Lodha Belvedere I

by Lodha Developers Limited · Hedutane, Thane 421203Registered on MahaRERA as “Belvedere I”

What’s in the report? →

Possession date of Lodha Belvedere I (MahaRERA P51700077599): 30 April 2031, moved from 31 July 2028 (29 months later). It has 95 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700077599, and currently active. Its completion date has moved from July 2028 to April 2031: 29 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700077599, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Lodha Belvedere I?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Lodha Belvedere I has moved

  1. 31 July 2028

    Completion date given when the project was registered

  2. 31 December 2030

    Extended at the builder's request (MahaRERA application EA07072621689)

    Reason the builder gave MahaRERA:
    “Due to management decisions and planning, there was a delay in “Belvedere I” launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now , at the time of extension request witho…” Read the full reason“Due to management decisions and planning, there was a delay in “Belvedere I” launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now , at the time of extension request without allotees in this project. There are no allotee in this project”
  3. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Lodha Belvedere I’s extension records on MahaRERA (P51700077599), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lodha Belvedere I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700077599
Status
Registered and active
Builder
Lodha Developers Limited
Location
Hedutane, Thane · 421203
Project type
Residential / Group Housing
Registered on
15 Oct 2024
Completion date at registration
July 2028
Latest completion date
April 2031
Delay so far
29 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
95
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Lodha Belvedere I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Belvedere I0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Belvedere I: covers 23 floors

Latest CC order on MahaRERA: dated 30/12/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lodha Belvedere I every 1–2 months.

Lodha Belvedere I: buildings, flats and land, as filed on MahaRERA

  • Buildings: Belvedere I (23 floors, 95 units)
  • Car parking: 67 covered
  • Land: 1,459 sq m (about 0.4 acres) · sanctioned built-up 11,232 sq m · recreational space 145 sq m
  • Land, as filed: 25/2A Part 25/2B Part
  • Map: Get directions

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects.

Read Google reviews of Lodha Belvedere I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lodha Belvedere I: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lodha Belvedere I

What is the possession date of Lodha Belvedere I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lodha Belvedere I in Hedutane, Thane is 30 April 2031 — 29 months later than 31 July 2028, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 29 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Lodha Belvedere I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lodha Belvedere I's builder has filed on MahaRERA, the official one, is 30 April 2031, already 29 months later than the 31 July 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Lodha Belvedere I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "Due to management decisions and planning, there was a delay in “Belvedere I” launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now , at the time of extension request without allotees in this project. There are no allotee in this project". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Lodha Belvedere I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lodha Belvedere I in Hedutane, Thane is P51700077599.

Is Lodha Belvedere I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I is registered as P51700077599 and its status is "Registered and active".

What is the current construction status of Lodha Belvedere I? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Belvedere I is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Lodha Belvedere I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Lodha Belvedere I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I is registered on MahaRERA as P51700077599, its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lodha Belvedere I?

Lodha Belvedere I is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lodha Belvedere I?

For a flat in Lodha Belvedere I (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Lodha Belvedere I received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Lodha Belvedere I uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lodha Belvedere I was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Lodha Belvedere I have other wings or phases?

Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Belvedere D (P51700052237, possession 29 Jun 2028); Belvedere E (P51700078941, possession 30 Jan 2030); Belvedere H (P51700052333, possession 31 May 2027); Belvedere J (P51700078768, possession 30 Apr 2030); Belvedere-K (P51700078177, possession 30 Jan 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Lodha Belvedere I's possession date changes?

The latest dates are on Lodha Belvedere I's MahaRERA page (P51700077599). GharKundli's Kundli Watch sends a free WhatsApp update on Lodha Belvedere I every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lodha Belvedere I have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I has one building filed: Belvedere I with 23 floors and 95 units.

How much parking does Lodha Belvedere I have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 67 covered car parking spaces for Lodha Belvedere I.

How big is the land of Lodha Belvedere I?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I stands on 1,459 sq m of land (about 0.4 acres), with 11,232 sq m of sanctioned built-up area and 145 sq m of recreational open space.

What is the track record of Lodha Belvedere I's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 386 GharKundli has checked: 219 finished, 201 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 16 past the promised date (typically 1 months late). 602 complaints on MahaRERA across 163 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Lodha Belvedere I?

Google Maps has reviews of Lodha Belvedere I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lodha Belvedere I?

Lodha Belvedere I by Lodha Developers Limited is in Hedutane, Thane, pincode 421203, Maharashtra, and is registered on MahaRERA as P51700077599, per GharKundli's check of MahaRERA records. Its land is filed as 25/2A Part 25/2B Part. GharKundli lists all 98 MahaRERA projects in Dombivali (421203).

How many flats are in Lodha Belvedere I, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I has 95 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Lodha Belvedere I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha Belvedere I was registered on MahaRERA on 15 October 2024. GharKundli did not find a title report on the land on file there.

Does Lodha Belvedere I have any legal issues or court cases?

1 court case is listed for Lodha Belvedere I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Lodha Belvedere I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2031 in Thane →

Other projects in Dombivali (421203)

All 98 projects in Dombivali (421203) →

Other projects by Lodha Developers Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.