Ramatai Heights
by Ashtavinayak Builders and Developers · At Gotheghar, Thane
Registered on MahaRERA under P51700079072, and currently active. Its completion date has moved from December 2026 to April 2027, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Ramatai Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700079072
- Status
- Registered and active
- Builder
- Ashtavinayak Builders and Developers
- Location
- At Gotheghar, Thane · 421601
- Project type
- Residential / Group Housing
- Registered on
- 3 Feb 2025
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- Delay so far
- 4 months
- Homes
- 12
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Kundli Watch
Ramatai Heights: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Ramatai Heights
Is Ramatai Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ramatai Heights is registered as P51700079072 and its status is "Registered and active".
Where is Ramatai Heights?
Ramatai Heights by Ashtavinayak Builders and Developers is in At Gotheghar, Thane (pincode 421601), Maharashtra, and is registered on MahaRERA as P51700079072, per GharKundli's check of MahaRERA records.
When is possession of Ramatai Heights due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ramatai Heights in At Gotheghar, Thane is 30 April 2027 — 4 months later than 31 December 2026, the date given at registration.
Does Ramatai Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Ramatai Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ashtavinayak Builders and Developers, which has 5 other projects registered on MahaRERA.
Other projects in pincode 421601
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.