Possession date of Life Sadhana Sadan (MahaRERA P51700080175): 20 January 2028. It has 23 homes, 70% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700080175, and currently active. Its completion date is now January 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700080175, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Life Sadhana Sadan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Life Sadhana Sadan has moved

  1. 20 September 2027

    Completion date given when the project was registered

  2. 20 January 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Life Sadhana Sadan’s extension records on MahaRERA (P51700080175), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Life Sadhana Sadan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700080175
Status
Registered and active
Builder
SM LIFE SPACE PRIVATE LIMITED
Location
Naupada S.O (Thane), Thane · 400602
Project type
Residential / Group Housing
Registered on
5 May 2025
Completion date at registration
September 2027
Latest completion date
January 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
23
Sold or booked
70%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Life Sadhana Sadan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SADHANA SADAN95%90%44%0%

Commencement certificate (CC), as filed on MahaRERA

  • SADHANA SADAN: covers 8TH FLOOR

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Life Sadhana Sadan every 1–2 months.

Life Sadhana Sadan: buildings, flats and land, as filed on MahaRERA

  • Buildings: SADHANA SADAN (9 floors, 23 units)
  • Land: 556 sq m (about 0.1 acres) · sanctioned built-up 2,282 sq m
  • Boundaries filed include: GOKHALE ROAD, SARASWATI MANDIR PRIMARY SCHOOL, MAHATMA GANDHI ROAD
  • Land, as filed: CTS NO 27/1 Tika No 21
  • Map: Get directions

The builder’s record and reviews

SM Life Space has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.

Read Google reviews of Life Sadhana Sadan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Life Sadhana Sadan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Life Sadhana Sadan

What is the possession date of Life Sadhana Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Life Sadhana Sadan in Naupada S.O (Thane), Thane is 20 January 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Life Sadhana Sadan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Life Sadhana Sadan's builder has filed on MahaRERA, the official one, is 20 January 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Life Sadhana Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Life Sadhana Sadan in Naupada S.O (Thane), Thane is P51700080175.

Is Life Sadhana Sadan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan is registered as P51700080175 and its status is "Registered and active".

What is the current construction status of Life Sadhana Sadan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SADHANA SADAN is 90% done and internal work 44%. GharKundli's full report compares construction progress with the deadline.

Does Life Sadhana Sadan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Life Sadhana Sadan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan is registered on MahaRERA as P51700080175, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Life Sadhana Sadan?

Life Sadhana Sadan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Life Sadhana Sadan?

For a flat in Life Sadhana Sadan (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Life Sadhana Sadan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan is still under construction, with 20 January 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Life Sadhana Sadan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Life Sadhana Sadan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Life Sadhana Sadan's possession date changes?

The latest dates are on Life Sadhana Sadan's MahaRERA page (P51700080175). GharKundli's Kundli Watch sends a free WhatsApp update on Life Sadhana Sadan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Life Sadhana Sadan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan has one building filed: SADHANA SADAN with 9 floors and 23 units.

How big is the land of Life Sadhana Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan stands on 556 sq m of land (about 0.1 acres), with 2,282 sq m of sanctioned built-up area.

What is the track record of Life Sadhana Sadan's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), SM Life Space has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Life Sadhana Sadan?

Google Maps has reviews of Life Sadhana Sadan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Life Sadhana Sadan?

Life Sadhana Sadan by SM LIFE SPACE PRIVATE LIMITED is in Naupada S.O (Thane), Thane, pincode 400602, Maharashtra, and is registered on MahaRERA as P51700080175, per GharKundli's check of MahaRERA records. Its boundaries filed there include GOKHALE ROAD, SARASWATI MANDIR PRIMARY SCHOOL, MAHATMA GANDHI ROAD. Its land is filed as CTS NO 27/1 Tika No 21. GharKundli lists all 258 MahaRERA projects in Naupada (400602).

How many flats are in Life Sadhana Sadan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan has 23 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.

When was Life Sadhana Sadan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Life Sadhana Sadan was registered on MahaRERA on 5 May 2025. GharKundli did not find a title report on the land on file there.

Does Life Sadhana Sadan have any legal issues or court cases?

No court cases are listed for Life Sadhana Sadan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Life Sadhana Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SM LIFE SPACE PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Naupada (400602)

All 258 projects in Naupada (400602) →

Other projects by SM LIFE SPACE PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.