ATLANTA AVADH
by ATLANTA GLOBALPROJECTS LLP · Near Kohinoor Prime, Thane
Possession date of ATLANTA AVADH: 30 August 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700078244, and currently active. Its completion date is now August 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ATLANTA AVADH?
How the possession date of ATLANTA AVADH has moved
30 April 2028
Completion date given when the project was registered
30 August 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ATLANTA AVADH’s extension records on MahaRERA (P51700078244), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ATLANTA AVADH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700078244
- Status
- Registered and active
- Builder
- ATLANTA GLOBALPROJECTS LLP
- Location
- Near Kohinoor Prime, Thane · 421001
- Project type
- Residential / Group Housing
- Registered on
- 29 Nov 2024
- Completion date at registration
- April 2028
- Latest completion date
- August 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 144
- Sold or booked
- 34%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ATLANTA AVADH, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 1 | 100% | 95% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 1: covers 16 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ATLANTA AVADH every month.
ATLANTA AVADH: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 1 (16 floors, 144 units)
- Land: 1,736 sq m (about 0.4 acres) · sanctioned built-up 6,941 sq m
- Boundaries filed include: KOHINOOR GARDEN, MUNICIPAL GARDEN
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ATLANTA AVADH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ATLANTA AVADH: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ATLANTA AVADH
What is the possession date of ATLANTA AVADH?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ATLANTA AVADH in Near Kohinoor Prime, Thane is 30 August 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ATLANTA AVADH?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ATLANTA AVADH's builder has filed on MahaRERA, the official one, is 30 August 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ATLANTA AVADH?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ATLANTA AVADH in Near Kohinoor Prime, Thane is P51700078244.
Is ATLANTA AVADH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA AVADH is registered as P51700078244 and its status is "Registered and active".
What is the construction status of ATLANTA AVADH?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA AVADH's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 1 is 95% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does ATLANTA AVADH have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ATLANTA AVADH safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA AVADH is registered on MahaRERA as P51700078244, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ATLANTA AVADH's possession date changes?
The latest dates are on ATLANTA AVADH's MahaRERA page (P51700078244). GharKundli's Kundli Watch sends a free WhatsApp update on ATLANTA AVADH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ATLANTA AVADH have?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA AVADH has one building filed: BUILDING NO 1 with 16 floors and 144 units.
How big is the land of ATLANTA AVADH?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA AVADH stands on 1,736 sq m of land (about 0.4 acres), with 6,941 sq m of sanctioned built-up area.
Where can I read reviews of ATLANTA AVADH?
Google Maps has reviews of ATLANTA AVADH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ATLANTA AVADH?
ATLANTA AVADH by ATLANTA GLOBALPROJECTS LLP is in Near Kohinoor Prime, Thane (pincode 421001), Maharashtra, and is registered on MahaRERA as P51700078244, per GharKundli's check of MahaRERA records. Its boundaries filed there include KOHINOOR GARDEN, MUNICIPAL GARDEN.
How many homes are in ATLANTA AVADH?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA AVADH has 144 homes in 1 tower registered on MahaRERA, and 34% of them are sold or booked.
When was ATLANTA AVADH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA AVADH was registered on MahaRERA on 29 November 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on ATLANTA AVADH?
No court cases are listed for ATLANTA AVADH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ATLANTA AVADH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ATLANTA GLOBALPROJECTS LLP.
Check it yourself on MahaRERA
- How to check the possession date of ATLANTA AVADH
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ulhasnagar
All Thane projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.