by Magestic premises private limited (Nandivardhan) · Village Panchpakadi, Thane 400602Also near Charai, Naupada, Thane West

What’s in the report? →

Possession date of Mohandeep (MahaRERA PM1330002500575): 15 October 2028, moved from 15 June 2027 (12 months later). It has 22 homes, 20% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1330002500575, and currently active. Its completion date has moved from June 2027 to October 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for PM1330002500575, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Mohandeep?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mohandeep has moved

  1. 15 June 2027

    Completion date given when the project was registered

  2. 15 June 2028

    Extended at the builder's request (MahaRERA application EA04062621237)

  3. 15 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Mohandeep’s extension records on MahaRERA (PM1330002500575), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mohandeep

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1330002500575
Status
Registered and active
Builder
Magestic premises private limited
Location
Village Panchpakadi, Thane · 400602
Project type
Mixed
Registered on
14 Aug 2025
Completion date at registration
June 2027
Latest completion date
October 2028
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
22
Sold or booked
20%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Mohandeep, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BLISS VIEW80%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • BLISS VIEW: covers 15 floors

Latest CC order on MahaRERA: dated 09/05/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mohandeep every 1–2 months.

Mohandeep: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Nandivardhan Constructions (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 7 months); 7 still being built, 1 past the promised date (typically 64 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Mohandeep →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mohandeep: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mohandeep

What is the possession date of Mohandeep?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mohandeep in Village Panchpakadi, Thane is 15 October 2028 — 12 months later than 15 June 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Mohandeep?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mohandeep's builder has filed on MahaRERA, the official one, is 15 October 2028, already 12 months later than the 15 June 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mohandeep extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep's builder applied to MahaRERA to extend the completion date once: to 15 June 2028. MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Mohandeep?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mohandeep in Village Panchpakadi, Thane is PM1330002500575.

Is Mohandeep registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep is registered as PM1330002500575 and its status is "Registered and active".

What is the current construction status of Mohandeep? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLISS VIEW is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Mohandeep have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mohandeep safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep is registered on MahaRERA as PM1330002500575, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mohandeep?

Mohandeep is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mohandeep?

For a flat in Mohandeep (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Mohandeep received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep is still under construction, with 15 October 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Mohandeep a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep is a redevelopment: 18 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Mohandeep uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mohandeep was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mohandeep's possession date changes?

The latest dates are on Mohandeep's MahaRERA page (PM1330002500575). GharKundli's Kundli Watch sends a free WhatsApp update on Mohandeep every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mohandeep have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep has one building filed: BLISS VIEW with 15 floors and 33 units.

How much parking does Mohandeep have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 30 covered car parking spaces for Mohandeep.

How big is the land of Mohandeep?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep stands on 665 sq m of land (about 0.2 acres), with 3,144 sq m of sanctioned built-up area.

What is the track record of Mohandeep's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandivardhan Constructions (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 7 months); 7 still being built, 1 past the promised date (typically 64 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Mohandeep?

Google Maps has reviews of Mohandeep written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mohandeep?

Mohandeep by Magestic premises private limited (Nandivardhan) is in Village Panchpakadi, Thane, pincode 400602 (near Charai, Naupada, Thane West), Maharashtra, and is registered on MahaRERA as PM1330002500575, per GharKundli's check of MahaRERA records. GharKundli lists all 258 MahaRERA projects in Naupada (400602).

How many flats are in Mohandeep, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep has 22 homes in 1 tower registered on MahaRERA, and 20% of them are sold or booked.

When was Mohandeep registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mohandeep was registered on MahaRERA on 14 August 2025. GharKundli did not find a title report on the land on file there.

Does Mohandeep have any legal issues or court cases?

No court cases are listed for Mohandeep on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Mohandeep?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Magestic premises private limited, the company Nandivardhan files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Thane

All 258 projects in Naupada (400602) →

Other projects by Magestic premises private limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.