Possession date of Miraya Trinity - Eternity (MahaRERA P51700080732): 15 April 2030. It has 178 homes, 42% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700080732, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700080732, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Miraya Trinity - Eternity?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Miraya Trinity - Eternity has moved

  1. 15 December 2029

    Completion date given when the project was registered

  2. 15 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Miraya Trinity - Eternity’s extension records on MahaRERA (P51700080732), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Miraya Trinity - Eternity

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700080732
Status
Registered and active
Builder
MEXTECH PROPERTY DEVELOPERS LLP
Location
Majiwade, Thane · 400601
Project type
Residential / Group Housing
Registered on
30 Jun 2025
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
178
Sold or booked
42%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Miraya Trinity - Eternity, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No 5 Miraya Eternity100%25%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building No 5 Miraya Eternity: covers Lower Ground Floor, Ground Floor. 3 Podium Floor, Amenity-Stilt Floor + 38 Floors

Latest CC order on MahaRERA: dated 28/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Miraya Trinity - Eternity every 1–2 months.

Miraya Trinity - Eternity: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building No 5 Miraya Eternity (44 floors, 178 units)
  • Car parking: 251 covered, 61 open
  • Land: 22,695 sq m (about 5.6 acres) · sanctioned built-up 18,358 sq m · recreational space 5,745 sq m
  • Boundaries filed include: Neelkanth Palm Complex, Entrance Road Of Neelkanth Palms
  • Land, as filed: S No. 146/1, 149/3, 154/3, 412/1, 414/1/C/1 & 414/1/C/2 Sector-4, Mouje-Majiwada
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Nandivardhan Constructions (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 7 months); 7 still being built, 1 past the promised date (typically 64 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Miraya Trinity - Eternity →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Miraya Trinity - Eternity: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Miraya Trinity - Eternity

What is the possession date of Miraya Trinity - Eternity?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Miraya Trinity - Eternity in Majiwade, Thane is 15 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Miraya Trinity - Eternity?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Miraya Trinity - Eternity's builder has filed on MahaRERA, the official one, is 15 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Miraya Trinity - Eternity?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Miraya Trinity - Eternity in Majiwade, Thane is P51700080732.

Is Miraya Trinity - Eternity registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity is registered as P51700080732 and its status is "Registered and active".

What is the current construction status of Miraya Trinity - Eternity? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No 5 Miraya Eternity is 25% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Miraya Trinity - Eternity have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Miraya Trinity - Eternity safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity is registered on MahaRERA as P51700080732, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Miraya Trinity - Eternity?

Miraya Trinity - Eternity is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Miraya Trinity - Eternity?

For a flat in Miraya Trinity - Eternity (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Miraya Trinity - Eternity received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity is still under construction, with 15 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Miraya Trinity - Eternity uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Miraya Trinity - Eternity was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Miraya Trinity - Eternity's possession date changes?

The latest dates are on Miraya Trinity - Eternity's MahaRERA page (P51700080732). GharKundli's Kundli Watch sends a free WhatsApp update on Miraya Trinity - Eternity every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Miraya Trinity - Eternity have?

According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity has one building filed: Building No 5 Miraya Eternity with 44 floors and 178 units.

How much parking does Miraya Trinity - Eternity have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 251 covered and 61 open car parking spaces for Miraya Trinity - Eternity.

How big is the land of Miraya Trinity - Eternity?

According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity stands on 22,695 sq m of land (about 5.6 acres), with 18,358 sq m of sanctioned built-up area and 5,745 sq m of recreational open space.

What is the track record of Miraya Trinity - Eternity's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandivardhan Constructions (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 7 months); 7 still being built, 1 past the promised date (typically 64 months late); 2 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Miraya Trinity - Eternity?

Google Maps has reviews of Miraya Trinity - Eternity written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Miraya Trinity - Eternity?

Miraya Trinity - Eternity by MEXTECH PROPERTY DEVELOPERS LLP (Nandivardhan) is in Majiwade, Thane, pincode 400601 (near Dhokali, Badlapur, Naupada), Maharashtra, and is registered on MahaRERA as P51700080732, per GharKundli's check of MahaRERA records. Its boundaries filed there include Neelkanth Palm Complex, Entrance Road Of Neelkanth Palms. Its land is filed as S No. 146/1, 149/3, 154/3, 412/1, 414/1/C/1 & 414/1/C/2 Sector-4, Mouje-Majiwada. GharKundli lists all 178 MahaRERA projects in Thane (400601).

How many flats are in Miraya Trinity - Eternity, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity has 178 homes in 1 tower registered on MahaRERA, and 42% of them are sold or booked.

When was Miraya Trinity - Eternity registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Miraya Trinity - Eternity was registered on MahaRERA on 30 June 2025. GharKundli did not find a title report on the land on file there.

Does Miraya Trinity - Eternity have any legal issues or court cases?

No court cases are listed for Miraya Trinity - Eternity on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Miraya Trinity - Eternity?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MEXTECH PROPERTY DEVELOPERS LLP, the company Nandivardhan files this project under, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2030 in Thane →

Other projects in Thane (400601)

All 178 projects in Thane (400601) →

Other projects by MEXTECH PROPERTY DEVELOPERS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.