Devyani CHS
by Shree Swami Sanket Enterprises · Naupada, Thane 400602
What’s in the report? →Possession date of Devyani CHS (MahaRERA PM1330002500168): 30 September 2028. It has 28 homes, 17% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1330002500168, and currently active. Its completion date is now September 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1330002500168, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Devyani CHS?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Devyani CHS has moved
31 May 2028
Completion date given when the project was registered
30 September 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Devyani CHS’s extension records on MahaRERA (PM1330002500168), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Devyani CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1330002500168
- Status
- Registered and active
- Builder
- Shree Swami Sanket Enterprises
- Location
- Naupada, Thane · 400602
- Project type
- Mixed
- Registered on
- 30 Jun 2025
- Completion date at registration
- May 2028
- Latest completion date
- September 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 28
- Sold or booked
- 17%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Devyani CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Proposed Building | 100% | 79% | 15% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Proposed Building: covers 7 floors
Latest CC order on MahaRERA: dated 02/12/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Devyani CHS every 1–2 months.
Devyani CHS: buildings, flats and land, as filed on MahaRERA
- Buildings: Proposed Building (10 floors, 39 units)
- Car parking: 18 covered
- Land: 577 sq m (about 0.1 acres) · sanctioned built-up 2,377 sq m
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Devyani CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Devyani CHS: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Devyani CHS
What is the possession date of Devyani CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Devyani CHS in Naupada, Thane is 30 September 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Devyani CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Devyani CHS's builder has filed on MahaRERA, the official one, is 30 September 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Devyani CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Devyani CHS in Naupada, Thane is PM1330002500168.
Is Devyani CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS is registered as PM1330002500168 and its status is "Registered and active".
What is the current construction status of Devyani CHS? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Proposed Building is 79% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.
Does Devyani CHS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Devyani CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS is registered on MahaRERA as PM1330002500168, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Devyani CHS?
Devyani CHS is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Devyani CHS?
For a flat in Devyani CHS (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Devyani CHS received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS is still under construction, with 30 September 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Devyani CHS a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS is a redevelopment: 27 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Devyani CHS uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Devyani CHS was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Devyani CHS's possession date changes?
The latest dates are on Devyani CHS's MahaRERA page (PM1330002500168). GharKundli's Kundli Watch sends a free WhatsApp update on Devyani CHS every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Devyani CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS has one building filed: Proposed Building with 10 floors and 39 units.
How much parking does Devyani CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered car parking spaces for Devyani CHS.
How big is the land of Devyani CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS stands on 577 sq m of land (about 0.1 acres), with 2,377 sq m of sanctioned built-up area.
What are the reviews of Devyani CHS?
Google Maps has reviews of Devyani CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Devyani CHS?
Devyani CHS by Shree Swami Sanket Enterprises is in Naupada, Thane, pincode 400602, Maharashtra, and is registered on MahaRERA as PM1330002500168, per GharKundli's check of MahaRERA records. GharKundli lists all 258 MahaRERA projects in Naupada (400602).
How many flats are in Devyani CHS, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS has 28 homes in 1 tower registered on MahaRERA, and 17% of them are sold or booked.
When was Devyani CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Devyani CHS was registered on MahaRERA on 30 June 2025. GharKundli did not find a title report on the land on file there.
Does Devyani CHS have any legal issues or court cases?
No court cases are listed for Devyani CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Devyani CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Swami Sanket Enterprises.
Check it yourself on MahaRERA
- How to check the possession date of Devyani CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Naupada (400602)
- Parvati Niwas
- Rivanta
- Ekatva Crescent
- Pitruchhaya
- Navyug Co.Op.Hsg.Limited
- Asavari Co Op HSG Soc LTD
- The Lake Corner
- Platinum Square
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.