GLR Siddhivinayak Apartment
by GLR Construction & Infraprojects · Nirmal Nagar, Thane 421601Registered on MahaRERA as “SIDDHIVINAYAK APARTMENT”
What’s in the report? →Possession date of GLR Siddhivinayak Apartment (MahaRERA P51700080597): 31 July 2026, and it has already passed. It has 12 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700080597. Status: Lapsed (registration period ended). Its completion date is now July 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51700080597, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about GLR Siddhivinayak Apartment?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of GLR Siddhivinayak Apartment has moved
31 March 2026
Completion date given when the project was registered
31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GLR Siddhivinayak Apartment’s extension records on MahaRERA (P51700080597), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GLR Siddhivinayak Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700080597
- Status
- Lapsed (registration period ended)
- Builder
- GLR Construction & Infraprojects
- Location
- Nirmal Nagar, Thane · 421601
- Project type
- Residential / Group Housing
- Registered on
- 17 Jun 2025
- Completion date at registration
- March 2026
- Latest completion date
- July 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 12
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GLR Siddhivinayak Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SIDDHIVINAYAK APARTMENT | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GLR Siddhivinayak Apartment every 1–2 months.
GLR Siddhivinayak Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: SIDDHIVINAYAK APARTMENT (5 floors)
- Land: 443 sq m (about 0.1 acres) · sanctioned built-up 443 sq m
- Boundaries filed include: INTERNAL LAYOUT ROAD
- Land, as filed: 151/1/151/2/202/1/202/2 PLOT NO 49
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GLR Siddhivinayak Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GLR Siddhivinayak Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about GLR Siddhivinayak Apartment
What is the possession date of GLR Siddhivinayak Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GLR Siddhivinayak Apartment in Nirmal Nagar, Thane is 31 July 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for GLR Siddhivinayak Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GLR Siddhivinayak Apartment's builder has filed on MahaRERA, the official one, is 31 July 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of GLR Siddhivinayak Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GLR Siddhivinayak Apartment in Nirmal Nagar, Thane is P51700080597.
Is GLR Siddhivinayak Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment is registered as P51700080597 and its status is "Lapsed (registration period ended)".
What is the current construction status of GLR Siddhivinayak Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SIDDHIVINAYAK APARTMENT is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does GLR Siddhivinayak Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is GLR Siddhivinayak Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment is registered on MahaRERA as P51700080597, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in GLR Siddhivinayak Apartment?
GLR Siddhivinayak Apartment isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in GLR Siddhivinayak Apartment?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in GLR Siddhivinayak Apartment: gharkundli.com/tools/property-cost-calculator
Has GLR Siddhivinayak Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for GLR Siddhivinayak Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has GLR Siddhivinayak Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for GLR Siddhivinayak Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if GLR Siddhivinayak Apartment's possession date changes?
The latest dates are on GLR Siddhivinayak Apartment's MahaRERA page (P51700080597). GharKundli's Kundli Watch sends a free WhatsApp update on GLR Siddhivinayak Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GLR Siddhivinayak Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment has one building filed: SIDDHIVINAYAK APARTMENT with 5 floors.
How big is the land of GLR Siddhivinayak Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment stands on 443 sq m of land (about 0.1 acres), with 443 sq m of sanctioned built-up area.
What are the reviews of GLR Siddhivinayak Apartment?
Google Maps has reviews of GLR Siddhivinayak Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of GLR Siddhivinayak Apartment?
GLR Siddhivinayak Apartment by GLR Construction & Infraprojects is in Nirmal Nagar, Thane, pincode 421601, Maharashtra, and is registered on MahaRERA as P51700080597, per GharKundli's check of MahaRERA records. Its boundaries filed there include INTERNAL LAYOUT ROAD. Its land is filed as 151/1/151/2/202/1/202/2 PLOT NO 49. GharKundli lists all 184 MahaRERA projects in Shahapur (421601).
How many flats are in GLR Siddhivinayak Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment has 12 homes in 1 tower registered on MahaRERA.
When was GLR Siddhivinayak Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GLR Siddhivinayak Apartment was registered on MahaRERA on 17 June 2025. GharKundli did not find a title report on the land on file there.
Does GLR Siddhivinayak Apartment have any legal issues or court cases?
No court cases are listed for GLR Siddhivinayak Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of GLR Siddhivinayak Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GLR Construction & Infraprojects.
Check it yourself on MahaRERA
- How to check the possession date of GLR Siddhivinayak Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Shahapur
- Aghav Resideny
- The White Villas
- The White Villas Kasara Phase 2
- Prem Narayan Residency
- Visava
- Sai Anand Apartment
- Chintamani Habitat (Fortuna Bungalow)
- Mirador Utsav Phase 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.