Hill Park Co-Operative Housing Society Limited
by Unigrow On Infrastructure Housing LLP · Vadavali, Thane 421501Also near Ambernath, Morivali, Chikhloli
What’s in the report? →Possession date of Hill Park Co-Operative Housing Society Limited (MahaRERA P51700079449): 31 December 2028. It has 79 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700079449, and currently active. Its completion date is now December 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700079449, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Hill Park Co-Operative Housing Society Limited?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Hill Park Co-Operative Housing Society Limited has moved
31 August 2028
Completion date given when the project was registered
31 December 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Hill Park Co-Operative Housing Society Limited’s extension records on MahaRERA (P51700079449), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hill Park Co-Operative Housing Society Limited
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700079449
- Status
- Registered and active
- Builder
- Unigrow On Infrastructure Housing LLP
- Location
- Vadavali, Thane · 421501
- Project type
- Others
- Registered on
- 6 Mar 2025
- Completion date at registration
- August 2028
- Latest completion date
- December 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 79
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Hill Park Co-Operative Housing Society Limited, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Hill Park Co-Operative Housing Society Limited | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Hill Park Co-Operative Housing Society Limited: covers STILT FLOOR+1ST TO 8TH fLOOR
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hill Park Co-Operative Housing Society Limited every 1–2 months.
Hill Park Co-Operative Housing Society Limited: buildings, flats and land, as filed on MahaRERA
- Buildings: Hill Park Co-Operative Housing Society Limited (9 floors, 89 units)
- Land: 1,535 sq m (about 0.4 acres) · sanctioned built-up 4,180 sq m
- Boundaries filed include: Public Road
- Land, as filed: CTS No 8971/22 and CTS No 8971/23
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Hill Park Co-Operative Housing Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hill Park Co-Operative Housing Society Limited: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Hill Park Co-Operative Housing Society Limited
What is the possession date of Hill Park Co-Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hill Park Co-Operative Housing Society Limited in Vadavali, Thane is 31 December 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Hill Park Co-Operative Housing Society Limited?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hill Park Co-Operative Housing Society Limited's builder has filed on MahaRERA, the official one, is 31 December 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Hill Park Co-Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hill Park Co-Operative Housing Society Limited in Vadavali, Thane is P51700079449.
Is Hill Park Co-Operative Housing Society Limited registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited is registered as P51700079449 and its status is "Registered and active".
What is the current construction status of Hill Park Co-Operative Housing Society Limited? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Hill Park Co-Operative Housing Society Limited is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Hill Park Co-Operative Housing Society Limited have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Hill Park Co-Operative Housing Society Limited safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited is registered on MahaRERA as P51700079449, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Hill Park Co-Operative Housing Society Limited?
Hill Park Co-Operative Housing Society Limited is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Hill Park Co-Operative Housing Society Limited?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Hill Park Co-Operative Housing Society Limited: gharkundli.com/tools/property-cost-calculator
Has Hill Park Co-Operative Housing Society Limited received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited is still under construction, with 31 December 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Hill Park Co-Operative Housing Society Limited a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited is a redevelopment: 42 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Hill Park Co-Operative Housing Society Limited uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hill Park Co-Operative Housing Society Limited was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Hill Park Co-Operative Housing Society Limited's possession date changes?
The latest dates are on Hill Park Co-Operative Housing Society Limited's MahaRERA page (P51700079449). GharKundli's Kundli Watch sends a free WhatsApp update on Hill Park Co-Operative Housing Society Limited every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hill Park Co-Operative Housing Society Limited have?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited has one building filed: Hill Park Co-Operative Housing Society Limited with 9 floors and 89 units.
How big is the land of Hill Park Co-Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited stands on 1,535 sq m of land (about 0.4 acres), with 4,180 sq m of sanctioned built-up area.
What are the reviews of Hill Park Co-Operative Housing Society Limited?
Google Maps has reviews of Hill Park Co-Operative Housing Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Hill Park Co-Operative Housing Society Limited?
Hill Park Co-Operative Housing Society Limited by Unigrow On Infrastructure Housing LLP is in Vadavali, Thane, pincode 421501 (near Ambernath, Morivali, Chikhloli), Maharashtra, and is registered on MahaRERA as P51700079449, per GharKundli's check of MahaRERA records. Its boundaries filed there include Public Road. Its land is filed as CTS No 8971/22 and CTS No 8971/23. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Hill Park Co-Operative Housing Society Limited, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited has 79 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Hill Park Co-Operative Housing Society Limited registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Park Co-Operative Housing Society Limited was registered on MahaRERA on 6 March 2025. GharKundli did not find a title report on the land on file there.
Does Hill Park Co-Operative Housing Society Limited have any legal issues or court cases?
No court cases are listed for Hill Park Co-Operative Housing Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Hill Park Co-Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Unigrow On Infrastructure Housing LLP.
Check it yourself on MahaRERA
- How to check the possession date of Hill Park Co-Operative Housing Society Limited
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Ambernath (421501)
- Ishwar Jay Jay Shankara Co-op. Housing Society LTD.
- Laxmi Narayan Co-op Housing Society Ltd
- Ashok Smruti
- Ashok Vatika
- Sai Sarvesh
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.