TATVA
by GITANJALI INFRATECH LIMITED · Borivali East, MumbaiAlso near Borivali West, Daulat Nagar, Kandivali West
Possession date of TATVA: 31 December 2019, moved from 31 December 2018 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800004498. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2019) has passed.
What do you want to know about TATVA?
GharKundli’s full report on TATVA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the December 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800004498
- Status
- Lapsed (registration period ended)
- Builder
- GITANJALI INFRATECH LIMITED
- Location
- Borivali East, Mumbai · 400066
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2019
- Delay so far
- 12 months
- Homes
- 155
- Towers
- 2
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of TATVA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Prayyan | 100% | 100% | 80% | 40% |
| Urja | 100% | 100% | 100% | 40% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TATVA every month.
TATVA: buildings, flats and land, as filed on MahaRERA
- Buildings: Prayyan (26 floors) · Urja (25 floors)
- Land: 7,938 sq m (about 2.0 acres) · sanctioned built-up 18,830 sq m · recreational space 1,535 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of TATVA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TATVA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TATVA
What is the possession date of TATVA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TATVA in Borivali East, Mumbai is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for TATVA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TATVA's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of TATVA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TATVA in Borivali East, Mumbai is P51800004498.
Is TATVA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TATVA is registered as P51800004498 and its status is "Lapsed (registration period ended)".
What is the construction status of TATVA?
According to GharKundli's check of MahaRERA records (updated November 2026), TATVA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does TATVA have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is TATVA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), TATVA is registered on MahaRERA as P51800004498, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TATVA's possession date changes?
The latest dates are on TATVA's MahaRERA page (P51800004498). GharKundli's Kundli Watch sends a free WhatsApp update on TATVA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TATVA have?
According to GharKundli's check of MahaRERA records (updated November 2026), TATVA has 2 buildings filed: Prayyan with 26 floors; Urja with 25 floors.
How big is the land of TATVA?
According to GharKundli's check of MahaRERA records (updated November 2026), TATVA stands on 7,938 sq m of land (about 2.0 acres), with 18,830 sq m of sanctioned built-up area and 1,535 sq m of recreational open space.
Where can I read reviews of TATVA?
Google Maps has reviews of TATVA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TATVA?
TATVA by GITANJALI INFRATECH LIMITED is in Borivali East, Mumbai (pincode 400066), near Borivali West, Daulat Nagar, Kandivali West, Maharashtra, and is registered on MahaRERA as P51800004498, per GharKundli's check of MahaRERA records.
How many homes are in TATVA?
According to GharKundli's check of MahaRERA records (updated November 2026), TATVA has 155 homes in 2 towers registered on MahaRERA.
When was TATVA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TATVA was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on TATVA?
No court cases are listed for TATVA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of TATVA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GITANJALI INFRATECH LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of TATVA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400066
- Rustomjee Summit
- RAJENDRA NAGAR SWAGAT CHSL
- RAJENDRA NAGAR OMSAI CO-OPERATIVE HOUSING SOCIETY LIMITED
- MEGH MAHAL CHSL
- PARSHURAM HEIGHTS
- DTG ASHFORD
- H. Rishabraj AER
- Paras Darshan
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.