA), Mumbai. Subject: Application for Extension of Project Completion Date under Section 7(3) of the RERA Act, 2016. Reference:1. Application EXT51700028149 for registration under MahaRERA. 2. Email received on 14.08.2025. Project Name: N G SILVER SPRING PHASE III Project Registration No.: P51700031911 Promoter Name: RNA BUILDERS (NG) Project Address: N G SILVE SPRING PHASE III, plot bearing CTS OLD S NO 310 NEW S NO 56 H NO 2P OLD S NO 311 NEW S NO 43 H NO 1 at Mira Bhayandar (M Corp.), Thane, 401101. De…"; to 31 December 2026, giving the reason "Reasons for Delay: Delay in Statutory Approvals: Permissions from urban local bodies and utility agencies were delayed, affecting the construction schedule for environmental clearances. Revised Timeline: We seek extension from the original completion date 31st December, 2024 to the revised proposed date 31st December,2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of N G Silver Spring Phase III?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of N G Silver Spring Phase III in Goddev, Thane is P51700031911.

Is N G Silver Spring Phase III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III is registered as P51700031911 and its status is "Registered and active".

What is the current construction status of N G Silver Spring Phase III? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 3 WING B is 84% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.

Does N G Silver Spring Phase III have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is N G Silver Spring Phase III safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III is registered on MahaRERA as P51700031911, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in N G Silver Spring Phase III?

N G Silver Spring Phase III is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in N G Silver Spring Phase III?

For a flat in N G Silver Spring Phase III (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has N G Silver Spring Phase III received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has N G Silver Spring Phase III uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for N G Silver Spring Phase III was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does N G Silver Spring Phase III have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: N G Silver Spring (P51700000009, possession 15 Dec 2018); N G SILVER SPRING PHASE II (P51700018291, possession 30 Dec 2021). Check that your agreement names the registration of your own wing.

How can I get updates if N G Silver Spring Phase III's possession date changes?

The latest dates are on N G Silver Spring Phase III's MahaRERA page (P51700031911). GharKundli's Kundli Watch sends a free WhatsApp update on N G Silver Spring Phase III every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does N G Silver Spring Phase III have?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III has one building filed: BUILDING NO 3 WING B with 14 floors and 47 units.

How much parking does N G Silver Spring Phase III have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 12 open car parking spaces for N G Silver Spring Phase III.

How big is the land of N G Silver Spring Phase III?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III stands on 2,500 sq m of land (about 0.6 acres), with 2,440 sq m of sanctioned built-up area and 375 sq m of recreational open space.

What is the track record of N G Silver Spring Phase III's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), RNA Builders NG has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 16 months); 11 still being built, 6 past the promised date (typically 32 months late); 4 lapsed. 19 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of N G Silver Spring Phase III?

Google Maps has reviews of N G Silver Spring Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of N G Silver Spring Phase III?

N G Silver Spring Phase III by RNA Builders (NG) is in Goddev, Thane, pincode 401101 (near Mira Road East, Bhayander East, Village Navghar), Maharashtra, and is registered on MahaRERA as P51700031911, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHREEJI COMPLEX, IDEAL PARK, RAMDEV PARK. Its land is filed as OLD S NO 310 NEW S NO 56 H NO 2P OLD S NO 311 NEW S NO 43 H NO 1. GharKundli lists all 99 MahaRERA projects in Bhayander West (401101).

How many flats are in N G Silver Spring Phase III, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III has 47 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.

When was N G Silver Spring Phase III registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), N G Silver Spring Phase III was registered on MahaRERA on 22 November 2021. GharKundli did not find a title report on the land on file there.

Does N G Silver Spring Phase III have any legal issues or court cases?

No court cases are listed for N G Silver Spring Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of N G Silver Spring Phase III?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RNA Builders (NG), which has 22 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Bhayander West (401101)

All 99 projects in Bhayander West (401101) →

Other projects by RNA Builders (NG)

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.