Regency Business Park Phase II

by REGENCY SHELTERS LLP · Sandozbaugh, Thane 400607Also near One Hiranandani Park, Kolshet, brahmand

What’s in the report? →

Possession date of Regency Business Park Phase II (MahaRERA PC1331012502970): 30 April 2028. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PC1331012502970, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PC1331012502970, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Regency Business Park Phase II?

5 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Regency Business Park Phase II has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Regency Business Park Phase II’s extension records on MahaRERA (PC1331012502970), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Regency Business Park Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
PC1331012502970
Status
Registered and active
Builder
REGENCY SHELTERS LLP
Location
Sandozbaugh, Thane · 400607
Project type
Commercial
Registered on
18 Mar 2026
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
2%
Towers
1
Complaints on MahaRERA
0
Court cases listed
5
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Regency Business Park Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No. 5100%100%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building No. 5: covers 7 floors

Latest CC order on MahaRERA: dated 26/08/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Regency Business Park Phase II every 1–2 months.

Regency Business Park Phase II: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Regency Shelters (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 1 months); 5 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Regency Business Park Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Regency Business Park Phase II: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Regency Business Park Phase II

What is the possession date of Regency Business Park Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Regency Business Park Phase II in Sandozbaugh, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Regency Business Park Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Regency Business Park Phase II's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Regency Business Park Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Regency Business Park Phase II in Sandozbaugh, Thane is PC1331012502970.

Is Regency Business Park Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II is registered as PC1331012502970 and its status is "Registered and active".

What is the current construction status of Regency Business Park Phase II? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No. 5 is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Regency Business Park Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Regency Business Park Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II is registered on MahaRERA as PC1331012502970, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Regency Business Park Phase II?

Regency Business Park Phase II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Regency Business Park Phase II?

For a flat in Regency Business Park Phase II (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Regency Business Park Phase II received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Regency Business Park Phase II uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Regency Business Park Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Regency Business Park Phase II have other wings or phases?

Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: REGENCY BUSINESS PARK PHASE I (P51700053811, possession 30 Apr 2027); Regency Business Park Phase III (PR1331012502818, possession 30 Oct 2028); Regency Business Park Phase IV (PC1331012502955, possession 30 Apr 2028); Regency Business Park Phase V (PC1334042601414, possession 30 Sep 2028). Check that your agreement names the registration of your own wing.

How can I get updates if Regency Business Park Phase II's possession date changes?

The latest dates are on Regency Business Park Phase II's MahaRERA page (PC1331012502970). GharKundli's Kundli Watch sends a free WhatsApp update on Regency Business Park Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Regency Business Park Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II has one building filed: Building No. 5 with 7 floors and 191 units.

How much parking does Regency Business Park Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 121 covered car parking spaces for Regency Business Park Phase II.

How big is the land of Regency Business Park Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II stands on 38,089 sq m of land (about 9.4 acres), with 10,168 sq m of sanctioned built-up area and 1,361 sq m of recreational open space.

What is the track record of Regency Business Park Phase II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Shelters (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 1 months); 5 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Regency Business Park Phase II?

Google Maps has reviews of Regency Business Park Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Regency Business Park Phase II?

Regency Business Park Phase II by REGENCY SHELTERS LLP is in Sandozbaugh, Thane, pincode 400607 (near One Hiranandani Park, Kolshet, brahmand), Maharashtra, and is registered on MahaRERA as PC1331012502970, per GharKundli's check of MahaRERA records. GharKundli lists all 218 MahaRERA projects in Sandozbaugh (400607).

How many flats are in Regency Business Park Phase II, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II has 0 homes in 1 tower registered on MahaRERA, and 2% of them are sold or booked.

When was Regency Business Park Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Regency Business Park Phase II was registered on MahaRERA on 18 March 2026. GharKundli did not find a title report on the land on file there.

Does Regency Business Park Phase II have any legal issues or court cases?

5 court cases are listed for Regency Business Park Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Regency Business Park Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is REGENCY SHELTERS LLP, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Sandozbaugh (400607)

All 218 projects in Sandozbaugh (400607) →

Other projects by REGENCY SHELTERS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.